IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Yellow River State Forest | Date: 5/22/2014 | Project No. |
| Repair Paint Creek Trail | County: | ALLAMAKEE | Time: 3:00 p.m. | 14-03-03-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $18,675.00 | Contractor: | Nick Jones Earthmoving | Strong Rock & Gravel LLC | Riehm Construction | |||||||||
| Funding Source: 75% Federal-FEMA 1, 25% REAP OS Acquisition & Development, | 1223 Peterson Hollow Dr | 721 S Front St | 2340 9th St SW | ||||||||||
| Waukon IA 52172 | Lansing IA 52151 | Waukon IA 52172 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-535-7146 | 563-880-8150 | 563-568-3314 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $500.00 | $500.00 | $500.00 | $500.00 | $3,000.00 | $3,000.00 | ||||
| 2 | Furnish & Place Contractor Furnished Fill | 1225 | C.Y. | $4.50 | $5,512.50 | $11.31 | $13,854.75 | $9.75 | $11,943.75 | ||||
| 3 | Repair Cross Trail Culvert | 1 | L.S. | $800.00 | $800.00 | $500.00 | $500.00 | $500.00 | $500.00 | ||||
| 4 | Furnish & Place Limestone Sceening Surfacing | 125 | Tons | $15.00 | $1,875.00 | $18.80 | $2,350.00 | $14.50 | $1,812.50 | ||||
| $8,687.50 | $17,204.75 | $17,256.25 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $18,675.00 | Contractor: | David Ryan Construction | Bacon Concrete, LLC | Matt Construction, Inc. | |||||||||
| Funding Source: 75% Federal-FEMA 1, 25% REAP OS Acquisition & Development, | 3566 236th Ave | 370 N Bancroft St | 203 Y Ave | ||||||||||
| Decorah IA 52101 | Postville IA 52162-0188 | Sumner IA 50674 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-735-5895 | 563-864-7602 | 563-578-8418 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $300.00 | $300.00 | $2,500.00 | $2,500.00 | $1,000.00 | $1,000.00 | ||||
| 2 | Furnish & Place Contractor Furnished Fill | 1225 | C.Y. | $13.45 | $16,476.25 | $12.00 | $14,700.00 | $15.00 | $18,375.00 | ||||
| 3 | Repair Cross Trail Culvert | 1 | L.S. | $1,200.00 | $1,200.00 | $1,600.00 | $1,600.00 | $200.00 | $200.00 | ||||
| 4 | Furnish & Place Limestone Sceening Surfacing | 125 | Tons | $15.00 | $1,875.00 | $18.00 | $2,250.00 | $20.00 | $2,500.00 | ||||
| $19,851.25 | $21,050.00 | $22,075.00 | |||||||||||
12/21/2025