IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Missouri River Fisheries Management Unit | Date: 7/24/2014 | Project No. |
Blue Lake ramp/parking | County: | MONONA | Time: 11:00 a.m. | 14-01-67-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $176,400.00 | Contractor: | Lessard Contracting Inc | L A Carlson Contracting Inc | K & L Construction Inc. | |||||||||
Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | PO Box 705 | 20984 C-43 | 501 S Ridge Rd | ||||||||||
Sergeant Bluff IA 51054-0705 | Merrill IA 51038 | Sgt Bluff IA 51054 | |||||||||||
Plan Sets Requested: 9 | Quantities | 712-252-4131 | 712-239-3195 | 712-943-2939 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $16,825.00 | $16,825.00 | $25,000.00 | $25,000.00 | $19,500.00 | $19,500.00 | ||||
2 | Tree Removal | 7 | Each | $600.00 | $4,200.00 | $2,000.00 | $14,000.00 | $700.00 | $4,900.00 | ||||
3 | Remove & Relocate Sign | 3 | Each | $250.00 | $750.00 | $500.00 | $1,500.00 | $350.00 | $1,050.00 | ||||
4 | Existing Ramp Remove & Dispose (North Ramp) | 1 | L.S. | $2,400.00 | $2,400.00 | $2,000.00 | $2,000.00 | $1,850.00 | $1,850.00 | ||||
5 | Existing Ramp Remove & Dispose (South Ramp) | 1 | L.S. | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | ||||
6 | Sawcut Asphalt Slab | 646 | L.F. | $7.50 | $4,845.00 | $5.00 | $3,230.00 | $6.00 | $3,876.00 | ||||
7 | Rain Garden | 1 | L.S. | $5,000.00 | $5,000.00 | $6,000.00 | $6,000.00 | $6,500.00 | $6,500.00 | ||||
8 | 6" HMA Pavement | 615 | Tons | $90.00 | $55,350.00 | $89.00 | $54,735.00 | $89.00 | $54,735.00 | ||||
9 | IDOT Special Backfill | 593 | Tons | $33.00 | $19,569.00 | $26.75 | $15,862.75 | $28.00 | $16,604.00 | ||||
10 | Geogrid Mat | 1883 | S.Y. | $2.10 | $3,954.30 | $2.00 | $3,766.00 | $2.00 | $3,766.00 | ||||
11 | 24" DIA. CMP Extension & FES | 1 | L.S. | $1,150.00 | $1,150.00 | $1,000.00 | $1,000.00 | $1,350.00 | $1,350.00 | ||||
12 | Pavement Striping | 1 | L.S. | $1,200.00 | $1,200.00 | $1,100.00 | $1,100.00 | $1,210.00 | $1,210.00 | ||||
13 | Class "A" Crushed Stone | 115 | Tons | $37.00 | $4,255.00 | $50.00 | $5,750.00 | $35.00 | $4,025.00 | ||||
14 | Concrete Class "C" Structural | 315 | S.Y. | $95.00 | $29,925.00 | $120.00 | $37,800.00 | $240.00 | $75,600.00 | ||||
15 | Class "D" Rip-Rap | 190 | Tons | $48.00 | $9,120.00 | $50.00 | $9,500.00 | $48.00 | $9,120.00 | ||||
16 | Seed, Fertilize, & Mulch | 1 | L.S. | $1,500.00 | $1,500.00 | $5,000.00 | $5,000.00 | $8,500.00 | $8,500.00 | ||||
$161,543.30 | $188,243.75 | $214,086.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $176,400.00 | Contractor: | Nelson & Rock Contracting | |||||||||||
Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), | 23565 Hwy K45 | ||||||||||||
Onawa IA 51040 | |||||||||||||
Plan Sets Requested: 9 | Quantities | 7124231065 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $50,000.00 | $50,000.00 | $0.00 | $0.00 | ||||||
2 | Tree Removal | 7 | Each | $1,000.00 | $7,000.00 | $0.00 | $0.00 | ||||||
3 | Remove & Relocate Sign | 3 | Each | $250.00 | $750.00 | $0.00 | $0.00 | ||||||
4 | Existing Ramp Remove & Dispose (North Ramp) | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
5 | Existing Ramp Remove & Dispose (South Ramp) | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
6 | Sawcut Asphalt Slab | 646 | L.F. | $3.00 | $1,938.00 | $0.00 | $0.00 | ||||||
7 | Rain Garden | 1 | L.S. | $3,000.00 | $3,000.00 | $0.00 | $0.00 | ||||||
8 | 6" HMA Pavement | 615 | Tons | $81.00 | $49,815.00 | $0.00 | $0.00 | ||||||
9 | IDOT Special Backfill | 593 | Tons | $40.00 | $23,720.00 | $0.00 | $0.00 | ||||||
10 | Geogrid Mat | 1883 | S.Y. | $3.00 | $5,649.00 | $0.00 | $0.00 | ||||||
11 | 24" DIA. CMP Extension & FES | 1 | L.S. | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
12 | Pavement Striping | 1 | L.S. | $1,000.00 | $1,000.00 | $0.00 | $0.00 | ||||||
13 | Class "A" Crushed Stone | 115 | Tons | $40.00 | $4,600.00 | $0.00 | $0.00 | ||||||
14 | Concrete Class "C" Structural | 315 | S.Y. | $150.00 | $47,250.00 | $0.00 | $0.00 | ||||||
15 | Class "D" Rip-Rap | 190 | Tons | $45.00 | $8,550.00 | $0.00 | $0.00 | ||||||
16 | Seed, Fertilize, & Mulch | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
$217,272.00 | $0.00 | $0.00 | |||||||||||
5/3/2024