IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Springbrook/Beeds Lake | Date: 12/24/2012 | Project No. |
| Shower Building | County: | GUTHRIE | Time: 11:00 am | 13-04-39-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $270,000.00 | Contractor: | AAA Concrete LLC DBA Caliber Concrete LLC | Murphy Heavy Contracting Corp. | Blue Ribbon Builders | |||||||||
| Funding Source: 80% Infrastructure 2013, 20% Infrastructure 2015, | 309 Audubon St | 101 Roosevelt Dr | 1840 137th Ln | ||||||||||
| Adair IA 50002 | Anita IA 50020 | Earlham IA 50072 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 515-979-2004 | 712-762-3386 | 515-758-2545 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $10,500.00 | $10,500.00 | $10,000.00 | $10,000.00 | $21,375.70 | $21,375.70 | ||||
| 2 | CLEARING AND GRUBBING | 1 | L.S. | $3,500.00 | $3,500.00 | $1,750.00 | $1,750.00 | $1,711.00 | $1,711.00 | ||||
| 3 | SITE WORK AND UTILITY CONNECTIONS | 1 | L.S. | $17,000.00 | $17,000.00 | $18,677.67 | $18,677.67 | $44,923.78 | $44,923.78 | ||||
| 4 | CXT CHEYENNE PRECAST CONCRETE SHOWER BUILDING | 1 | Each | $204,629.00 | $204,629.00 | $200,000.00 | $200,000.00 | $223,020.00 | $223,020.00 | ||||
| 5 | CLASS "A" CRUSHED STONE | 153 | Tons | $26.00 | $3,978.00 | $28.50 | $4,360.50 | $42.48 | $6,499.44 | ||||
| 6 | SIDEWALK, PCC, 6" | 147.4 | S.Y. | $44.28 | $6,526.872 | $100.00 | $14,740.00 | $38.10 | $5,615.94 | ||||
| 7 | PARKING LOT, PCC, 6" | 62.2 | S.Y. | $43.11 | $2,681.442 | $100.00 | $6,220.00 | $38.10 | $2,369.82 | ||||
| 8 | SIGNING | 1 | Each | $1,310.00 | $1,310.00 | $1,200.00 | $1,200.00 | $2,596.00 | $2,596.00 | ||||
| 9 | DRAIN-DOWN PIT | 1 | L.S. | $3,250.00 | $3,250.00 | $6,500.00 | $6,500.00 | $6,785.00 | $6,785.00 | ||||
| 10 | PRECAST CONCRETE PARKING WHEEL STOPS | 2 | Each | $100.00 | $200.00 | $100.00 | $200.00 | $236.00 | $472.00 | ||||
| 11 | EROSION CONTROL | 245 | L.F. | $2.50 | $612.50 | $7.00 | $1,715.00 | $3.54 | $867.30 | ||||
| 12 | CONSTRUCTION STAKING | 1 | L.S. | $1,500.00 | $1,500.00 | $1,600.00 | $1,600.00 | $6,195.00 | $6,195.00 | ||||
| 13 | WATER MAIN, 2" PVC | 32 | L.F. | $43.75 | $1,400.00 | $25.00 | $800.00 | $73.75 | $2,360.00 | ||||
| 14 | ELECTRICAL SERVICE | 1 | L.S. | $12,250.00 | $12,250.00 | $22,745.00 | $22,745.00 | $14,822.85 | $14,822.85 | ||||
| 15 | LIFT STATION CONTROL PANEL INSTALLATION | 1 | L.S. | $750.00 | $750.00 | $2,500.00 | $2,500.00 | $4,000.00 | $4,000.00 | ||||
| $270,087.814 | $293,008.17 | $343,613.83 | |||||||||||