IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Boone Fisheries Management Unit | Date: 4/17/2014 | Project No. |
| OSHA UPDATES | County: | BOONE | Time: 11:00 am | 13-02-08-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $35,000.00 | Contractor: | R H Grabau Construction Inc | STORY CONSTRUCTION CO | Blue Ribbon Builders | |||||||||
| Funding Source: 100% REAP Land Management, | 871 "P" Ave | 300 S. BELL AVE PO BOX 1680 | 1840 137th Lane | ||||||||||
| Boone IA 50036 | AMES IA 50010 | Earlham IA 50072 | |||||||||||
| Plan Sets Requested: 0 | Quantities | (515) 432-6935 | 515-232-4358 | 515-290-3023 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $1,200.00 | $1,200.00 | $1,600.00 | $1,600.00 | $3,725.00 | $3,725.00 | ||||
| 2 | NEW FIREWALL & FIRE RATED ASSEMBLIES | 1 | L.S. | $12,991.00 | $12,991.00 | $17,070.00 | $17,070.00 | $17,001.00 | $17,001.00 | ||||
| 3 | ELECTRICAL REWIRING AND POWER VENT | 1 | L.S. | $3,355.00 | $3,355.00 | $2,380.00 | $2,380.00 | $9,164.00 | $9,164.00 | ||||
| 4 | MOBILIZATION | 1 | L.S. | $4,590.00 | $4,590.00 | $2,850.00 | $2,850.00 | $4,500.00 | $4,500.00 | ||||
| $22,136.00 | $23,900.00 | $34,390.00 | |||||||||||
12/21/2025