IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Rock Creek State Park  Date: 5/22/2014  Project No.  
  Precast Concrete Restrooms  County:   JASPER  Time: 11:00 a.m.  14-05-50-01

 

 
1
2
3
Estimated Cost: $260,000.00
Contractor: 
Caliber Concrete LLCHay Construction Services Inc.
Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, 309 Audubon St
16 S 18th Avenue

Adair IA  50002Marshalltown IA  50158  
Plan Sets Requested: 4
Quantities
515-979-2004641-752-3551
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1DEMOLITION1L.S.$8,000.00$8,000.00 $14,718.00$14,718.00 $0.00 
2CLEARING AND GRUBBING1L.S.$2,000.00$2,000.00 $6,240.00$6,240.00 $0.00 
3SITE WORK AND UTILITY CONNECTIONS1L.S.$24,000.00$24,000.00 $12,900.00$12,900.00 $0.00 
4SINGLE RIGHT HAND CASCADIAN PRECAST CONCRETE VAULT1Each$24,898.00$24,898.00 $33,342.00$33,342.00 $0.00 
5DOUBLE CASCADIAN PRECAST CONCRETE VAULT1Each$40,128.00$40,128.00 $57,780.00$57,780.00 $0.00 
6MONTROSS PRECAST CONCRETE RESTROOM1Each$86,798.00$86,798.00 $117,480.00$117,480.00 $0.00 
7CLASS "A' CRUSHED STONE162Tons$40.00$6,480.00 $48.00$7,776.00 $0.00 
8SIDEWALK, PCC, 6"125S.Y.$60.00$7,500.00 $77.00$9,625.00 $0.00 
9PARKING LOT, PCC, 6"109S.Y.$60.00$6,540.00 $70.00$7,630.00 $0.00 
10SIGNING4Each$1,300.00$5,200.00 $580.00$2,320.00 $0.00 
11DRAIN-DOWN PIT1L.S.$3,200.00$3,200.00 $7,800.00$7,800.00 $0.00 
12PRECAST CONCRETE PARKING WHEEL STOPS4Each$200.00$800.00 $260.00$1,040.00 $0.00 
13EROSION CONTROL275L.F.$5.00$1,375.00 $5.00$1,375.00 $0.00 
14PAINTED PAVEMENT MARKINGS, WATERBORNE/SOLVENT9.6STA.$50.00$480.00 $270.00$2,592.00 $0.00 
15DETECTABLE WARNING PANEL16S.F.$30.00$480.00 $26.00$416.00 $0.00 
16REMOVE CONCRETE PAD16S.Y.$18.00$288.00 $102.00$1,632.00 $0.00 
17ELECTRICAL SERVICE1L.S.$8,000.00$8,000.00 $8,682.00$8,682.00 $0.00 
18WATER MAIN, 2" HDPE23L.F.$50.00$1,150.00 $60.00$1,380.00 $0.00 
19REMOVAL OF PAVEMENT 62.5S.Y.$25.00$1,562.50 $42.00$2,625.00 $0.00 
20CONSTRUCTION STAKING1L.S.$1,500.00$1,500.00 $2,700.00$2,700.00 $0.00 
21MOBILIZATION1L.S.$9,000.00$9,000.00 $41,100.00$41,100.00 $0.00 
      $239,379.50  $341,153.00  $0.00 
 



 