IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Coon Creek WMA | Date: 12/19/2013 | Project No. |
| Parking facility Stabilization | County: | WINNESHIEK | Time: 11:00 a.m. | 12-03-96-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | H & H Construction & Development LLC | JB Holland Construction Inc. | Burr Oak Springs Limited | |||||||||
| Funding Source: 90% Federal-FEMA 1, 10% F&W Trust - Other, | 60559 Hwy 64 | 2092 Hwy 9 West | 2113 County Rd W-14 | ||||||||||
| Sabula IA 52070 | Decorah IA 52101 | Ridgeway IA 52165 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 563-357-1849 | 563-382-2901 | 563-737-3510 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $9,200.00 | $9,200.00 | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Clearing & Grubbing | 1200 | Units | $4.00 | $4,800.00 | $10.15 | $12,180.00 | $20.00 | $24,000.00 | ||||
| 3 | Revetment, Class B Modified | 975 | Tons | $23.47 | $22,883.25 | $24.30 | $23,692.50 | $24.70 | $24,082.50 | ||||
| 4 | Class D Revetment | 745 | Tons | $19.19 | $14,296.55 | $21.90 | $16,315.50 | $21.70 | $16,166.50 | ||||
| 5 | Class 10 Excavation/Earthwork | 12450 | C.Y. | $2.00 | $24,900.00 | $3.05 | $37,972.50 | $2.00 | $24,900.00 | ||||
| 6 | Engineering Fabric | 1600 | S.Y. | $3.33 | $5,328.00 | $1.85 | $2,960.00 | $2.00 | $3,200.00 | ||||
| 7 | Erosion Mat | 3333 | S.Y. | $2.41 | $8,032.53 | $1.85 | $6,166.05 | $1.50 | $4,999.50 | ||||
| 8 | Silt Fence | 1000 | L.F. | $1.50 | $1,500.00 | $1.85 | $1,850.00 | $1.60 | $1,600.00 | ||||
| 9 | Seeding, Fertilizing & Mulching | 2 | Acres | $2,200.00 | $4,400.00 | $1,100.00 | $2,200.00 | $1,000.00 | $2,000.00 | ||||
| $95,340.33 | $105,336.55 | $105,948.50 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | Riehm Construction Company | C J Moyna & Sons Inc | Bacon Concrete LLC | |||||||||
| Funding Source: 90% Federal-FEMA 1, 10% F&W Trust - Other, | 2340 - 9th St SW | 24412 Hwy 13 | 370 N Bancroft St. | ||||||||||
| Waukon IA 52172 | Elkader IA 52043 | Postville IA 52162-0188 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 563-568-3314 | 563-245-1442 | 563-864-7602 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $18,500.00 | $18,500.00 | $3,000.00 | $3,000.00 | ||||
| 2 | Clearing & Grubbing | 1200 | Units | $4.00 | $4,800.00 | $10.00 | $12,000.00 | $5.00 | $6,000.00 | ||||
| 3 | Revetment, Class B Modified | 975 | Tons | $19.65 | $19,158.75 | $26.20 | $25,545.00 | $35.00 | $34,125.00 | ||||
| 4 | Class D Revetment | 745 | Tons | $16.05 | $11,957.25 | $21.90 | $16,315.50 | $31.00 | $23,095.00 | ||||
| 5 | Class 10 Excavation/Earthwork | 12450 | C.Y. | $3.25 | $40,462.50 | $2.80 | $34,860.00 | $2.10 | $26,145.00 | ||||
| 6 | Engineering Fabric | 1600 | S.Y. | $2.25 | $3,600.00 | $3.00 | $4,800.00 | $4.00 | $6,400.00 | ||||
| 7 | Erosion Mat | 3333 | S.Y. | $4.19 | $13,965.27 | $1.70 | $5,666.10 | $3.75 | $12,498.75 | ||||
| 8 | Silt Fence | 1000 | L.F. | $2.65 | $2,650.00 | $1.85 | $1,850.00 | $3.75 | $3,750.00 | ||||
| 9 | Seeding, Fertilizing & Mulching | 2 | Acres | $825.00 | $1,650.00 | $1,100.00 | $2,200.00 | $3,800.00 | $7,600.00 | ||||
| $108,243.77 | $121,736.60 | $122,613.75 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | David Ryan Construction LLC | Tri-Smith Construction LLC | ||||||||||
| Funding Source: 90% Federal-FEMA 1, 10% F&W Trust - Other, | 3566 236th Ave | 21239 CR 366 | |||||||||||
| Deccorah IA 52101 | Carrollton MO 64633 | ||||||||||||
| Plan Sets Requested: 8 | Quantities | 563-735-5895 | 660-542-2738 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $48,175.00 | $48,175.00 | $0.00 | |||||
| 2 | Clearing & Grubbing | 1200 | Units | $6.60 | $7,920.00 | $15.50 | $18,600.00 | $0.00 | |||||
| 3 | Revetment, Class B Modified | 975 | Tons | $29.50 | $28,762.50 | $35.00 | $34,125.00 | $0.00 | |||||
| 4 | Class D Revetment | 745 | Tons | $27.00 | $20,115.00 | $24.00 | $17,880.00 | $0.00 | |||||
| 5 | Class 10 Excavation/Earthwork | 12450 | C.Y. | $4.05 | $50,422.50 | $5.00 | $62,250.00 | $0.00 | |||||
| 6 | Engineering Fabric | 1600 | S.Y. | $4.00 | $6,400.00 | $10.00 | $16,000.00 | $0.00 | |||||
| 7 | Erosion Mat | 3333 | S.Y. | $3.10 | $10,332.30 | $20.00 | $66,660.00 | $0.00 | |||||
| 8 | Silt Fence | 1000 | L.F. | $4.50 | $4,500.00 | $15.00 | $15,000.00 | $0.00 | |||||
| 9 | Seeding, Fertilizing & Mulching | 2 | Acres | $1,000.00 | $2,000.00 | $1,000.00 | $2,000.00 | $0.00 | |||||
| $131,952.30 | $280,690.00 | $0.00 | |||||||||||
Burr Oak Springs Limited, Ridgeway, IA
David Ryan Construction LLC, Deccorah, IA