 Bids For:  Location:   Missouri River Fisheries Management Unit  Date: 7/24/2014  Project No.  
  Blue Lake ramp/parking  County:   MONONA  Time: 11:00 a.m.  14-01-67-01

 

 
1
2
3
Estimated Cost: $176,400.00
Contractor: 
Lessard Contracting IncL A Carlson Contracting IncK & L Construction Inc.
Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), PO Box 705
20984 C-43
501 S Ridge Rd
Sergeant Bluff IA  51054-0705Merrill IA  51038Sgt Bluff IA  51054
Plan Sets Requested: 9
Quantities
712-252-4131712-239-3195712-943-2939
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$16,825.00$16,825.00 $25,000.00$25,000.00 $19,500.00$19,500.00 
2Tree Removal7Each$600.00$4,200.00 $2,000.00$14,000.00 $700.00$4,900.00 
3Remove & Relocate Sign3Each$250.00$750.00 $500.00$1,500.00 $350.00$1,050.00 
4Existing Ramp Remove & Dispose (North Ramp)1L.S.$2,400.00$2,400.00 $2,000.00$2,000.00 $1,850.00$1,850.00 
5Existing Ramp Remove & Dispose (South Ramp)1L.S.$1,500.00$1,500.00 $2,000.00$2,000.00 $1,500.00$1,500.00 
6Sawcut Asphalt Slab646L.F.$7.50$4,845.00 $5.00$3,230.00 $6.00$3,876.00 
7Rain Garden1L.S.$5,000.00$5,000.00 $6,000.00$6,000.00 $6,500.00$6,500.00 
86" HMA Pavement615Tons$90.00$55,350.00 $89.00$54,735.00 $89.00$54,735.00 
9IDOT Special Backfill593Tons$33.00$19,569.00 $26.75$15,862.75 $28.00$16,604.00 
10Geogrid Mat1883S.Y.$2.10$3,954.30 $2.00$3,766.00 $2.00$3,766.00 
1124" DIA. CMP Extension & FES1L.S.$1,150.00$1,150.00 $1,000.00$1,000.00 $1,350.00$1,350.00 
12Pavement Striping1L.S.$1,200.00$1,200.00 $1,100.00$1,100.00 $1,210.00$1,210.00 
13Class "A" Crushed Stone115Tons$37.00$4,255.00 $50.00$5,750.00 $35.00$4,025.00 
14Concrete Class "C" Structural315S.Y.$95.00$29,925.00 $120.00$37,800.00 $240.00$75,600.00 
15Class "D" Rip-Rap190Tons$48.00$9,120.00 $50.00$9,500.00 $48.00$9,120.00 
16Seed, Fertilize, & Mulch1L.S.$1,500.00$1,500.00 $5,000.00$5,000.00 $8,500.00$8,500.00 
      $161,543.30  $188,243.75  $214,086.00 
 
 
4
5
6
Estimated Cost: $176,400.00
Contractor: 
Nelson & Rock Contracting
Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), 23565 Hwy K45


Onawa IA  51040    
Plan Sets Requested: 9
Quantities
7124231065
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$50,000.00$50,000.00 $0.00 $0.00 
2Tree Removal7Each$1,000.00$7,000.00 $0.00 $0.00 
3Remove & Relocate Sign3Each$250.00$750.00 $0.00 $0.00 
4Existing Ramp Remove & Dispose (North Ramp)1L.S.$5,000.00$5,000.00 $0.00 $0.00 
5Existing Ramp Remove & Dispose (South Ramp)1L.S.$5,000.00$5,000.00 $0.00 $0.00 
6Sawcut Asphalt Slab646L.F.$3.00$1,938.00 $0.00 $0.00 
7Rain Garden1L.S.$3,000.00$3,000.00 $0.00 $0.00 
86" HMA Pavement615Tons$81.00$49,815.00 $0.00 $0.00 
9IDOT Special Backfill593Tons$40.00$23,720.00 $0.00 $0.00 
10Geogrid Mat1883S.Y.$3.00$5,649.00 $0.00 $0.00 
1124" DIA. CMP Extension & FES1L.S.$1,500.00$1,500.00 $0.00 $0.00 
12Pavement Striping1L.S.$1,000.00$1,000.00 $0.00 $0.00 
13Class "A" Crushed Stone115Tons$40.00$4,600.00 $0.00 $0.00 
14Concrete Class "C" Structural315S.Y.$150.00$47,250.00 $0.00 $0.00 
15Class "D" Rip-Rap190Tons$45.00$8,550.00 $0.00 $0.00 
16Seed, Fertilize, & Mulch1L.S.$2,500.00$2,500.00 $0.00 $0.00 
      $217,272.00  $0.00  $0.00 
 



 