IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | George Wyth State Park | Date: 4/16/2015 | Project No. |
| Install Two (2) Pit Vault Toilets | County: | BLACK HAWK | Time: 3:00 p.m. | 14-03-07-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $65,000.00 | Contractor: | Jonas Raber Construction LLC | F.L. Krapfl Inc. | Boulder Contracting, LLC | |||||||||
| Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, | 1296 145th St | PO Box 303 | 25789 N Ave | ||||||||||
| Fairbank IA 50629 | Dyersville IA 52040 | Grundy Center IA 50638 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-551-9346 | 563-875-8938 | 319-269-8680 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Grading | 1 | L.S. | $2,500.00 | $2,500.00 | $500.00 | $500.00 | $2,500.00 | $2,500.00 | ||||
| 2 | Import Off-Site Fill Material | 50 | C.Y. | $17.00 | $850.00 | $26.00 | $1,300.00 | $30.00 | $1,500.00 | ||||
| 3 | Saw Cut | 10 | L.F. | $15.00 | $150.00 | $6.00 | $60.00 | $10.00 | $100.00 | ||||
| 4 | Precast Single Vault Building | 2 | Each | $23,500.00 | $47,000.00 | $27,551.00 | $55,102.00 | $25,000.00 | $50,000.00 | ||||
| 5 | 6" Non-Reinforced PCC Sidewalk | 11.2 | S.Y. | $185.00 | $2,072.00 | $76.00 | $851.20 | $75.00 | $840.00 | ||||
| 6 | Granular Base | 16 | Tons | $23.50 | $376.00 | $23.00 | $368.00 | $35.00 | $560.00 | ||||
| 7 | Seeding, Fertilizing, and Mulching | 1 | L.S. | $2,020.00 | $2,020.00 | $1,460.00 | $1,460.00 | $750.00 | $750.00 | ||||
| 8 | Mobilization | 1 | L.S. | $550.00 | $550.00 | $992.00 | $992.00 | $5,725.00 | $5,725.00 | ||||
| $55,518.00 | $60,633.20 | $61,975.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $65,000.00 | Contractor: | Matt Construction Inc. | Swales Precast Inc. | ||||||||||
| Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, | 203 Y Ave | PO Box 309 | |||||||||||
| Sumner IA 50676 | Strawberry Point IA 52076 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-578-8418 | 563-933-2227 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Grading | 1 | L.S. | $5,000.00 | $5,000.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| 2 | Import Off-Site Fill Material | 50 | C.Y. | $55.00 | $2,750.00 | $30.00 | $1,500.00 | $0.00 | |||||
| 3 | Saw Cut | 10 | L.F. | $20.00 | $200.00 | $200.00 | $2,000.00 | $0.00 | |||||
| 4 | Precast Single Vault Building | 2 | Each | $24,385.00 | $48,770.00 | $29,000.00 | $58,000.00 | $0.00 | |||||
| 5 | 6" Non-Reinforced PCC Sidewalk | 11.2 | S.Y. | $45.00 | $504.00 | $200.00 | $2,240.00 | $0.00 | |||||
| 6 | Granular Base | 16 | Tons | $18.00 | $288.00 | $400.00 | $6,400.00 | $0.00 | |||||
| 7 | Seeding, Fertilizing, and Mulching | 1 | L.S. | $3,000.00 | $3,000.00 | $750.00 | $750.00 | $0.00 | |||||
| 8 | Mobilization | 1 | L.S. | $4,000.00 | $4,000.00 | $1,000.00 | $1,000.00 | $0.00 | |||||
| $64,512.00 | $74,390.00 | $0.00 | |||||||||||
Jonas Raber Construction LLC, Fairbank, IA
12/21/2025