IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Hawkeye Wildlife Management Area Phase 2  Date: 11/21/2013  Project No.  
  Water Quality & Wetland Project  County:   JOHNSON  Time: 11:00 a.m.  12-06-52-07

 

 
1
2
3
Estimated Cost: $574,937.00
Contractor: 
Cole Construction Company IncDeLong Construction IncRicklefs Excavating Ltd
Funding Source: 100% Federal-Other, 24100 Queen Ave
PO Box 488
12536 Buffalo Road
Keosauqua IA  525658329Washington IA  52353Anamosa IA  52205
Plan Sets Requested: 14
Quantities
319-592-3103319-653-3334319-462-4435
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$22,000.00$22,000.00 $16,750.00$16,750.00 $100,000.00$100,000.00 
2Clearing & Grubbing2Acres$2,500.00$5,000.00 $3,270.00$6,540.00 $3,000.00$6,000.00 
3Class 10 Excavation, strip and re-use2540C.Y.$3.00$7,620.00 $2.60$6,604.00 $2.40$6,096.00 
4Berm Construction, Class 10 Excavation (Borrow Area)39126C.Y.$2.15$84,120.90 $2.50$97,815.00 $2.10$82,164.60 
510' x 10' RCBC With Top24L.F.$1,100.00$26,400.00 $1,150.00$27,600.00 $1,300.00$31,200.00 
610' x 10' Precast RCB no Top48L.F.$850.00$40,800.00 $900.00$43,200.00 $1,200.00$57,600.00 
7Sheet Piling2240S.F.$42.00$94,080.00 $42.00$94,080.00 $38.00$85,120.00 
8Curtain Walls (Precast Concrete)6.4C.Y.$700.00$4,480.00 $700.00$4,480.00 $1,500.00$9,600.00 
9Aluminum Stoplog Guides730LB.$4.11$3,000.30 $16.50$12,045.00 $10.00$7,300.00 
10Aluminum Stoplog & Aluminum Hooks700LB.$14.29$10,003.00 $15.00$10,500.00 $10.00$7,000.00 
11Geotextile - WCS & Berm600S.Y.$1.75$1,050.00 $2.70$1,620.00 $1.00$600.00 
12Rip Rap - WCS & Berm360Tons$33.00$11,880.00 $32.30$11,628.00 $31.00$11,160.00 
13P.C.C. Grout for Rip Rap - WCS & Berm71C.Y.$166.00$11,786.00 $140.00$9,940.00 $115.00$8,165.00 
14Crushed Rock Surfacing42Tons$16.50$693.00 $29.90$1,255.80 $15.00$630.00 
15Silt Fencing4620L.F.$1.65$7,623.00 $1.90$8,778.00 $1.50$6,930.00 
16Inplement Stormwater Pollution Plan1L.S.$750.00$750.00 $3,500.00$3,500.00 $1,000.00$1,000.00 
178" PCC Spillway crest with Wire652S.Y.$60.00$39,120.00 $72.60$47,335.20 $48.00$31,296.00 
18Geotextile - Spillway6125S.Y.$1.75$10,718.75 $2.70$16,537.50 $1.00$6,125.00 
19Rip Rap - Spillway3695Tons$33.00$121,935.00 $32.30$119,348.50 $30.00$110,850.00 
20P.C.C. Grout - Spillway342C.Y.$166.00$56,772.00 $162.80$55,677.60 $115.00$39,330.00 
      $559,831.95  $595,234.60  $608,166.60 
 
4
5
6
Estimated Cost: $574,937.00
Contractor: 
Connolly Construction IncTaylor Construction IncSmith Seeding Inc
Funding Source: 100% Federal-Other, 18409 N Cascade Rd
PO Box 68
7314 Columbus St
PO Box 110
219 N 1st Street
Peosta IA  52068New Vienna IA  52065Eldridge IA  52748
Plan Sets Requested: 14
Quantities
563-876-3225563-921-2315563-285-2604
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$25,000.00$25,000.00 $45,000.00$45,000.00 $45,000.00$45,000.00 
2Clearing & Grubbing2Acres$4,500.00$9,000.00 $2,500.00$5,000.00 $750.00$1,500.00 
3Class 10 Excavation, strip and re-use2540C.Y.$2.10$5,334.00 $4.00$10,160.00 $2.42$6,146.80 
4Berm Construction, Class 10 Excavation (Borrow Area)39126C.Y.$2.80$109,552.80 $2.00$78,252.00 $2.73$106,813.98 
510' x 10' RCBC With Top24L.F.$1,700.00$40,800.00 $1,500.00$36,000.00 $1,800.00$43,200.00 
610' x 10' Precast RCB no Top48L.F.$1,000.00$48,000.00 $1,050.00$50,400.00 $1,500.00$72,000.00 
7Sheet Piling2240S.F.$30.00$67,200.00 $43.00$96,320.00 $30.00$67,200.00 
8Curtain Walls (Precast Concrete)6.4C.Y.$1,500.00$9,600.00 $1,500.00$9,600.00 $1,000.00$6,400.00 
9Aluminum Stoplog Guides730LB.$8.50$6,205.00 $15.00$10,950.00 $10.00$7,300.00 
10Aluminum Stoplog & Aluminum Hooks700LB.$15.75$11,025.00 $19.00$13,300.00 $10.00$7,000.00 
11Geotextile - WCS & Berm600S.Y.$2.30$1,380.00 $3.00$1,800.00 $2.00$1,200.00 
12Rip Rap - WCS & Berm360Tons$38.00$13,680.00 $30.00$10,800.00 $28.80$10,368.00 
13P.C.C. Grout for Rip Rap - WCS & Berm71C.Y.$165.00$11,715.00 $141.00$10,011.00 $150.00$10,650.00 
14Crushed Rock Surfacing42Tons$26.25$1,102.50 $18.00$756.00 $20.90$877.80 
15Silt Fencing4620L.F.$2.00$9,240.00 $2.00$9,240.00 $2.25$10,395.00 
16Inplement Stormwater Pollution Plan1L.S.$5,500.00$5,500.00 $1,000.00$1,000.00 $8,000.00$8,000.00 
178" PCC Spillway crest with Wire652S.Y.$75.00$48,900.00 $110.00$71,720.00 $100.00$65,200.00 
18Geotextile - Spillway6125S.Y.$2.30$14,087.50 $3.00$18,375.00 $2.00$12,250.00 
19Rip Rap - Spillway3695Tons$38.00$140,410.00 $30.00$110,850.00 $28.80$106,416.00 
20P.C.C. Grout - Spillway342C.Y.$165.00$56,430.00 $141.00$48,222.00 $150.00$51,300.00 
      $634,161.80  $637,756.00  $639,217.58 
 
7
8
9
Estimated Cost: $574,937.00
Contractor: 
Miller Trucking & ExcavPETERSON CONTRACTORS INC (PCI-REINBECK)
Funding Source: 100% Federal-Other, 3033 John Deere Rd
104 Blackhawk St
Box A

Silvis IL  61282Reinbeck IA  50669  
Plan Sets Requested: 14
Quantities
(309) 755-7644319-345-2713
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$18,000.00$18,000.00 $35,000.00$35,000.00 $0.00 
2Clearing & Grubbing2Acres$7,200.00$14,400.00 $64,000.00$128,000.00 $0.00 
3Class 10 Excavation, strip and re-use2540C.Y.$1.00$2,540.00 $6.25$15,875.00 $0.00 
4Berm Construction, Class 10 Excavation (Borrow Area)39126C.Y.$3.00$117,378.00 $4.75$185,848.50 $0.00 
510' x 10' RCBC With Top24L.F.$2,200.00$52,800.00 $1,220.00$29,280.00 $0.00 
610' x 10' Precast RCB no Top48L.F.$1,400.00$67,200.00 $1,185.00$56,880.00 $0.00 
7Sheet Piling2240S.F.$48.00$107,520.00 $40.00$89,600.00 $0.00 
8Curtain Walls (Precast Concrete)6.4C.Y.$1,100.00$7,040.00 $2,500.00$16,000.00 $0.00 
9Aluminum Stoplog Guides730LB.$4.00$2,920.00 $6.25$4,562.50 $0.00 
10Aluminum Stoplog & Aluminum Hooks700LB.$34.00$23,800.00 $16.25$11,375.00 $0.00 
11Geotextile - WCS & Berm600S.Y.$1.00$600.00 $4.50$2,700.00 $0.00 
12Rip Rap - WCS & Berm360Tons$40.00$14,400.00 $42.50$15,300.00 $0.00 
13P.C.C. Grout for Rip Rap - WCS & Berm71C.Y.$205.00$14,555.00 $160.00$11,360.00 $0.00 
14Crushed Rock Surfacing42Tons$28.00$1,176.00 $42.00$1,764.00 $0.00 
15Silt Fencing4620L.F.$1.85$8,547.00 $1.95$9,009.00 $0.00 
16Inplement Stormwater Pollution Plan1L.S.$7,800.00$7,800.00 $10,000.00$10,000.00 $0.00 
178" PCC Spillway crest with Wire652S.Y.$65.00$42,380.00 $70.00$45,640.00 $0.00 
18Geotextile - Spillway6125S.Y.$1.00$6,125.00 $4.50$27,562.50 $0.00 
19Rip Rap - Spillway3695Tons$40.00$147,800.00 $42.50$157,037.50 $0.00 
20P.C.C. Grout - Spillway342C.Y.$205.00$70,110.00 $160.00$54,720.00 $0.00 
      $727,091.00  $907,514.00  $0.00 
 



 