| Bids For: | Location: | George Wyth State Park | Date: 8/21/2014 | Project No. |
| Beach Concession Remodel | County: | BLACK HAWK | Time: 11:00 a.m. | 14-03-07-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $125,000.00 | Contractor: | Jonas Raber Construction LLC | Woodruff Construction | ||||||||||
| Funding Source: 81% Special Appropriations, 19% Other, | 1296 145th St | 1890 Kountry Ln | |||||||||||
| Fairbank IA 50629 | Ft. Dodge IA 50501 | ||||||||||||
| Plan Sets Requested: 3 | Quantities | 319-551-9346 | (515) 576-1118 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION OF SPECIFIED ITEMS (CMU CUTTING, REMOVAL | 1 | L.S. | $18,610.00 | $18,610.00 | $5,100.00 | $5,100.00 | $0.00 | |||||
| 2 | INSTALL OF ALL NEW DOORS AND WINDOWS | 1 | L.S. | $24,460.00 | $24,460.00 | $22,000.00 | $22,000.00 | $0.00 | |||||
| 3 | INSTALL OF LINTELS OVER NEW CUT-OUT DOORS | 1 | L.S. | $3,000.00 | $3,000.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| 4 | ALL MECHANICAL AND ELECTRICAL ITEMS | 1 | L.S. | $26,430.00 | $26,430.00 | $45,000.00 | $45,000.00 | $0.00 | |||||
| 5 | INSTALL OF NEW ROOFING AND SHEATHING AS SPECIFIED | 1 | L.S. | $10,420.00 | $10,420.00 | $5,000.00 | $5,000.00 | $0.00 | |||||
| 6 | ALL OTHER ITEMS (FINISHES, CEILING, ARCHITECTURAL | 1 | L.S. | $7,330.00 | $7,330.00 | $19,700.00 | $19,700.00 | $0.00 | |||||
| 7 | MOBILIZATION | 1 | L.S. | $1,500.00 | $1,500.00 | $6,700.00 | $6,700.00 | $0.00 | |||||
| $91,750.00 | $106,000.00 | $0.00 | |||||||||||
10/16/2026