IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Decorah Fisheries Management Unit  Date: 8/29/2013  Project No.  
  Waterloo Creek - Bank Stabilization  County:   ALLAMAKEE  Time: 3:00 p.m.  14-03-03-01

 

 
1
2
3
Estimated Cost: $45,000.00
Contractor: 
David Ryan ConstructionDon Rausch and Sons Construction IncRiehm Construction
Funding Source: 100% Federal-Other, 3566 236th Ave
2678 118th St
2340 9th St SW
Decorah IA  52101Fort Atkinson IA  52144Waukon IA  52172
Plan Sets Requested: 0
Quantities
563-735-5895563-534-7356563-568-3314
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$500.00$500.00 $3,000.00$3,000.00 $15,000.00$15,000.00 
2Bank Reshaping1960L.F.$3.93$7,702.80 $17.00$33,320.00 $6.00$11,760.00 
3Revetment, Cl 'D' Rip Rap1450Tons$22.16$32,132.00 $17.00$24,650.00 $25.00$36,250.00 
4Stabilizing Crop Seeding2Acres$750.00$1,500.00 $300.00$600.00 $1,000.00$2,000.00 
5Provide Erosion Control Mat & Bio Stakes1L.S.$4,630.00$4,630.00 $2,975.00$2,975.00 $6,489.05$6,489.05 
      $46,464.80  $64,545.00  $71,499.05 
 



 