IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Macbride | Date: 3/24/2016 | Project No. |
| Coralville Boat Ramp Sidewalk | County: | JOHNSON | Time: 3:00 p.m. | 15-06-52-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $18,000.00 | Contractor: | Midwest Concrete Inc. | Weaver's Inc. | Triple B Construction Corporation | |||||||||
| Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | 16869 Navarre Ct | 1524 Highway 130 | 2272 Spicer Ave | ||||||||||
| Peosta IA 52068 | Tipton IA 52772 | Wilton IA 52778 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-580-9848 | 563-886-6556 | 319-631-0320 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $500.00 | $500.00 | $1,175.00 | $1,175.00 | $2,000.00 | $2,000.00 | ||||
| 2 | Site Preparation | 1 | L.S. | $500.00 | $500.00 | $3,850.00 | $3,850.00 | $2,500.00 | $2,500.00 | ||||
| 3 | Fill Material | 40 | C.Y. | $40.00 | $1,600.00 | $49.00 | $1,960.00 | $55.00 | $2,200.00 | ||||
| 4 | Crushed Stone, Class A | 30 | Tons | $30.00 | $900.00 | $32.50 | $975.00 | $30.00 | $900.00 | ||||
| 5 | PCCSidewalk, 6”DepthReinforced | 102 | S.Y. | $45.00 | $4,590.00 | $73.00 | $7,446.00 | $62.00 | $6,324.00 | ||||
| 6 | Handrail | 116 | L.F. | $60.34 | $6,999.44 | $26.90 | $3,120.40 | $60.00 | $6,960.00 | ||||
| $15,089.44 | $18,526.40 | $20,884.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $18,000.00 | Contractor: | Curtis Contracting Corp. | Hymbaugh Construction | ||||||||||
| Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | PO Box 341 | 821 Quiet Harbor | |||||||||||
| Ely IA 52227 | Creston IA 50801 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-848-5710 | 641-340-0232 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $2,520.00 | $2,520.00 | $0.00 | |||||
| 2 | Site Preparation | 1 | L.S. | $6,800.00 | $6,800.00 | $4,000.00 | $4,000.00 | $0.00 | |||||
| 3 | Fill Material | 40 | C.Y. | $17.00 | $680.00 | $60.00 | $2,400.00 | $0.00 | |||||
| 4 | Crushed Stone, Class A | 30 | Tons | $45.00 | $1,350.00 | $70.00 | $2,100.00 | $0.00 | |||||
| 5 | PCCSidewalk, 6”DepthReinforced | 102 | S.Y. | $50.00 | $5,100.00 | $80.00 | $8,160.00 | $0.00 | |||||
| 6 | Handrail | 116 | L.F. | $43.50 | $5,046.00 | $50.00 | $5,800.00 | $0.00 | |||||
| $22,476.00 | $24,980.00 | $0.00 | |||||||||||