IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Union Grove  Date: 5/1/2014  Project No.  
  Cabin Road  County:   TAMA  Time: 3:00 p.m.  14-05-86-02

 

 
1
2
3
Estimated Cost: $55,220.00
Contractor: 
McGee Concrete and LandscapingHill ContractingBoulder Contracting, LLC
Funding Source: 100% Infrastructure 2015, 219 N Fryer St
20904 215th Ave
25789 N Ave
Russell IA  50238Leon IA  50144Grundy Center IA  50638
Plan Sets Requested: 0
Quantities
641-203-0721641-446-6428319-269-8680
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation141C.Y.$8.85$1,247.85 $10.00$1,410.00 $20.00$2,820.00 
2Fill Dirt From Offsite156C.Y.$26.44$4,124.64 $15.00$2,340.00 $40.00$6,240.00 
3C4 PCC Pavement483S.Y.$54.00$26,082.00 $50.00$24,150.00 $65.00$31,395.00 
4Construction Staking1L.S.$1,800.00$1,800.00 $2,000.00$2,000.00 $2,500.00$2,500.00 
5Mobilization1L.S.$1,500.00$1,500.00 $5,000.00$5,000.00 $5,000.00$5,000.00 
6Porous Concrete118S.Y.$78.48$9,260.64 $80.00$9,440.00 $95.00$11,210.00 
71" Clean Stone64Tons$28.00$1,792.00 $30.00$1,920.00 $35.00$2,240.00 
86" Standard Curb37L.F.$30.00$1,110.00 $50.00$1,850.00 $65.00$2,405.00 
9Fabric for Subsurface Drainage147S.Y.$5.63$827.61 $4.00$588.00 $3.00$441.00 
10Earth Shoulder Construction5.44STA.$386.03$2,100.003 $250.00$1,360.00 $200.00$1,088.00 
11Highway Underdrain Pipe61L.F.$5.75$350.75 $20.00$1,220.00 $40.00$2,440.00 
12Site Restoration1L.S.$2,700.00$2,700.00 $3,000.00$3,000.00 $5,000.00$5,000.00 
      $52,895.493  $54,278.00  $72,779.00 
 



 

12/21/2025