IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Iowa Great Lakes | Date: 9/25/2012 | Project No. |
| Electric Fish Barrier | County: | DICKINSON | Time: 11:00 a.m. | 13-01-30-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $627,464.00 | Contractor: | Christensen Construction & Design Company, Inc | Graves Construction Company Inc. | Dixon Construction Company | |||||||||
| Funding Source: 70% Marine Fuel Tax, 30% Other, | 821 S 28th St | 1810 340th St | 409 Driftwood St | ||||||||||
| Estherville IA 51334 | Spencer IA 51301 | Correctionville IA 51016 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 712-362-7755 | 712-262-2403 | 712-372-4224 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Testing and Inspecting, supervision of earthwork for cut to fill and fill import locations | 2 | Day | $455.00 | $910.00 | $850.00 | $1,700.00 | $1,000.00 | $2,000.00 | ||||
| 2 | Field Density Testing to subbase access road , set of three samples | 3 | Each | $650.00 | $1,950.00 | $350.00 | $1,050.00 | $250.00 | $750.00 | ||||
| 3 | Concrete testing, aggregates, abrasion, ASTM C 131 for InsulcreteTM and control building slab | 2 | Each | $390.00 | $780.00 | $250.00 | $500.00 | $250.00 | $500.00 | ||||
| 4 | Concrete testing, water cement ratio curve, 3 batches for InsulcreteTM and control building slab. | 1 | Each | $390.00 | $390.00 | $250.00 | $250.00 | $250.00 | $250.00 | ||||
| 5 | Office Trailer, furnished, rent per month, 20' x 8', excl. hookups. | 3 | Each | $3.333 | $9.999 | $4,500.00 | $13,500.00 | $1,000.00 | $3,000.00 | ||||
| 6 | Modular office building, delivery, each way. | 2 | Each | $5.00 | $10.00 | $2,500.00 | $5,000.00 | $250.00 | $500.00 | ||||
| 7 | Field Office Expense, office equipment rental, average | 3 | Mo. | $3.333 | $9.999 | $1,000.00 | $3,000.00 | $100.00 | $300.00 | ||||
| 8 | Field Office Expense, office supplies, average. | 3 | Mo. | $3.333 | $9.999 | $250.00 | $750.00 | $50.00 | $150.00 | ||||
| 9 | Field Office Expense, telephone bill; avg. bill/month, incl. long distance | 2 | Mo. | $5.00 | $10.00 | $125.00 | $250.00 | $50.00 | $100.00 | ||||
| 10 | Field Office Expense, field office lights & HVAC. | 3 | Mo. | $3.333 | $9.999 | $1,500.00 | $4,500.00 | $50.00 | $150.00 | ||||
| 11 | Temporary access road, gravel fill, 4" gravel depth, excl surfacing | 208 | S.Y. | $0.048 | $10.005 | $8.00 | $1,664.00 | $10.00 | $2,080.00 | ||||
| 12 | Project signs, sign, high intensity reflectorized, buy, incl. Posts | 12 | S.F. | $54.166 | $649.992 | $65.00 | $780.00 | $100.00 | $1,200.00 | ||||
| 13 | Boundary & survey markers, crew for building layout, 2 person crew | 2 | Day | $5.00 | $10.00 | $1,800.00 | $3,600.00 | $500.00 | $1,000.00 | ||||
| 14 | Cleaning up, cleanup of job site, final by GC at end of job | 10 | M.S.F. | $260.00 | $2,600.00 | $200.00 | $2,000.00 | $10.00 | $100.00 | ||||
| 15 | Partial wing-wall demolition on both the north and south side of the waterway, remove concrete walls, plain concrete, 12" thick, including disposal co | 144 | S.F. | $45.138 | $6,499.872 | $30.00 | $4,320.00 | $50.00 | $7,200.00 | ||||
| 16 | C.I.P. concrete forms, slab on grade, edge, wood, 12" high, 1 use, includes erecting, bracing, stripping and cleaning | 1328 | S.F.C.A. | $13.651 | $18,127.997 | $5.00 | $6,640.00 | $10.00 | $13,280.00 | ||||
| 17 | C.I.P. concrete forms, wing- wall, battered, job built plywood, to 8' high, 1 use, includes erecting, bracing, stripping and cleaning | 600 | S.F.C.A. | $25.52 | $15,312.00 | $7.00 | $4,200.00 | $20.00 | $12,000.00 | ||||
| 18 | Epoxy coating, for reinforcing steel, add to fabricated & delivered price for coating with epoxy | 1.08 | Tons | $1,535.185 | $1,658.00 | $500.00 | $540.00 | $200.00 | $216.00 | ||||
| 19 | Insulative concrete (InsulcreteTM), ready mix, normal weight, includes local aggregate, sand, Portland cement and water, delivered, including all addi | 297 | C.Y. | $260.00 | $77,220.00 | $875.00 | $259,875.00 | $800.00 | $237,600.00 | ||||
| 20 | Structural concrete, ready mix, normal weight, 4000 PSI, includes local aggregate, sand, Portland cement and water, delivered, including all additives | 4 | C.Y. | $130.00 | $520.00 | $175.00 | $700.00 | $500.00 | $2,000.00 | ||||
| 21 | Shotcrete, wet mix, fiber reinforced 3000 psi, 2" thick including delivery and installation. | 5976 | S.F. | $3.045 | $18,196.92 | $2.00 | $11,952.00 | $3.00 | $17,928.00 | ||||
| 22 | Fiberglass Castings, square tube, 4" x 4" x 1/4" thick for electrode wire raceway to the top of newly formed wing-walls | 24 | L.F. | $135.42 | $3,250.08 | $300.00 | $7,200.00 | $200.00 | $4,800.00 | ||||
| 23 | Electrode mild steel plate, structural, for connections & stiffeners, 3/4" T, shop fabricated, uncoated including delivery and installation | 466 | S.F. | $50.214 | $23,399.724 | $65.00 | $30,290.00 | $100.00 | $46,600.00 | ||||
| 24 | Anchor bolts (Hilti Hus-h)single, 16.5mm diameter x 135mm long, installed in fresh concrete (InsulcreteTM), includes nut and washer including delivery | 312 | Each | $7.916 | $2,469.792 | $6.00 | $1,872.00 | $20.00 | $6,240.00 | ||||
| 25 | Topsoil stripping and stockpiling, topsoil, sandy loam, ideal conditions, 200 H.P. dozer | 163 | C.Y. | $13.00 | $2,119.00 | $3.00 | $489.00 | $20.00 | $3,260.00 | ||||
| 26 | Fine grading, slopes, gentle, finish grading. | 1471 | S.Y. | $3.535 | $5,199.985 | $5.00 | $7,355.00 | $1.00 | $1,471.00 | ||||
| 27 | Synthetic erosion control, silt fence, polypropylene, ideal conditions, 3' high. | 361 | L.F. | $3.90 | $1,407.90 | $5.00 | $1,805.00 | $4.50 | $1,624.50 | ||||
| 28 | Synthetic erosion control, paper hydromulch. | 1471 | S.Y. | $1.817 | $2,672.807 | $2.10 | $3,089.10 | $1.00 | $1,471.00 | ||||
| 29 | Provide sheet piling, steel, 22 psf, 15' excavation, per ton, drive, extract and salvage, including wales. | 6 | Tons | $2,288.00 | $13,728.00 | $500.00 | $3,000.00 | $100.00 | $600.00 | ||||
| 30 | Mobilization | 1 | Each | $82,229.00 | $82,229.00 | $65,000.00 | $65,000.00 | $200,000.00 | $200,000.00 | ||||
| 31 | Demobilization | 1 | Each | $14,040.00 | $14,040.00 | $20,000.00 | $20,000.00 | $49,000.00 | $49,000.00 | ||||
| 32 | Reinforcing Steel, western mill, A615, grade 60, mill base price, material and delivery | 1.08 | Tons | $1,300.00 | $1,404.00 | $4,500.00 | $4,860.00 | $1,600.00 | $1,728.00 | ||||
| 33 | Reinforcing Steel, average price, cut, bent and delivered, A615, grade 60, material only | 1.08 | Tons | $1,560.185 | $1,685.00 | $500.00 | $540.00 | $200.00 | $216.00 | ||||
| 34 | Reinforcing bars, glass fiber reinforced polymer, #5 bar, 0.258 lb./L.F., including labor and material for accessories. | 23206 | L.F. | $2.016 | $46,783.296 | $1.42 | $32,952.52 | $4.00 | $92,824.00 | ||||
| 35 | Excavating, chain trencher, utility trench, common earth, 8" wide, 24" deep, backfill by hand, includes bed material and compaction. | 300 | L.F. | $15.60 | $4,680.00 | $12.00 | $3,600.00 | $2.50 | $750.00 | ||||
| 36 | Load and deliver bank run gravel for concrete barrier slab and wing-wall foundation haul 2 miles, spread with 200 H.P. dozer | 930 | Tons | $14.301 | $13,299.93 | $16.00 | $14,880.00 | $20.00 | $18,600.00 | ||||
| 37 | Borrow, material only, bank run gravel for concrete barrier slab and wing-wall foundation. | 930 | Tons | $19.50 | $18,135.00 | $30.00 | $27,900.00 | $30.00 | $27,900.00 | ||||
| 38 | Compaction, riding, vibrating roller, 2 passes, 8" lifts | 585 | E.C.Y. | $1.30 | $760.50 | $5.00 | $2,925.00 | $5.00 | $2,925.00 | ||||
| 39 | Supply, deliver and place 6" erosion stone minors to downstream edge of concrete slab. | 92 | C.Y. | $133.532 | $12,284.944 | $85.00 | $7,820.00 | $100.00 | $9,200.00 | ||||
| 40 | Geosynthetic soil stabilization, geotextile fabric, woven, 200 lb. tensile strength | 5257 | S.Y. | $4.451 | $23,398.907 | $6.86 | $36,063.02 | $0.50 | $2,628.50 | ||||
| 41 | Supply, deliver and place 8" thick subbase for new access road | 540 | S.Y. | $11.507 | $6,213.78 | $19.00 | $10,260.00 | $5.00 | $2,700.00 | ||||
| 42 | Supply, deliver and erect 8' high chain link fence | 217 | L.F. | $49.723 | $10,789.891 | $38.96 | $8,454.32 | $38.20 | $8,289.40 | ||||
| 43 | Supply, deliver and erect single chain link gates | 2 | Each | $793.00 | $1,586.00 | $623.00 | $1,246.00 | $610.00 | $1,220.00 | ||||
| 44 | Supply, deliver and erect double gate entry to control building | 1 | Each | $1,586.00 | $1,586.00 | $1,244.00 | $1,244.00 | $1,220.00 | $1,220.00 | ||||
| 45 | Supply, deliver and install Schedule 40 conduit to barrier | 846 | L.F. | $26.845 | $22,710.87 | $21.27 | $17,994.42 | $2.00 | $1,692.00 | ||||
| 46 | Subbase material for access road, loaded at the pit, prices per ton, includes material only | 215 | Tons | $14.302 | $3,074.93 | $21.00 | $4,515.00 | $25.00 | $5,375.00 | ||||
| 47 | Borrow, delivery charge, minimum 20 tons, 1 hour round trip | 215 | Tons | $9.102 | $1,956.93 | $6.00 | $1,290.00 | $5.00 | $1,075.00 | ||||
| 48 | Supply and install control building including all fixtures and communication with the electricity and communication service providers | 1 | Each | $66,040.00 | $66,040.00 | $42,530.00 | $42,530.00 | $87,000.00 | $87,000.00 | ||||
| 49 | Manufacture, supply and deliver SRI fish barrier equipment | 1 | Each | $311,300.00 | $311,300.00 | $301,000.00 | $301,000.00 | $307,000.00 | $307,000.00 | ||||
| $843,101.047 | $986,945.38 | $1,189,713.40 | |||||||||||