IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Hawthorn WMA | Date: 7/23/2015 | Project No. |
| Sediment Ponds | County: | MAHASKA | Time: 11:00 AM | 13-05-62-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $325,000.00 | Contractor: | Kinman Company Inc | Hammes Bulldozing Inc. | Stek Earthmoving | |||||||||
| Funding Source: 100% I-JOBS, | 3101 Kent Ave | 16520 Hwy 92 | 1515 Queens Ave | ||||||||||
| Oskaloosa IA 52577 | Sigourney IA 52591 | New Sharon IA 50207 | |||||||||||
| Plan Sets Requested: 13 | Quantities | 641-660-0897 | 641-660-1610 | 641-295-4352 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $6,500.00 | $6,500.00 | $3,000.00 | $3,000.00 | ||||
| 2 | Earthfill - Embankment | 58750 | C.Y. | $1.24 | $72,850.00 | $1.15 | $67,562.50 | $1.96 | $115,150.00 | ||||
| 3 | Earthfill - Core Trence | 2908 | C.Y. | $1.00 | $2,908.00 | $1.15 | $3,344.20 | $1.97 | $5,728.76 | ||||
| 4 | Clearing and Grubbing | 25.8 | Acres | $360.00 | $9,288.00 | $1,100.00 | $28,380.00 | $375.00 | $9,675.00 | ||||
| 5 | Seeding | 6.5 | Acres | $1,520.00 | $9,880.00 | $1,500.00 | $9,750.00 | $2,000.00 | $13,000.00 | ||||
| 6 | Fine Drainfill | 161 | Tons | $21.39 | $3,443.79 | $20.00 | $3,220.00 | $35.00 | $5,635.00 | ||||
| 7 | Riprap | 10 | Tons | $44.31 | $443.10 | $35.00 | $350.00 | $48.00 | $480.00 | ||||
| 8 | 21" Trash Rack | 1 | Each | $1,000.00 | $1,000.00 | $1,800.00 | $1,800.00 | $1,050.00 | $1,050.00 | ||||
| 9 | 48" Trash Rack | 1 | Each | $4,200.00 | $4,200.00 | $2,200.00 | $2,200.00 | $4,450.00 | $4,450.00 | ||||
| 10 | 66" Trash Rack | 1 | Each | $4,700.00 | $4,700.00 | $2,200.00 | $2,200.00 | $4,950.00 | $4,950.00 | ||||
| 11 | 21" CMP | 109 | L.F. | $28.05 | $3,057.45 | $28.00 | $3,052.00 | $31.00 | $3,379.00 | ||||
| 12 | 36" CMP | 114 | L.F. | $44.80 | $5,107.20 | $43.00 | $4,902.00 | $49.00 | $5,586.00 | ||||
| 13 | 48" CMP | 200 | L.F. | $60.50 | $12,100.00 | $65.00 | $13,000.00 | $65.00 | $13,000.00 | ||||
| 14 | 48" Riser | 1 | Each | $1,693.50 | $1,693.50 | $700.00 | $700.00 | $1,700.00 | $1,700.00 | ||||
| 15 | 66" Riser | 1 | Each | $1,976.50 | $1,976.50 | $1,550.00 | $1,550.00 | $2,100.00 | $2,100.00 | ||||
| 16 | 72" x 72" Antiseep | 3 | Each | $320.00 | $960.00 | $300.00 | $900.00 | $500.00 | $1,500.00 | ||||
| 17 | 96" x 96" Antiseep | 2 | Each | $420.00 | $840.00 | $620.00 | $1,240.00 | $650.00 | $1,300.00 | ||||
| 18 | Cattle Barrier | 100 | L.F. | $8.00 | $800.00 | $16.00 | $1,600.00 | $9.00 | $900.00 | ||||
| 19 | Mobilization | 1 | L.S. | $200.00 | $200.00 | $0.00 | $0.00 | $100.00 | $100.00 | ||||
| 20 | Earthfill - Embankment | 13622 | C.Y. | $1.23 | $16,755.06 | $1.15 | $15,665.30 | $1.20 | $16,346.40 | ||||
| 21 | Earthfill - Core Trence | 3545 | C.Y. | $0.95 | $3,367.75 | $1.15 | $4,076.75 | $1.50 | $5,317.50 | ||||
| 22 | Clearing and Grubbing | 7 | Acres | $10.00 | $70.00 | $1,100.00 | $7,700.00 | $150.00 | $1,050.00 | ||||
| 23 | Seeding | 7 | Acres | $1,520.00 | $10,640.00 | $1,500.00 | $10,500.00 | $2,000.00 | $14,000.00 | ||||
| 24 | 18" Trash Rack | 7 | Each | $820.00 | $5,740.00 | $1,800.00 | $12,600.00 | $875.00 | $6,125.00 | ||||
| 25 | 6" CMP | 325 | L.F. | $16.60 | $5,395.00 | $5.50 | $1,787.50 | $22.00 | $7,150.00 | ||||
| 26 | 8" CMP | 193 | L.F. | $19.75 | $3,811.75 | $8.20 | $1,582.60 | $25.00 | $4,825.00 | ||||
| 27 | 12" CMP | 105 | L.F. | $21.30 | $2,236.50 | $13.50 | $1,417.50 | $26.00 | $2,730.00 | ||||
| 28 | 14" CMP | 91 | L.F. | $26.00 | $2,366.00 | $18.15 | $1,651.65 | $30.00 | $2,730.00 | ||||
| 29 | 18" Riser | 6 | Each | $350.00 | $2,100.00 | $190.00 | $1,140.00 | $750.00 | $4,500.00 | ||||
| $191,429.60 | $210,372.00 | $257,457.66 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $325,000.00 | Contractor: | Smith Seeding Inc | Seaton Construction | LeRoy & Sons Inc | |||||||||
| Funding Source: 100% I-JOBS, | 219 N 1st Street | 602 Locust St PO Box 213 | 405 Dunlap St | ||||||||||
| Eldridge IA 52748 | Deep River IA 522220213 | Arcadia IA 51430 | |||||||||||
| Plan Sets Requested: 13 | Quantities | 563-285-2604 | 6415952261 | 712-689-2470 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $17,500.00 | $17,500.00 | $5,000.00 | $5,000.00 | $80,000.00 | $80,000.00 | ||||
| 2 | Earthfill - Embankment | 58750 | C.Y. | $1.88 | $110,450.00 | $1.35 | $79,312.50 | $2.35 | $138,062.50 | ||||
| 3 | Earthfill - Core Trence | 2908 | C.Y. | $2.02 | $5,874.16 | $1.40 | $4,071.20 | $4.00 | $11,632.00 | ||||
| 4 | Clearing and Grubbing | 25.8 | Acres | $700.00 | $18,060.00 | $1,000.00 | $25,800.00 | $3,000.00 | $77,400.00 | ||||
| 5 | Seeding | 6.5 | Acres | $2,000.00 | $13,000.00 | $1,800.00 | $11,700.00 | $2,700.00 | $17,550.00 | ||||
| 6 | Fine Drainfill | 161 | Tons | $50.00 | $8,050.00 | $31.00 | $4,991.00 | $55.00 | $8,855.00 | ||||
| 7 | Riprap | 10 | Tons | $50.00 | $500.00 | $50.00 | $500.00 | $100.00 | $1,000.00 | ||||
| 8 | 21" Trash Rack | 1 | Each | $1,100.00 | $1,100.00 | $2,800.00 | $2,800.00 | $2,500.00 | $2,500.00 | ||||
| 9 | 48" Trash Rack | 1 | Each | $4,000.00 | $4,000.00 | $3,100.00 | $3,100.00 | $3,500.00 | $3,500.00 | ||||
| 10 | 66" Trash Rack | 1 | Each | $4,400.00 | $4,400.00 | $3,700.00 | $3,700.00 | $4,500.00 | $4,500.00 | ||||
| 11 | 21" CMP | 109 | L.F. | $30.00 | $3,270.00 | $29.00 | $3,161.00 | $35.00 | $3,815.00 | ||||
| 12 | 36" CMP | 114 | L.F. | $42.00 | $4,788.00 | $48.00 | $5,472.00 | $50.00 | $5,700.00 | ||||
| 13 | 48" CMP | 200 | L.F. | $60.00 | $12,000.00 | $73.00 | $14,600.00 | $65.00 | $13,000.00 | ||||
| 14 | 48" Riser | 1 | Each | $1,000.00 | $1,000.00 | $1,450.00 | $1,450.00 | $3,500.00 | $3,500.00 | ||||
| 15 | 66" Riser | 1 | Each | $1,200.00 | $1,200.00 | $2,700.00 | $2,700.00 | $5,000.00 | $5,000.00 | ||||
| 16 | 72" x 72" Antiseep | 3 | Each | $360.00 | $1,080.00 | $550.00 | $1,650.00 | $2,000.00 | $6,000.00 | ||||
| 17 | 96" x 96" Antiseep | 2 | Each | $480.00 | $960.00 | $950.00 | $1,900.00 | $3,000.00 | $6,000.00 | ||||
| 18 | Cattle Barrier | 100 | L.F. | $4.00 | $400.00 | $32.00 | $3,200.00 | $40.00 | $4,000.00 | ||||
| 19 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $500.00 | $500.00 | $20,000.00 | $20,000.00 | ||||
| 20 | Earthfill - Embankment | 13622 | C.Y. | $2.21 | $30,104.62 | $1.35 | $18,389.70 | $2.75 | $37,460.50 | ||||
| 21 | Earthfill - Core Trence | 3545 | C.Y. | $2.21 | $7,834.45 | $1.50 | $5,317.50 | $4.25 | $15,066.25 | ||||
| 22 | Clearing and Grubbing | 7 | Acres | $200.00 | $1,400.00 | $7,000.00 | $49,000.00 | $3,000.00 | $21,000.00 | ||||
| 23 | Seeding | 7 | Acres | $2,000.00 | $14,000.00 | $1,600.00 | $11,200.00 | $2,700.00 | $18,900.00 | ||||
| 24 | 18" Trash Rack | 7 | Each | $880.00 | $6,160.00 | $2,700.00 | $18,900.00 | $500.00 | $3,500.00 | ||||
| 25 | 6" CMP | 325 | L.F. | $15.00 | $4,875.00 | $14.00 | $4,550.00 | $17.00 | $5,525.00 | ||||
| 26 | 8" CMP | 193 | L.F. | $19.00 | $3,667.00 | $16.00 | $3,088.00 | $19.00 | $3,667.00 | ||||
| 27 | 12" CMP | 105 | L.F. | $19.00 | $1,995.00 | $22.00 | $2,310.00 | $23.00 | $2,415.00 | ||||
| 28 | 14" CMP | 91 | L.F. | $25.00 | $2,275.00 | $27.00 | $2,457.00 | $30.00 | $2,730.00 | ||||
| 29 | 18" Riser | 6 | Each | $360.00 | $2,160.00 | $495.00 | $2,970.00 | $1,500.00 | $9,000.00 | ||||
| $287,103.23 | $293,789.90 | $531,278.25 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $325,000.00 | Contractor: | Miller Trucking & Excav | |||||||||||
| Funding Source: 100% I-JOBS, | 3033 John Deere Rd | ||||||||||||
| Silvis IL 61282 | |||||||||||||
| Plan Sets Requested: 13 | Quantities | (309) 755-7644 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $75,000.00 | $75,000.00 | $0.00 | $0.00 | ||||||
| 2 | Earthfill - Embankment | 58750 | C.Y. | $15.00 | $881,250.00 | $0.00 | $0.00 | ||||||
| 3 | Earthfill - Core Trence | 2908 | C.Y. | $10.00 | $29,080.00 | $0.00 | $0.00 | ||||||
| 4 | Clearing and Grubbing | 25.8 | Acres | $15,000.00 | $387,000.00 | $0.00 | $0.00 | ||||||
| 5 | Seeding | 6.5 | Acres | $4,000.00 | $26,000.00 | $0.00 | $0.00 | ||||||
| 6 | Fine Drainfill | 161 | Tons | $50.00 | $8,050.00 | $0.00 | $0.00 | ||||||
| 7 | Riprap | 10 | Tons | $150.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 8 | 21" Trash Rack | 1 | Each | $2,680.00 | $2,680.00 | $0.00 | $0.00 | ||||||
| 9 | 48" Trash Rack | 1 | Each | $5,550.00 | $5,550.00 | $0.00 | $0.00 | ||||||
| 10 | 66" Trash Rack | 1 | Each | $6,150.00 | $6,150.00 | $0.00 | $0.00 | ||||||
| 11 | 21" CMP | 109 | L.F. | $90.00 | $9,810.00 | $0.00 | $0.00 | ||||||
| 12 | 36" CMP | 114 | L.F. | $130.00 | $14,820.00 | $0.00 | $0.00 | ||||||
| 13 | 48" CMP | 200 | L.F. | $140.00 | $28,000.00 | $0.00 | $0.00 | ||||||
| 14 | 48" Riser | 1 | Each | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 15 | 66" Riser | 1 | Each | $1,740.00 | $1,740.00 | $0.00 | $0.00 | ||||||
| 16 | 72" x 72" Antiseep | 3 | Each | $3,000.00 | $9,000.00 | $0.00 | $0.00 | ||||||
| 17 | 96" x 96" Antiseep | 2 | Each | $5,000.00 | $10,000.00 | $0.00 | $0.00 | ||||||
| 18 | Cattle Barrier | 100 | L.F. | $20.00 | $2,000.00 | $0.00 | $0.00 | ||||||
| 19 | Mobilization | 1 | L.S. | $25,000.00 | $25,000.00 | $0.00 | $0.00 | ||||||
| 20 | Earthfill - Embankment | 13622 | C.Y. | $15.00 | $204,330.00 | $0.00 | $0.00 | ||||||
| 21 | Earthfill - Core Trence | 3545 | C.Y. | $10.00 | $35,450.00 | $0.00 | $0.00 | ||||||
| 22 | Clearing and Grubbing | 7 | Acres | $12,000.00 | $84,000.00 | $0.00 | $0.00 | ||||||
| 23 | Seeding | 7 | Acres | $4,000.00 | $28,000.00 | $0.00 | $0.00 | ||||||
| 24 | 18" Trash Rack | 7 | Each | $1,300.00 | $9,100.00 | $0.00 | $0.00 | ||||||
| 25 | 6" CMP | 325 | L.F. | $57.00 | $18,525.00 | $0.00 | $0.00 | ||||||
| 26 | 8" CMP | 193 | L.F. | $57.00 | $11,001.00 | $0.00 | $0.00 | ||||||
| 27 | 12" CMP | 105 | L.F. | $57.00 | $5,985.00 | $0.00 | $0.00 | ||||||
| 28 | 14" CMP | 91 | L.F. | $65.00 | $5,915.00 | $0.00 | $0.00 | ||||||
| 29 | 18" Riser | 6 | Each | $1,020.00 | $6,120.00 | $0.00 | $0.00 | ||||||
| $1,932,556.00 | $0.00 | $0.00 | |||||||||||
10/17/2026