IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Clear Lake Dredge Spoil Containment Site  Date: 11/7/2013  Project No.  
  Lower Existing Dikes Phase 2  County:   CERRO GORDO  Time: 3:00 p.m.  13-03-17-04

 

 
1
2
3
Estimated Cost: $29,000.00
Contractor: 
Cole ExcavatingBurr Oak Springs
Funding Source: 100% Lake Restoration, 10471 Packard Ave
2113 Couty Rd W14

Greene IA  50636Ridgeway IA  52165  
Plan Sets Requested: 0
Quantities
641-823-4700563-737-2510
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$3,000.00$3,000.00 $9,999.00$9,999.00 $0.00 
2Lower Dikes1L.S.$30,600.00$30,600.00 $30,000.00$30,000.00 $0.00 
3Level Tree Removal Piles1L.S.$5,000.00$5,000.00 $10,000.00$10,000.00 $0.00 
      $38,600.00  $49,999.00  $0.00 
 



 

12/17/2025