IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Union Grove | Date: 4/21/2016 | Project No. |
| Hydraulic Dredging | County: | TAMA | Time: 11:00 a.m. | 14-05-86-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,130,000.00 | Contractor: | Southwind Construction Corp | Magruder Construction Co. Inc. | Dubuque Barge & Fleeting Service Co. dba | |||||||||
| Funding Source: 100% Lake Restoration, | 14649 Hwy 41 N Suite 100 | 243 West Outer Rd | Newt Marine Service 5 Jones St | ||||||||||
| Evansville IN 47725 | Eolia MO 63344 | Dubuque IA 52001 | |||||||||||
| Plan Sets Requested: 1 | Quantities | 812-867-7220 | 573-485-2161 | 563-557-1855 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DREDGING, HYDRAULIC | 249000 | C.Y. | $3.97 | $988,530.00 | $3.70 | $921,300.00 | $7.55 | $1,879,950.00 | ||||
| 2 | IN-LAKE SILT DAM CROSSING | 1 | L.S. | $0.00 | $0.00 | $42,000.00 | $42,000.00 | $20,000.00 | $20,000.00 | ||||
| 3 | Control Structure | 1 | L.S. | $8,272.43 | $8,272.43 | $70,000.00 | $70,000.00 | $20,000.00 | $20,000.00 | ||||
| 4 | Mobilization | 1 | L.S. | $352,817.51 | $352,817.51 | $625,000.00 | $625,000.00 | $311,000.00 | $311,000.00 | ||||
| $1,349,619.94 | $1,658,300.00 | $2,230,950.00 | |||||||||||
| Alternate | |||||||||||||
| 5 | Dredging, Hydraulic | 18500 | C.Y. | $4.07 | $75,295.00 | $11.15 | $206,275.00 | $9.25 | $171,125.00 | ||||
| $1,424,914.94 | $1,864,575.00 | $2,402,075.00 | |||||||||||