IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Springbrook | Date: 6/19/2014 | Project No. |
| HVAC system replacement | County: | GUTHRIE | Time: 11:00 a.m. | 14-04-39-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $100,000.00 | Contractor: | Lemke Repair | Hymbaugh Construction | Climate Solutions, Inc. | |||||||||
| Funding Source: 100% REAP Land Management, | 406 N 1st St | 821 Quiet Harbor | 1217 E Anthony St PO Box 754 | ||||||||||
| Guthrie Center IA 50115 | Creston IA 50801 | Carroll IA 51401 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 641-747-2014 | 641-340-0232 | 712-792-8959 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | RUUD UGTC-10ERBJS DOWNFLOW 95+ LP FURNACE | 2 | Each | $1,333.80 | $2,667.60 | $3,000.00 | $6,000.00 | $4,071.59 | $8,143.18 | ||||
| 2 | RUUD UARL-038JEZ 16 SEER 410A 2-STAGE AC | 9 | Each | $2,046.60 | $18,419.40 | $2,000.00 | $18,000.00 | $1,819.20 | $16,372.80 | ||||
| 3 | RUUD UGRC-10EZAJS UPFLOW 95+ LP FURNACE | 5 | Each | $1,333.80 | $6,669.00 | $3,000.00 | $15,000.00 | $4,071.59 | $20,357.95 | ||||
| 4 | RUUD UARL-060JEZ 16 SEER 410A 2-STAGE AC | 5 | Each | $2,728.35 | $13,641.75 | $2,000.00 | $10,000.00 | $2,424.00 | $12,120.00 | ||||
| 5 | RUUD UGRC-07EMAES UPFLOW 95+ LP FURNACE | 7 | Each | $1,080.00 | $7,560.00 | $3,000.00 | $21,000.00 | $4,071.59 | $28,501.13 | ||||
| 6 | ASPEN CC36B34-175L-101 R410A CASED COIL | 9 | Each | $418.50 | $3,766.50 | $1,000.00 | $9,000.00 | $310.00 | $2,790.00 | ||||
| 7 | ASPEN CC60B34-210L-101 R410A CASED COIL | 5 | Each | $500.85 | $2,504.25 | $1,000.00 | $5,000.00 | $371.00 | $1,855.00 | ||||
| 8 | 50' LINESET, PAD, WHIP, THERMOSTAT | 14 | Each | $394.20 | $5,518.80 | $500.00 | $7,000.00 | $290.00 | $4,060.00 | ||||
| 9 | MISC GAS FITTINGS, SHEET METAL, PARTS | 1 | L.S. | $13,041.00 | $13,041.00 | $5,000.00 | $5,000.00 | $5,040.00 | $5,040.00 | ||||
| 10 | MOBILIZATION | 1 | L.S. | $11,200.00 | $11,200.00 | $3,000.00 | $3,000.00 | $7,350.00 | $7,350.00 | ||||
| $84,988.30 | $99,000.00 | $106,590.06 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $100,000.00 | Contractor: | Proctor Mechanical Corporation | |||||||||||
| Funding Source: 100% REAP Land Management, | 1100 Hoak Dr | ||||||||||||
| West Des Moines IA 50265 | |||||||||||||
| Plan Sets Requested: 3 | Quantities | 515-288-2251 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | RUUD UGTC-10ERBJS DOWNFLOW 95+ LP FURNACE | 2 | Each | $2,108.00 | $4,216.00 | $0.00 | $0.00 | ||||||
| 2 | RUUD UARL-038JEZ 16 SEER 410A 2-STAGE AC | 9 | Each | $2,204.00 | $19,836.00 | $0.00 | $0.00 | ||||||
| 3 | RUUD UGRC-10EZAJS UPFLOW 95+ LP FURNACE | 5 | Each | $2,002.00 | $10,010.00 | $0.00 | $0.00 | ||||||
| 4 | RUUD UARL-060JEZ 16 SEER 410A 2-STAGE AC | 5 | Each | $2,874.00 | $14,370.00 | $0.00 | $0.00 | ||||||
| 5 | RUUD UGRC-07EMAES UPFLOW 95+ LP FURNACE | 7 | Each | $1,827.00 | $12,789.00 | $0.00 | $0.00 | ||||||
| 6 | ASPEN CC36B34-175L-101 R410A CASED COIL | 9 | Each | $438.00 | $3,942.00 | $0.00 | $0.00 | ||||||
| 7 | ASPEN CC60B34-210L-101 R410A CASED COIL | 5 | Each | $489.00 | $2,445.00 | $0.00 | $0.00 | ||||||
| 8 | 50' LINESET, PAD, WHIP, THERMOSTAT | 14 | Each | $2,097.00 | $29,358.00 | $0.00 | $0.00 | ||||||
| 9 | MISC GAS FITTINGS, SHEET METAL, PARTS | 1 | L.S. | $18,928.00 | $18,928.00 | $0.00 | $0.00 | ||||||
| 10 | MOBILIZATION | 1 | L.S. | $6,880.00 | $6,880.00 | $0.00 | $0.00 | ||||||
| $122,774.00 | $0.00 | $0.00 | |||||||||||