IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Missouri River Wildlife Unit | Date: 9/18/2014 | Project No. |
Boat Ramp Construction | County: | HARRISON | Time: 11:00 a.m. | 14-04-43-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $76,000.00 | Contractor: | Carley Construction LLC | Lessard Contracting Inc | ||||||||||
Funding Source: 100% Marine Fuel Tax, | PO Box 2025 | 2300 Blvd of Champions Box 705 | |||||||||||
Council Bluffs IA 51502 | Sergeant Bluff IA 51054-0705 | ||||||||||||
Plan Sets Requested: 1 | Quantities | 712-487-3599 | 712-252-4131 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,100.00 | $2,100.00 | $33,083.00 | $33,083.00 | $0.00 | |||||
2 | Clearing & Grubbing | 1 | L.S. | $500.00 | $500.00 | $7,700.00 | $7,700.00 | $0.00 | |||||
3 | Class A Crushed Stone (Ramp Base) | 762 | Tons | $25.50 | $19,431.00 | $55.00 | $41,910.00 | $0.00 | |||||
4 | Concrete, Structural Class C Ramp- 6" | 238 | S.Y. | $85.00 | $20,230.00 | $185.00 | $44,030.00 | $0.00 | |||||
5 | Class E Revetment (RipRap) | 323 | Tons | $48.50 | $15,665.50 | $62.00 | $20,026.00 | $0.00 | |||||
6 | Excavation | 116 | C.Y. | $8.00 | $928.00 | $18.85 | $2,186.60 | $0.00 | |||||
7 | Class A Crushed Stone (Parking) | 278 | Tons | $25.50 | $7,089.00 | $37.00 | $10,286.00 | $0.00 | |||||
8 | Site Restoration | 1 | L.S. | $500.00 | $500.00 | $6,500.00 | $6,500.00 | $0.00 | |||||
$66,443.50 | $165,721.60 | $0.00 | |||||||||||
5/2/2024