IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Prairie Rose | Date: 3/7/2013 | Project No. |
| Rock Chute Sediment Removal | County: | SHELBY | Time: 3:00 p.m. | 13-04-83-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Michael J. Lamb dba Lamb Tiling | Titus Demolition & Dirt Work | K & L Landscape & Construction | |||||||||
| Funding Source: 100% Lake Restoration, | 2751 Marion Ave | 3985 340th Ave | 501 S Ridge Rd | ||||||||||
| Greenfield IA 50849 | Ruthven IA 51358 | Sergeant Bluff IA 51054 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-743-8312 | 712-260-2707 | 712-943-2939 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Removal & Disposal | 8000 | C.Y. | $2.09 | $16,720.00 | $2.00 | $16,000.00 | $4.25 | $34,000.00 | ||||
| 2 | Site Restoration | 1 | L.S. | $2,880.00 | $2,880.00 | $8,410.79 | $8,410.79 | $2,850.00 | $2,850.00 | ||||
| $19,600.00 | $24,410.79 | $36,850.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | TEK Builders, Inc. | L.A. Carlson Contracting, Inc. | Hill Contracting | |||||||||
| Funding Source: 100% Lake Restoration, | 201 N Taylor St | 20984 C-43 | 20904 215 Ave | ||||||||||
| Mt Ayr IA 50854 | Merrill IA 51038 | Leon IA 50144 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-464-3972 | 712-239-3195 | 641-446-6428 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Removal & Disposal | 8000 | C.Y. | $3.68 | $29,440.00 | $3.65 | $29,200.00 | $3.25 | $26,000.00 | ||||
| 2 | Site Restoration | 1 | L.S. | $9,500.00 | $9,500.00 | $10,000.00 | $10,000.00 | $13,500.00 | $13,500.00 | ||||
| $38,940.00 | $39,200.00 | $39,500.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Richards Construction Co., Inc. | Murphy Heavy Contracting Corporation | Jason Roberts | |||||||||
| Funding Source: 100% Lake Restoration, | 2721 Sierra Ave | 101 Roosevelt Dr | 509 Cedar St | ||||||||||
| Sac City IA 50583 | Anita IA 50020 | Adair IA 50002 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 712-662-4421 | 712-762-3386 | 641-740-1411 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Removal & Disposal | 8000 | C.Y. | $4.00 | $32,000.00 | $5.10 | $40,800.00 | $5.75 | $46,000.00 | ||||
| 2 | Site Restoration | 1 | L.S. | $7,500.00 | $7,500.00 | $7,292.00 | $7,292.00 | $3,800.00 | $3,800.00 | ||||
| $39,500.00 | $48,092.00 | $49,800.00 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Joy Dirt Construction | Torco Enterprises Inc. | Malone Bulldozing Inc. | |||||||||
| Funding Source: 100% Lake Restoration, | 202 State St PO Box 185 | PO Box 461086 | 108 Remsen St PO Box 35 | ||||||||||
| Cushing IA 51018 | Papillion NE 68046 | Dunlap IA 51529 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 712-384-2700 | 402-880-1845 | 712-643-2281 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Removal & Disposal | 8000 | C.Y. | $5.43 | $43,440.00 | $6.00 | $48,000.00 | $5.72 | $45,760.00 | ||||
| 2 | Site Restoration | 1 | L.S. | $8,750.00 | $8,750.00 | $5,000.00 | $5,000.00 | $8,800.00 | $8,800.00 | ||||
| $52,190.00 | $53,000.00 | $54,560.00 | |||||||||||
13 | 14 | 15 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Lee Construction, Inc | |||||||||||
| Funding Source: 100% Lake Restoration, | 57258 225th St | ||||||||||||
| Glenwood IA 51534 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-527-3455 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Removal & Disposal | 8000 | C.Y. | $7.00 | $56,000.00 | $0.00 | $0.00 | ||||||
| 2 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| $61,000.00 | $0.00 | $0.00 | |||||||||||
10/15/2026