| Bids For: | Location: | Lost Grove Lake WMA | Date: 4/17/2014 | Project No. |
| Parking Lot Expansion | County: | SCOTT | Time: 11:00 AM | 14-06-82-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $217,000.00 | Contractor: | BWC Excavating LC | Emery Construction Group Inc | Rittmer Inc | |||||||||
| Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | 1303 Hickory Hollow Rd | 4512 Avenue of the Cities | 2464 330th Ave | ||||||||||
| Solon IA 52333 | Moline IL 61265 | DeWitt IA 52742 | |||||||||||
| Plan Sets Requested: 10 | Quantities | 319-848-7513 | 309-797-2070 | (319) 659-3386 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilzation | 1 | L.S. | $1,500.00 | $1,500.00 | $10,000.00 | $10,000.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Excavation, Class 10 | 7463 | C.Y. | $2.00 | $14,926.00 | $4.00 | $29,852.00 | $3.25 | $24,254.75 | ||||
| 3 | Special Backfill | 1677 | Tons | $16.94 | $28,408.38 | $15.50 | $25,993.50 | $20.00 | $33,540.00 | ||||
| 4 | 7" PCC | 5304 | S.Y. | $29.00 | $153,816.00 | $27.00 | $143,208.00 | $29.50 | $156,468.00 | ||||
| 5 | Striping | 58.8 | STA. | $26.67 | $1,568.196 | $39.50 | $2,322.60 | $100.00 | $5,880.00 | ||||
| 6 | Parking Posts | 883 | L.F. | $6.50 | $5,739.50 | $6.25 | $5,518.75 | $5.00 | $4,415.00 | ||||
| 7 | Clearing and Grubbing | 1.8 | Acres | $200.00 | $360.00 | $1,000.00 | $1,800.00 | $2,500.00 | $4,500.00 | ||||
| 8 | Seed and Fertilize | 0.7 | Acres | $857.14 | $599.998 | $3,500.00 | $2,450.00 | $1,000.00 | $700.00 | ||||
| 9 | Mulch | 0.7 | Acres | $1,000.00 | $700.00 | $3,500.00 | $2,450.00 | $1,000.00 | $700.00 | ||||
| 10 | Granular Shoulders | 14 | Tons | $30.00 | $420.00 | $50.00 | $700.00 | $25.00 | $350.00 | ||||
| 11 | Silt Fence | 200 | L.F. | $0.01 | $2.00 | $3.00 | $600.00 | $4.00 | $800.00 | ||||
| 12 | Keep Right Sign | 1 | Each | $350.00 | $350.00 | $1,000.00 | $1,000.00 | $100.00 | $100.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | $1,500.00 | $1,500.00 | ||||
| $210,390.074 | $230,894.85 | $238,207.75 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $217,000.00 | Contractor: | H & H Construction & Development LLC | Hawkeye Paving Corp | Needham Excavating | |||||||||
| Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | 60559 Hwy 64 | 801 42nd Street | 17470 70th Avenue | ||||||||||
| Sabula IA 52070 | Bettendorf IA 52722 | Walcott IA 52773 | |||||||||||
| Plan Sets Requested: 10 | Quantities | 563-357-1849 | (563) 355-6834 | 563-529-5840 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilzation | 1 | L.S. | $7,400.00 | $7,400.00 | $30,000.00 | $30,000.00 | $9,935.00 | $9,935.00 | ||||
| 2 | Excavation, Class 10 | 7463 | C.Y. | $1.80 | $13,433.40 | $5.00 | $37,315.00 | $3.18 | $23,732.34 | ||||
| 3 | Special Backfill | 1677 | Tons | $16.50 | $27,670.50 | $23.00 | $38,571.00 | $16.88 | $28,307.76 | ||||
| 4 | 7" PCC | 5304 | S.Y. | $36.00 | $190,944.00 | $32.00 | $169,728.00 | $41.62 | $220,752.48 | ||||
| 5 | Striping | 58.8 | STA. | $57.82 | $3,399.816 | $35.00 | $2,058.00 | $46.80 | $2,751.84 | ||||
| 6 | Parking Posts | 883 | L.F. | $5.60 | $4,944.80 | $7.00 | $6,181.00 | $10.40 | $9,183.20 | ||||
| 7 | Clearing and Grubbing | 1.8 | Acres | $500.00 | $900.00 | $900.00 | $1,620.00 | $2,003.00 | $3,605.40 | ||||
| 8 | Seed and Fertilize | 0.7 | Acres | $1,500.00 | $1,050.00 | $2,200.00 | $1,540.00 | $988.00 | $691.60 | ||||
| 9 | Mulch | 0.7 | Acres | $1,000.00 | $700.00 | $1,100.00 | $770.00 | $468.00 | $327.60 | ||||
| 10 | Granular Shoulders | 14 | Tons | $50.00 | $700.00 | $45.00 | $630.00 | $19.90 | $278.60 | ||||
| 11 | Silt Fence | 200 | L.F. | $4.00 | $800.00 | $2.00 | $400.00 | $2.25 | $450.00 | ||||
| 12 | Keep Right Sign | 1 | Each | $400.00 | $400.00 | $200.00 | $200.00 | $800.00 | $800.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | ||||
| $255,342.516 | $294,013.00 | $305,815.82 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $217,000.00 | Contractor: | Ag & Turf Construction LLC | Valley Construction Company | Anderson Commercial Concrete Inc. | |||||||||
| Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | 4302 W 60th St | 3610 78th Ave W | 21254 N. Brady St | ||||||||||
| Davenport IA 52806 | Rock Island IL 61201 | Davenport IA 52806 | |||||||||||
| Plan Sets Requested: 10 | Quantities | 563-349-2089 | 309-787-0292 | 563-391-3281 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilzation | 1 | L.S. | $9,875.00 | $9,875.00 | $16,800.00 | $16,800.00 | $14,500.00 | $14,500.00 | ||||
| 2 | Excavation, Class 10 | 7463 | C.Y. | $2.18 | $16,269.34 | $4.80 | $35,822.40 | $13.00 | $97,019.00 | ||||
| 3 | Special Backfill | 1677 | Tons | $22.48 | $37,698.96 | $24.00 | $40,248.00 | $28.00 | $46,956.00 | ||||
| 4 | 7" PCC | 5304 | S.Y. | $43.57 | $231,095.28 | $43.60 | $231,254.40 | $43.50 | $230,724.00 | ||||
| 5 | Striping | 58.8 | STA. | $55.55 | $3,266.34 | $40.00 | $2,352.00 | $45.00 | $2,646.00 | ||||
| 6 | Parking Posts | 883 | L.F. | $7.19 | $6,348.77 | $6.25 | $5,518.75 | $10.00 | $8,830.00 | ||||
| 7 | Clearing and Grubbing | 1.8 | Acres | $575.00 | $1,035.00 | $800.00 | $1,440.00 | $7,700.00 | $13,860.00 | ||||
| 8 | Seed and Fertilize | 0.7 | Acres | $1,180.00 | $826.00 | $2,000.00 | $1,400.00 | $4,400.00 | $3,080.00 | ||||
| 9 | Mulch | 0.7 | Acres | $825.00 | $577.50 | $800.00 | $560.00 | $935.00 | $654.50 | ||||
| 10 | Granular Shoulders | 14 | Tons | $82.50 | $1,155.00 | $45.00 | $630.00 | $31.00 | $434.00 | ||||
| 11 | Silt Fence | 200 | L.F. | $4.03 | $806.00 | $2.50 | $500.00 | $6.00 | $1,200.00 | ||||
| 12 | Keep Right Sign | 1 | Each | $460.00 | $460.00 | $300.00 | $300.00 | $800.00 | $800.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $2,875.00 | $2,875.00 | $3,000.00 | $3,000.00 | $6,500.00 | $6,500.00 | ||||
| $312,288.19 | $339,825.55 | $427,203.50 | |||||||||||