IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Rock Creek Lake State Park | Date: 10/10/2013 | Project No. |
| Sediment Basin #1 | County: | JASPER | Time: 3:00 p.m. | 11-05-50-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $18,825.00 | Contractor: | Huyser Dozing and Tiling LLC | Sterk Excavating, Inc. | Kinman Co. Inc. | |||||||||
| Funding Source: 25% Lake Restoration, 75% Federal-EPA, | 1896 Oxford Ave | 117 180th Ave | 3101 Kent Ave | ||||||||||
| New Sharon IA 50207 | Otley IA 50214 | Oskaloosa IA 52577 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-660-3878 | 641-416-0110 | 641-660-0896 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing & Grubbing | 0.6 | Acres | $1,100.00 | $660.00 | $1,000.00 | $600.00 | $1,600.00 | $960.00 | ||||
| 2 | Earthwork | 6403 | C.Y. | $1.50 | $9,604.50 | $1.25 | $8,003.75 | $1.44 | $9,220.32 | ||||
| 3 | Installation of 8" Spiral CMP, Supplied by Owner | 146 | L.F. | $2.00 | $292.00 | $6.00 | $876.00 | $5.00 | $730.00 | ||||
| 4 | Installation of 10"x15' Spriral CMP Intake, Supplied by Owner | 1 | L.S. | $50.00 | $50.00 | $100.00 | $100.00 | $60.00 | $60.00 | ||||
| 5 | Installation of 72"x72" Antiseep Collars, Supplied by Owner | 3 | Each | $80.00 | $240.00 | $50.00 | $150.00 | $100.00 | $300.00 | ||||
| 6 | 2 Gallons Asphaltic Mastic Sealer, Supplied by Contractor | 1 | L.S. | $15.00 | $15.00 | $50.00 | $50.00 | $40.00 | $40.00 | ||||
| 7 | 10" Spiral CMP, Supplied by Contractor | 150 | L.F. | $13.00 | $1,950.00 | $13.35 | $2,002.50 | $23.44 | $3,516.00 | ||||
| 8 | 8" Corrugated Field Tile, Supplied by Contractor | 40 | L.F. | $5.00 | $200.00 | $9.00 | $360.00 | $7.00 | $280.00 | ||||
| 9 | 8" Rodent Guard, Supplied by Contractor | 1 | Each | $10.00 | $10.00 | $25.00 | $25.00 | $15.00 | $15.00 | ||||
| 10 | 10" Rodent Guard, Supplied by Contractor | 1 | Each | $12.00 | $12.00 | $25.00 | $25.00 | $18.00 | $18.00 | ||||
| 11 | Seed, Fertilizer, & Mulch, Supplied by Contractor | 1.5 | Acres | $750.00 | $1,125.00 | $1,200.00 | $1,800.00 | $2,500.00 | $3,750.00 | ||||
| 12 | Fence Removal & Replacement | 350 | L.F. | $3.00 | $1,050.00 | $3.75 | $1,312.50 | $5.00 | $1,750.00 | ||||
| 13 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,975.00 | $1,975.00 | ||||
| $16,708.50 | $16,804.75 | $22,614.32 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $18,825.00 | Contractor: | Jay and Garret Inc. | Nagle Land Tiling, Inc. | Burr Oak Springs | |||||||||
| Funding Source: 25% Lake Restoration, 75% Federal-EPA, | 806 W 1st | 1326 230th St | 2113 County Rd W14 | ||||||||||
| Leon IA 50144 | Garwin IA 50632 | Ridgeway IA 52165 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-344-7646 | 641-751-8614 | 563-737-2510 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing & Grubbing | 0.6 | Acres | $4,166.66 | $2,499.996 | $2,500.00 | $1,500.00 | $1,000.00 | $600.00 | ||||
| 2 | Earthwork | 6403 | C.Y. | $1.65 | $10,564.95 | $1.75 | $11,205.25 | $3.00 | $19,209.00 | ||||
| 3 | Installation of 8" Spiral CMP, Supplied by Owner | 146 | L.F. | $5.00 | $730.00 | $3.10 | $452.60 | $10.00 | $1,460.00 | ||||
| 4 | Installation of 10"x15' Spriral CMP Intake, Supplied by Owner | 1 | L.S. | $500.00 | $500.00 | $450.00 | $450.00 | $200.00 | $200.00 | ||||
| 5 | Installation of 72"x72" Antiseep Collars, Supplied by Owner | 3 | Each | $200.00 | $600.00 | $150.00 | $450.00 | $100.00 | $300.00 | ||||
| 6 | 2 Gallons Asphaltic Mastic Sealer, Supplied by Contractor | 1 | L.S. | $250.00 | $250.00 | $42.00 | $42.00 | $20.00 | $20.00 | ||||
| 7 | 10" Spiral CMP, Supplied by Contractor | 150 | L.F. | $23.87 | $3,580.50 | $25.20 | $3,780.00 | $24.25 | $3,637.50 | ||||
| 8 | 8" Corrugated Field Tile, Supplied by Contractor | 40 | L.F. | $5.00 | $200.00 | $3.00 | $120.00 | $8.00 | $320.00 | ||||
| 9 | 8" Rodent Guard, Supplied by Contractor | 1 | Each | $15.00 | $15.00 | $25.00 | $25.00 | $8.00 | $8.00 | ||||
| 10 | 10" Rodent Guard, Supplied by Contractor | 1 | Each | $15.00 | $15.00 | $30.00 | $30.00 | $12.00 | $12.00 | ||||
| 11 | Seed, Fertilizer, & Mulch, Supplied by Contractor | 1.5 | Acres | $1,333.33 | $1,999.995 | $4,400.00 | $6,600.00 | $500.00 | $750.00 | ||||
| 12 | Fence Removal & Replacement | 350 | L.F. | $5.71 | $1,998.50 | $2.10 | $735.00 | $2.00 | $700.00 | ||||
| 13 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | ||||
| $24,953.941 | $27,889.85 | $29,216.50 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $18,825.00 | Contractor: | Hatch Grading & Contracting Inc. | Schoon Construction, Inc. | ||||||||||
| Funding Source: 25% Lake Restoration, 75% Federal-EPA, | 101 Cushman St PO Box 157 | 603 Penrose | |||||||||||
| Dysart IA 52224 | Grinnell IA 50112 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-476-2626 | 641-236-8395 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing & Grubbing | 0.6 | Acres | $5,000.00 | $3,000.00 | $3,000.00 | $1,800.00 | $0.00 | |||||
| 2 | Earthwork | 6403 | C.Y. | $3.00 | $19,209.00 | $3.00 | $19,209.00 | $0.00 | |||||
| 3 | Installation of 8" Spiral CMP, Supplied by Owner | 146 | L.F. | $18.00 | $2,628.00 | $30.00 | $4,380.00 | $0.00 | |||||
| 4 | Installation of 10"x15' Spriral CMP Intake, Supplied by Owner | 1 | L.S. | $500.00 | $500.00 | $350.00 | $350.00 | $0.00 | |||||
| 5 | Installation of 72"x72" Antiseep Collars, Supplied by Owner | 3 | Each | $250.00 | $750.00 | $350.00 | $1,050.00 | $0.00 | |||||
| 6 | 2 Gallons Asphaltic Mastic Sealer, Supplied by Contractor | 1 | L.S. | $150.00 | $150.00 | $70.00 | $70.00 | $0.00 | |||||
| 7 | 10" Spiral CMP, Supplied by Contractor | 150 | L.F. | $18.50 | $2,775.00 | $37.52 | $5,628.00 | $0.00 | |||||
| 8 | 8" Corrugated Field Tile, Supplied by Contractor | 40 | L.F. | $17.00 | $680.00 | $8.00 | $320.00 | $0.00 | |||||
| 9 | 8" Rodent Guard, Supplied by Contractor | 1 | Each | $30.00 | $30.00 | $15.00 | $15.00 | $0.00 | |||||
| 10 | 10" Rodent Guard, Supplied by Contractor | 1 | Each | $35.00 | $35.00 | $20.00 | $20.00 | $0.00 | |||||
| 11 | Seed, Fertilizer, & Mulch, Supplied by Contractor | 1.5 | Acres | $2,500.00 | $3,750.00 | $1,600.00 | $2,400.00 | $0.00 | |||||
| 12 | Fence Removal & Replacement | 350 | L.F. | $6.00 | $2,100.00 | $5.75 | $2,012.50 | $0.00 | |||||
| 13 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| $38,107.00 | $39,754.50 | $0.00 | |||||||||||
12/17/2025