IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Anita | Date: 12/18/2014 | Project No. |
| Analyze lift station problems | County: | CASS | Time: 3:00 p.m. | 14-04-15-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $30,450.00 | Contractor: | Schoon Construction, Inc. | |||||||||||
| Funding Source: 100% REAP Land Management, | 1500 S 2nd St PO Box 800 | ||||||||||||
| Cherokee IA 51012 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-225-5736 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $2,820.00 | $2,820.00 | $0.00 | $0.00 | ||||||
| 2 | REPLACE EXISTING PUMPS WITH NEW PUMPS | 1 | L.S. | $10,775.00 | $10,775.00 | $0.00 | $0.00 | ||||||
| 3 | EXCAVATE, REMOVE AND DISPOSE EXISTING SEWER LINE TO INSTALL SEPTIC TANK | 1 | L.S. | $2,410.00 | $2,410.00 | $0.00 | $0.00 | ||||||
| 4 | INSTALL SEPTIC TANK COMPLETE WITH RISERS, EFFLUENT FILTER, CONNECTIONS TO EXISTING SEWER & GRADING | 1 | L.S. | $11,460.00 | $11,460.00 | $0.00 | $0.00 | ||||||
| 5 | SITE RESTORATION & SEEDING | 1 | L.S. | $1,320.00 | $1,320.00 | $0.00 | $0.00 | ||||||
| $28,785.00 | $0.00 | $0.00 | |||||||||||
12/20/2025