| Bids For: | Location: | Big Creek Enforcement | Date: 10/18/2012 | Project No. |
| Storage and Office Building | County: | POLK | Time: 11:00 am | 10-02-77-09 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $350,000.00 | Contractor: | TK Concrete Inc | R.H. Grabau Construction, Inc. | Edge Commercial | |||||||||
| Funding Source: 67% Marine Fuel Tax, 33% F&W Trust - Other, | 1608 Fifield Rd | 871 P Ave 99 | 3155 SE Miehe Dr, Ste 2 | ||||||||||
| Pella IA 50219 | Boone IA 50036 | Grimes IA 50111 | |||||||||||
| Plan Sets Requested: 4 | Quantities | 641-628-4590 | 515-432-6935 | 515-986-2229 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | ON-SITE TOPSOIL (STRIP, SALVAGE & RESPREAD) | 660 | C.Y. | $9.00 | $5,940.00 | $7.58 | $5,002.80 | $17.34 | $11,444.40 | ||||
| 2 | EXCAVATION CLASS 10 (INCLUDES 580 CY BORROW) | 940 | C.Y. | $17.50 | $16,450.00 | $10.64 | $10,001.60 | $14.58 | $13,705.20 | ||||
| 3 | MODIFIED SUBBASE | 65 | Tons | $30.00 | $1,950.00 | $30.77 | $2,000.05 | $150.94 | $9,811.10 | ||||
| 4 | WATER SERVICE | 1 | Each | $4,000.00 | $4,000.00 | $14,000.00 | $14,000.00 | $20,653.00 | $20,653.00 | ||||
| 5 | 12" RCP | 114 | L.F. | $50.00 | $5,700.00 | $175.44 | $20,000.16 | $39.19 | $4,467.66 | ||||
| 6 | 12" CONCRETE PIPE APRON | 6 | Each | $850.00 | $5,100.00 | $1,333.33 | $7,999.98 | $874.00 | $5,244.00 | ||||
| 7 | 6" PCC PAVEMENT | 308 | S.Y. | $36.00 | $11,088.00 | $81.17 | $25,000.36 | $113.87 | $35,071.96 | ||||
| 8 | GRANULAR SURFACING | 362 | Tons | $25.00 | $9,050.00 | $22.10 | $8,000.20 | $29.89 | $10,820.18 | ||||
| 9 | CONVENTIONAL SEEDING (NATIVE GRASS & WILDFLOWER) | 0.4 | Acres | $5,000.00 | $2,000.00 | $3,750.00 | $1,500.00 | $5,542.50 | $2,217.00 | ||||
| 10 | SILT FENCE | 310 | L.F. | $3.00 | $930.00 | $1.61 | $499.10 | $2.80 | $868.00 | ||||
| 11 | ELECTRIC SERVICE | 1 | Each | $6,000.00 | $6,000.00 | $2,000.00 | $2,000.00 | $10,963.00 | $10,963.00 | ||||
| 12 | BUILDING (SIPS & POST-FRAME) & ALL BUILDING RELATED ITEMS | 1 | L.S. | $280,000.00 | $280,000.00 | $347,199.00 | $347,199.00 | $455,288.00 | $455,288.00 | ||||
| $348,208.00 | $443,203.25 | $580,553.50 | |||||||||||