IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   George Wyth State Park  Date: 4/16/2015  Project No.  
  Install Two (2) Pit Vault Toilets  County:   BLACK HAWK  Time: 3:00 p.m.  14-03-07-01

 

 
1
2
3
Estimated Cost: $65,000.00
Contractor: 
Jonas Raber Construction LLCF.L. Krapfl Inc. Boulder Contracting, LLC
Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, 1296 145th St

PO Box 303
25789 N Ave
Fairbank IA  50629Dyersville IA  52040Grundy Center IA  50638
Plan Sets Requested: 0
Quantities
319-551-9346563-875-8938319-269-8680
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Grading1L.S.$2,500.00$2,500.00 $500.00$500.00 $2,500.00$2,500.00 
2Import Off-Site Fill Material50C.Y.$17.00$850.00 $26.00$1,300.00 $30.00$1,500.00 
3Saw Cut10L.F.$15.00$150.00 $6.00$60.00 $10.00$100.00 
4Precast Single Vault Building2Each$23,500.00$47,000.00 $27,551.00$55,102.00 $25,000.00$50,000.00 
56" Non-Reinforced PCC Sidewalk11.2S.Y.$185.00$2,072.00 $76.00$851.20 $75.00$840.00 
6Granular Base16Tons$23.50$376.00 $23.00$368.00 $35.00$560.00 
7Seeding, Fertilizing, and Mulching1L.S.$2,020.00$2,020.00 $1,460.00$1,460.00 $750.00$750.00 
8Mobilization1L.S.$550.00$550.00 $992.00$992.00 $5,725.00$5,725.00 
      $55,518.00  $60,633.20  $61,975.00 
 
 
4
5
6
Estimated Cost: $65,000.00
Contractor: 
Matt Construction Inc.Swales Precast Inc.
Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, 203 Y Ave

PO Box 309

Sumner IA  50676Strawberry Point IA  52076  
Plan Sets Requested: 0
Quantities
563-578-8418563-933-2227
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Grading1L.S.$5,000.00$5,000.00 $2,500.00$2,500.00 $0.00 
2Import Off-Site Fill Material50C.Y.$55.00$2,750.00 $30.00$1,500.00 $0.00 
3Saw Cut10L.F.$20.00$200.00 $200.00$2,000.00 $0.00 
4Precast Single Vault Building2Each$24,385.00$48,770.00 $29,000.00$58,000.00 $0.00 
56" Non-Reinforced PCC Sidewalk11.2S.Y.$45.00$504.00 $200.00$2,240.00 $0.00 
6Granular Base16Tons$18.00$288.00 $400.00$6,400.00 $0.00 
7Seeding, Fertilizing, and Mulching1L.S.$3,000.00$3,000.00 $750.00$750.00 $0.00 
8Mobilization1L.S.$4,000.00$4,000.00 $1,000.00$1,000.00 $0.00 
      $64,512.00  $74,390.00  $0.00 
 


The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.


Jonas Raber Construction LLC, Fairbank, IA
 

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

12/21/2025