IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Anita | Date: 3/21/2013 | Project No. |
| East Silt Pond Renovation | County: | CASS | Time: 11:00 a.m. | 13-04-15-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $70,000.00 | Contractor: | Jeff Sickels Dozing LLC | C L Carroll Company Inc | Lamb Tiling | |||||||||
| Funding Source: 100% Lake Restoration, | 2047 220th St | 3623 6th Ave | 2751 Marion Ave | ||||||||||
| Mount Ayr IA 50854 | Des Moines IA 50313 | Greenfield IA 50849 | |||||||||||
| Plan Sets Requested: 11 | Quantities | 641-464-2453 | 515-282-7495 | 641-743-8312 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment/Soil Dredge & Haul | 8000 | C.Y. | $3.45 | $27,600.00 | $3.10 | $24,800.00 | $3.90 | $31,200.00 | ||||
| 2 | Box Culvert Modification | 1 | L.S. | $10,500.00 | $10,500.00 | $24,357.00 | $24,357.00 | $21,499.00 | $21,499.00 | ||||
| 3 | Seed, Fertilize, & Mulch | 1 | L.S. | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 | $6,650.00 | $6,650.00 | ||||
| $41,100.00 | $54,157.00 | $59,349.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $70,000.00 | Contractor: | MPS Engineers | Murphy Heavy Contracting Inc | Big River Construction | |||||||||
| Funding Source: 100% Lake Restoration, | 1444 Illinois St | 101 Roosevelt Street PO BOX 148 | 115 N 10th Street PO Box 277 | ||||||||||
| Des Moines IA 50314 | Anita IA 50020 | Nebraska City NE 68410 | |||||||||||
| Plan Sets Requested: 11 | Quantities | 515-221-9832 | 712-762-3386 | 402-873-6890 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment/Soil Dredge & Haul | 8000 | C.Y. | $4.75 | $38,000.00 | $6.28 | $50,240.00 | $6.95 | $55,600.00 | ||||
| 2 | Box Culvert Modification | 1 | L.S. | $18,400.00 | $18,400.00 | $24,141.77 | $24,141.77 | $14,620.00 | $14,620.00 | ||||
| 3 | Seed, Fertilize, & Mulch | 1 | L.S. | $3,592.00 | $3,592.00 | $2,000.00 | $2,000.00 | $14,620.00 | $14,620.00 | ||||
| $59,992.00 | $76,381.77 | $84,840.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $70,000.00 | Contractor: | Joy Dirt Construction | |||||||||||
| Funding Source: 100% Lake Restoration, | 202 State St Box 185 | ||||||||||||
| Cushing IA 51018-0185 | |||||||||||||
| Plan Sets Requested: 11 | Quantities | 712-384-2700 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment/Soil Dredge & Haul | 8000 | C.Y. | $7.50 | $60,000.00 | $0.00 | $0.00 | ||||||
| 2 | Box Culvert Modification | 1 | L.S. | $25,381.52 | $25,381.52 | $0.00 | $0.00 | ||||||
| 3 | Seed, Fertilize, & Mulch | 1 | L.S. | $21,381.52 | $21,381.52 | $0.00 | $0.00 | ||||||
| $106,763.04 | $0.00 | $0.00 | |||||||||||
10/15/2026