IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Brushy Creek Recreation Area | Date: 4/17/2014 | Project No. |
| Installation of Pre-Fab Bridge | County: | WEBSTER | Time: 11:00 a.m. | 13-02-94-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $99,965.00 | Contractor: | Richards Construction Co Inc | Jonas Raber Construction | Hecks Dozer | |||||||||
| Funding Source: 25% Infrastructure 2013, 50% Other, 25% REAP Land Management, | 2721 Sierra Ave | 1296 145th St | 518 W Sycamore | ||||||||||
| Sac City IA 50583 | Fairbank IA 50629 | Ogden IA 50212 | |||||||||||
| Plan Sets Requested: 11 | Quantities | 712-662-4421 | 319-551-9346 | 515-275-2953 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $2,500.00 | $2,500.00 | $1,850.00 | $1,850.00 | $2,991.60 | $2,991.60 | ||||
| 2 | Access Route | 1 | L.S. | $7,500.00 | $7,500.00 | $5,200.00 | $5,200.00 | $8,974.80 | $8,974.80 | ||||
| 3 | Class 'E' Riprap | 15 | Tons | $60.00 | $900.00 | $130.00 | $1,950.00 | $106.56 | $1,598.40 | ||||
| 4 | Grading | 1 | L.S. | $3,500.00 | $3,500.00 | $2,500.00 | $2,500.00 | $7,479.00 | $7,479.00 | ||||
| 5 | Contech Connector 75' Span x 10' Width Equestrian Bridge (or Equivalent) | 1 | L.S. | $89,500.00 | $89,500.00 | $86,200.00 | $86,200.00 | $84,153.60 | $84,153.60 | ||||
| 6 | Contech Precast Abutment System (or Equivalent) | 1 | L.S. | $12,000.00 | $12,000.00 | $19,800.00 | $19,800.00 | $18,684.00 | $18,684.00 | ||||
| 7 | Concrete Base With TS3x3x1/4 Galvanized Square Tubular Fence Post | 4 | Each | $350.00 | $1,400.00 | $800.00 | $3,200.00 | $715.50 | $2,862.00 | ||||
| 8 | Fence Reconstruction | 1 | L.S. | $2,000.00 | $2,000.00 | $3,000.00 | $3,000.00 | $1,242.00 | $1,242.00 | ||||
| 9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $1,500.00 | $1,500.00 | $2,800.00 | $2,800.00 | $5,238.00 | $5,238.00 | ||||
| 10 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $9,400.00 | $9,400.00 | $4,320.00 | $4,320.00 | ||||
| $125,800.00 | $135,900.00 | $137,543.40 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $99,965.00 | Contractor: | Boulder Contracting LLC | PETERSON CONTRACTORS INC (PCI-REINBECK) | WOODRUFF CONSTRUCTION | |||||||||
| Funding Source: 25% Infrastructure 2013, 50% Other, 25% REAP Land Management, | 25789 N Avenue | 104 Blackhawk St | 1890 KOUNTRY LANE PO Box 1830 | ||||||||||
| Grundy Center IA 50638 | Reinbeck IA 50669 | FT DODGE IA 50501 | |||||||||||
| Plan Sets Requested: 11 | Quantities | 319-269-8680 | 319-345-2713 | 515-576-1118 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $16,000.00 | $16,000.00 | $32,650.00 | $32,650.00 | $20,400.00 | $20,400.00 | ||||
| 2 | Access Route | 1 | L.S. | $65,000.00 | $65,000.00 | $59,040.00 | $59,040.00 | $120,000.00 | $120,000.00 | ||||
| 3 | Class 'E' Riprap | 15 | Tons | $100.00 | $1,500.00 | $147.75 | $2,216.25 | $120.00 | $1,800.00 | ||||
| 4 | Grading | 1 | L.S. | $18,000.00 | $18,000.00 | $17,000.00 | $17,000.00 | $42,000.00 | $42,000.00 | ||||
| 5 | Contech Connector 75' Span x 10' Width Equestrian Bridge (or Equivalent) | 1 | L.S. | $81,000.00 | $81,000.00 | $89,250.00 | $89,250.00 | $120,000.00 | $120,000.00 | ||||
| 6 | Contech Precast Abutment System (or Equivalent) | 1 | L.S. | $17,000.00 | $17,000.00 | $23,500.00 | $23,500.00 | $20,000.00 | $20,000.00 | ||||
| 7 | Concrete Base With TS3x3x1/4 Galvanized Square Tubular Fence Post | 4 | Each | $750.00 | $3,000.00 | $1,725.00 | $6,900.00 | $1,000.00 | $4,000.00 | ||||
| 8 | Fence Reconstruction | 1 | L.S. | $1,200.00 | $1,200.00 | $3,535.00 | $3,535.00 | $10,000.00 | $10,000.00 | ||||
| 9 | Seeding, Fertilizing and Mulching | 1 | L.S. | $10,500.00 | $10,500.00 | $12,120.00 | $12,120.00 | $20,000.00 | $20,000.00 | ||||
| 10 | Mobilization | 1 | L.S. | $45,000.00 | $45,000.00 | $21,246.00 | $21,246.00 | $25,000.00 | $25,000.00 | ||||
| $258,200.00 | $267,457.25 | $383,200.00 | |||||||||||