IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Big Creek State Park | Date: 9/20/2012 | Project No. |
| Beach Renovation Project | County: | POLK | Time: 11:00 a.m. | 13-02-77-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $1,500,000.00 | Contractor: | Lansink Construction Inc. | Bergstrom Construction Inc | Rochon Corporation of Iowa Inc. | |||||||||
| Funding Source: 100% Infrastructure 2013, | 5967 Merle Hay Rd | 1719 Hull Ave | 3401 - 106th Circle | ||||||||||
| Johnston IA 50131 | Des Moines IA 50313 | Urbandale IA 50322 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 515-270-8506 | 515-266-5146 | 515-278-9446 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $117,408.00 | $117,408.00 | $252,000.00 | $252,000.00 | ||||
| 2 | Earthwork | 1 | L.S. | $30,000.00 | $30,000.00 | $35,763.00 | $35,763.00 | $77,000.00 | $77,000.00 | ||||
| 3 | Sanitary Sewer Service, Trenched, 6" PVC | 340 | L.F. | $150.00 | $51,000.00 | $71.00 | $24,140.00 | $70.00 | $23,800.00 | ||||
| 4 | Sanitary Sewer, Cleanout, 6" Diam | 3 | Each | $400.00 | $1,200.00 | $455.00 | $1,365.00 | $450.00 | $1,350.00 | ||||
| 5 | Connection to Existing Manhole | 2 | Each | $500.00 | $1,000.00 | $1,854.00 | $3,708.00 | $2,500.00 | $5,000.00 | ||||
| 6 | Water Service Pipe,2" Diam | 346 | L.F. | $20.00 | $6,920.00 | $25.00 | $8,650.00 | $85.00 | $29,410.00 | ||||
| 7 | Water Service Pipe, 1" Diam | 487 | L.F. | $19.00 | $9,253.00 | $14.00 | $6,818.00 | $78.00 | $37,986.00 | ||||
| 8 | Water Main Connection, 4" x 2" | 1 | Each | $600.00 | $600.00 | $2,068.00 | $2,068.00 | $2,500.00 | $2,500.00 | ||||
| 9 | Water Main Connection, 3" x 2" | 2 | Each | $600.00 | $1,200.00 | $2,068.00 | $4,136.00 | $2,500.00 | $5,000.00 | ||||
| 10 | Manhole, SW-301 (48" Diam) | 1 | Each | $14,000.00 | $14,000.00 | $6,662.00 | $6,662.00 | $4,500.00 | $4,500.00 | ||||
| 11 | Intake, Type SW-501, Top Only | 1 | Each | $3,000.00 | $3,000.00 | $2,299.00 | $2,299.00 | $2,200.00 | $2,200.00 | ||||
| 12 | Intake, Type SW-512, (24" Diam) | 1 | Each | $3,000.00 | $3,000.00 | $2,299.00 | $2,299.00 | $2,200.00 | $2,200.00 | ||||
| 13 | Intake, Pourous Fill Drain Pit | 1 | Each | $1,000.00 | $1,000.00 | $3,025.00 | $3,025.00 | $3,800.00 | $3,800.00 | ||||
| 14 | Intake, Trench Drain | 2 | Each | $1,500.00 | $3,000.00 | $1,743.00 | $3,486.00 | $1,700.00 | $3,400.00 | ||||
| 15 | Storm Sewer, Treanched, CMP, 12" Diam | 73 | L.F. | $42.00 | $3,066.00 | $95.00 | $6,935.00 | $110.00 | $8,030.00 | ||||
| 16 | PCC Curb & Gutter, 30" | 335 | L.F. | $25.00 | $8,375.00 | $28.00 | $9,380.00 | $24.00 | $8,040.00 | ||||
| 17 | Sidewalk, PCC 6" | 4812 | S.Y. | $50.00 | $240,600.00 | $58.00 | $279,096.00 | $47.00 | $226,164.00 | ||||
| 18 | Sidewalk, PCC 7" | 50 | S.Y. | $60.00 | $3,000.00 | $63.00 | $3,150.00 | $53.00 | $2,650.00 | ||||
| 19 | Detectable Warnings | 206 | S.F. | $25.00 | $5,150.00 | $27.00 | $5,562.00 | $23.00 | $4,738.00 | ||||
| 20 | Driveway, PCC, Type 1, 7" | 130 | S.Y. | $50.00 | $6,500.00 | $58.00 | $7,540.00 | $47.00 | $6,110.00 | ||||
| 21 | Stormwater Pollution Prevention Plan (SWPPP) | 1 | L.S. | $6,000.00 | $6,000.00 | $5,120.00 | $5,120.00 | $12,000.00 | $12,000.00 | ||||
| 22 | Silt Fence, Indtallation & Removal | 700 | L.F. | $3.00 | $2,100.00 | $4.00 | $2,800.00 | $3.50 | $2,450.00 | ||||
| 23 | Construction Survey | 1 | L.S. | $6,000.00 | $6,000.00 | $12,165.00 | $12,165.00 | $4,500.00 | $4,500.00 | ||||
| 24 | Drinking Fountain | 1 | Each | $3,000.00 | $3,000.00 | $3,095.00 | $3,095.00 | $2,300.00 | $2,300.00 | ||||
| 25 | Yard Hydrant | 4 | Each | $1,000.00 | $4,000.00 | $2,540.00 | $10,160.00 | $1,300.00 | $5,200.00 | ||||
| 26 | Shelter, Nominal 40'x68', Romtec Iowa DNR Custom | 3 | Each | $150,000.00 | $450,000.00 | $119,452.00 | $358,356.00 | $98,700.00 | $296,100.00 | ||||
| 27 | Restroom, Nominal 18'x24', Romtec Iowa DNR Custom | 3 | Each | $160,000.00 | $480,000.00 | $139,288.00 | $417,864.00 | $123,100.00 | $369,300.00 | ||||
| 28 | Cabanas, Nominal 13'x13', Romtec Iowa DNR Custom | 9 | Each | $23,000.00 | $207,000.00 | $31,772.00 | $285,948.00 | $26,400.00 | $237,600.00 | ||||
| 29 | storage Building, Nominal 20'x30', As Shown on Plans | 1 | Each | $36,000.00 | $36,000.00 | $60,928.00 | $60,928.00 | $52,000.00 | $52,000.00 | ||||
| 30 | Kiosk, As Shown On Plans | 1 | Each | $10,000.00 | $10,000.00 | $19,454.00 | $19,454.00 | $24,500.00 | $24,500.00 | ||||
| 31 | Bike Racks, S.S., Huntco BR11 | 3 | Each | $1,200.00 | $3,600.00 | $1,356.00 | $4,068.00 | $1,800.00 | $5,400.00 | ||||
| 32 | Benches, Kay Contour 6' Douglas Fir 3x4 | 25 | Each | $500.00 | $12,500.00 | $704.00 | $17,600.00 | $2,000.00 | $50,000.00 | ||||
| 33 | Site Lighting, Kim Archetecture LED w 20' Pole | 3 | Each | $5,000.00 | $15,000.00 | $5,223.00 | $15,669.00 | $4,100.00 | $12,300.00 | ||||
| $1,637,064.00 | $1,746,717.00 | $1,779,528.00 | |||||||||||