IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Chariton Research Station | Date: 4/18/2013 | Project No. |
| Parking Lot Paving | County: | LUCAS | Time: 3:00 p.m. | 12-05-59-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $68,000.00 | Contractor: | Hill Contracting | Joiner Construction Co. Inc. | McGee Concrete & Landscaping | |||||||||
| Funding Source: 100% F&W Trust-Fisheries Non-Habitat Stamp, | 20904 215 Ave | 11996 490th St | 219 N Fryer St | ||||||||||
| Leon IA 50144 | Plano IA 52531 | Russell IA 50238 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-446-6428 | 641-649-2646 | 641-203-0721 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Construction Staking | 1 | L.S. | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,750.00 | $1,750.00 | ||||
| 2 | Class 13 Excavation, Stockpile, Reuse, & Compact | 171.5 | C.Y. | $2.00 | $343.00 | $15.00 | $2,572.50 | $20.00 | $3,430.00 | ||||
| 3 | Class 13 Excavation, to be wasted onsite | 429 | C.Y. | $2.00 | $858.00 | $10.00 | $4,290.00 | $9.25 | $3,968.25 | ||||
| 4 | Asphalt Pavement Removal & Disposal | 387 | S.Y. | $18.00 | $6,966.00 | $11.00 | $4,257.00 | $3.16 | $1,222.92 | ||||
| 5 | Special Backfill | 130.5 | Tons | $20.00 | $2,610.00 | $0.00 | $0.00 | $28.00 | $3,654.00 | ||||
| 6 | Class C4 PCC, 6” Thick, No Reinforcement | 1030.6 | S.Y. | $38.00 | $39,162.80 | $34.00 | $35,040.40 | $35.00 | $36,071.00 | ||||
| 7 | 2”x4’x8’ Rigid Foam Insulation | 3 | Each | $10.00 | $30.00 | $50.00 | $150.00 | $38.33 | $114.99 | ||||
| 8 | 12” Diameter CMP | 158 | L.F. | $10.00 | $1,580.00 | $25.00 | $3,950.00 | $25.00 | $3,950.00 | ||||
| 9 | Site Restoration, Seed (Urban Mix), Fertilizer, Straw Mulch | 1 | L.S. | $250.00 | $250.00 | $2,000.00 | $2,000.00 | $1,625.00 | $1,625.00 | ||||
| 10 | Seeding Waste Dirt Site, Native Mix, Fertilizer, Straw Mulch | 0.25 | Acres | $2,000.00 | $500.00 | $3,500.00 | $875.00 | $2,000.00 | $500.00 | ||||
| 11 | Silt Fence | 65 | L.F. | $2.00 | $130.00 | $3.00 | $195.00 | $8.00 | $520.00 | ||||
| 12 | Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $2,000.00 | $2,000.00 | $1,000.00 | $1,000.00 | ||||
| 13 | Concrete Sidewalk Removal & Disposal | 21.3 | S.Y. | $10.00 | $213.00 | $11.00 | $234.30 | $38.00 | $809.40 | ||||
| 14 | Culvert Removal, 12” CMP | 40 | L.F. | $2.00 | $80.00 | $15.00 | $600.00 | $5.00 | $200.00 | ||||
| 15 | Subgrade Preparation & Compaction | 1230.6 | S.Y. | $0.50 | $615.30 | $2.00 | $2,461.20 | $3.00 | $3,691.80 | ||||
| 16 | Class C4 PCC, 6” Thick, Reinforced | 200 | S.Y. | $40.00 | $8,000.00 | $48.00 | $9,600.00 | $47.00 | $9,400.00 | ||||
| 17 | Floor Drains and Outlet with Rodent Guard | 1 | L.S. | $300.00 | $300.00 | $1,500.00 | $1,500.00 | $750.00 | $750.00 | ||||
| $66,638.10 | $71,225.40 | $72,657.36 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $68,000.00 | Contractor: | TK Concrete Inc | TEK Builders Inc. | Hanson Construction LLC | |||||||||
| Funding Source: 100% F&W Trust-Fisheries Non-Habitat Stamp, | 1608 Fifield Rd | PO Box 632 | PO Box 641 | ||||||||||
| Pella IA 50219 | Mount Ayr IA 50854 | Clear Lake IA 50428 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-628-4590 | 641-464-3972 | 641-357-8171 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Construction Staking | 1 | L.S. | $3,750.00 | $3,750.00 | $2,000.00 | $2,000.00 | $0.00 | $0.00 | ||||
| 2 | Class 13 Excavation, Stockpile, Reuse, & Compact | 171.5 | C.Y. | $24.00 | $4,116.00 | $10.00 | $1,715.00 | $10.00 | $1,715.00 | ||||
| 3 | Class 13 Excavation, to be wasted onsite | 429 | C.Y. | $6.00 | $2,574.00 | $10.00 | $4,290.00 | $5.00 | $2,145.00 | ||||
| 4 | Asphalt Pavement Removal & Disposal | 387 | S.Y. | $8.00 | $3,096.00 | $10.00 | $3,870.00 | $10.00 | $3,870.00 | ||||
| 5 | Special Backfill | 130.5 | Tons | $25.00 | $3,262.50 | $21.00 | $2,740.50 | $35.00 | $4,567.50 | ||||
| 6 | Class C4 PCC, 6” Thick, No Reinforcement | 1030.6 | S.Y. | $30.00 | $30,918.00 | $38.64 | $39,822.384 | $45.00 | $46,377.00 | ||||
| 7 | 2”x4’x8’ Rigid Foam Insulation | 3 | Each | $75.00 | $225.00 | $50.00 | $150.00 | $35.00 | $105.00 | ||||
| 8 | 12” Diameter CMP | 158 | L.F. | $35.00 | $5,530.00 | $28.00 | $4,424.00 | $15.00 | $2,370.00 | ||||
| 9 | Site Restoration, Seed (Urban Mix), Fertilizer, Straw Mulch | 1 | L.S. | $3,500.00 | $3,500.00 | $1,000.00 | $1,000.00 | $3,000.00 | $3,000.00 | ||||
| 10 | Seeding Waste Dirt Site, Native Mix, Fertilizer, Straw Mulch | 0.25 | Acres | $10,000.00 | $2,500.00 | $3,000.00 | $750.00 | $5,000.00 | $1,250.00 | ||||
| 11 | Silt Fence | 65 | L.F. | $3.00 | $195.00 | $4.00 | $260.00 | $10.00 | $650.00 | ||||
| 12 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | ||||
| 13 | Concrete Sidewalk Removal & Disposal | 21.3 | S.Y. | $15.00 | $319.50 | $12.00 | $255.60 | $25.00 | $532.50 | ||||
| 14 | Culvert Removal, 12” CMP | 40 | L.F. | $8.00 | $320.00 | $12.00 | $480.00 | $10.00 | $400.00 | ||||
| 15 | Subgrade Preparation & Compaction | 1230.6 | S.Y. | $2.00 | $2,461.20 | $2.00 | $2,461.20 | $5.00 | $6,153.00 | ||||
| 16 | Class C4 PCC, 6” Thick, Reinforced | 200 | S.Y. | $38.25 | $7,650.00 | $55.00 | $11,000.00 | $40.00 | $8,000.00 | ||||
| 17 | Floor Drains and Outlet with Rodent Guard | 1 | L.S. | $2,000.00 | $2,000.00 | $500.00 | $500.00 | $4,000.00 | $4,000.00 | ||||
| $79,917.20 | $80,718.684 | $90,135.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $68,000.00 | Contractor: | MPS Engineers | Absolute Concrete Construction | ||||||||||
| Funding Source: 100% F&W Trust-Fisheries Non-Habitat Stamp, | 1444 Illinois St | PO Box 148 | |||||||||||
| Des Moines IA 50314 | Slater IA 50244 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 515-221-9832 | 515-228-3030 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Construction Staking | 1 | L.S. | $2,100.00 | $2,100.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| 2 | Class 13 Excavation, Stockpile, Reuse, & Compact | 171.5 | C.Y. | $34.00 | $5,831.00 | $35.00 | $6,002.50 | $0.00 | |||||
| 3 | Class 13 Excavation, to be wasted onsite | 429 | C.Y. | $21.00 | $9,009.00 | $10.00 | $4,290.00 | $0.00 | |||||
| 4 | Asphalt Pavement Removal & Disposal | 387 | S.Y. | $12.00 | $4,644.00 | $10.00 | $3,870.00 | $0.00 | |||||
| 5 | Special Backfill | 130.5 | Tons | $24.00 | $3,132.00 | $20.00 | $2,610.00 | $0.00 | |||||
| 6 | Class C4 PCC, 6” Thick, No Reinforcement | 1030.6 | S.Y. | $39.00 | $40,193.40 | $48.00 | $49,468.80 | $0.00 | |||||
| 7 | 2”x4’x8’ Rigid Foam Insulation | 3 | Each | $45.00 | $135.00 | $100.00 | $300.00 | $0.00 | |||||
| 8 | 12” Diameter CMP | 158 | L.F. | $32.00 | $5,056.00 | $26.00 | $4,108.00 | $0.00 | |||||
| 9 | Site Restoration, Seed (Urban Mix), Fertilizer, Straw Mulch | 1 | L.S. | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | $0.00 | |||||
| 10 | Seeding Waste Dirt Site, Native Mix, Fertilizer, Straw Mulch | 0.25 | Acres | $6,000.00 | $1,500.00 | $6,000.00 | $1,500.00 | $0.00 | |||||
| 11 | Silt Fence | 65 | L.F. | $4.00 | $260.00 | $10.00 | $650.00 | $0.00 | |||||
| 12 | Mobilization | 1 | L.S. | $9,000.00 | $9,000.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
| 13 | Concrete Sidewalk Removal & Disposal | 21.3 | S.Y. | $10.00 | $213.00 | $20.00 | $426.00 | $0.00 | |||||
| 14 | Culvert Removal, 12” CMP | 40 | L.F. | $16.00 | $640.00 | $10.00 | $400.00 | $0.00 | |||||
| 15 | Subgrade Preparation & Compaction | 1230.6 | S.Y. | $3.00 | $3,691.80 | $1.75 | $2,153.55 | $0.00 | |||||
| 16 | Class C4 PCC, 6” Thick, Reinforced | 200 | S.Y. | $52.00 | $10,400.00 | $61.50 | $12,300.00 | $0.00 | |||||
| 17 | Floor Drains and Outlet with Rodent Guard | 1 | L.S. | $2,175.00 | $2,175.00 | $1,300.00 | $1,300.00 | $0.00 | |||||
| $99,980.20 | $108,378.85 | $0.00 | |||||||||||