 Bids For:  Location:   Backbone State Park  Date: 8/15/2013  Project No.  
  Emergency Boat Ramp Roadway Repair  County:   DELAWARE  Time: 3:00 p.m.  13-03-28-02

 

 
1
2
3
Estimated Cost: $35,000.00
Contractor: 
Nickol Earth Moving LLCTop Grade Excavating, Inc
Funding Source: 100% Park & Institutional Road Fund, 403 South Lake Dr
971 9th Ave NW

Farley IA  52046Farley IA  52046  
Plan Sets Requested: 0
Quantities
563-590-1869563-744-3416
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,900.00$1,900.00 $2,500.00$2,500.00 $0.00 
2Off-Site Fill Material, In Place900C.Y.$14.85$13,365.00 $18.00$16,200.00 $0.00 
3Revetment, Class D In Place650Tons$20.00$13,000.00 $21.00$13,650.00 $0.00 
4Base, Crushed Stone15Tons$15.00$225.00 $25.00$375.00 $0.00 
5Pavement, PCC Class 'C' 6" Shoulder840S.F.$9.50$7,980.00 $7.75$6,510.00 $0.00 
6Rubble Removal1L.S.$1,450.00$1,450.00 $1,200.00$1,200.00 $0.00 
7Tree Removal1L.S.$3,450.00$3,450.00 $1,800.00$1,800.00 $0.00 
      $41,370.00  $42,235.00  $0.00 
 



 

12/17/2025