IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Muskrat Slough | Date: 10/25/2012 | Project No. |
| dike design and construction | County: | JONES | Time: 3:00 p.m. | 12-06-53-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Taylor Construction Inc. | Connolly Construction Inc. | ||||||||||
| Funding Source: 100% Federal-NAWCA, | 7314 Columbus St | 18409 N Cascade Rd | |||||||||||
| New Vienna IA 52065 | Peosta IA 52068 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-921-2315 | 563-876-3225 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $5,200.00 | $5,200.00 | $0.00 | |||||
| 2 | Stripping, salvaging, spreading topsoil | 5 | Acres | $1,500.00 | $7,500.00 | $6,465.00 | $32,325.00 | $0.00 | |||||
| 3 | Embankment in place, Type A compaction. | 550 | C.Y. | $20.00 | $11,000.00 | $8.90 | $4,895.00 | $0.00 | |||||
| 4 | 12” Solid steel pipe, Sch 80 | 78 | L.F. | $60.00 | $4,680.00 | $100.00 | $7,800.00 | $0.00 | |||||
| 5 | 12” “Agri Drain” Inline Water Level Control Structure, 12’. | 1 | Each | $3,700.00 | $3,700.00 | $4,200.00 | $4,200.00 | $0.00 | |||||
| 6 | Seeding, Fertilizing and Mulching | 5 | Acres | $1,400.00 | $7,000.00 | $2,000.00 | $10,000.00 | $0.00 | |||||
| 7 | 3' X 3' X 1/2" steel, anti-seep collar | 1 | Each | $500.00 | $500.00 | $285.00 | $285.00 | $0.00 | |||||
| $39,380.00 | $64,705.00 | $0.00 | |||||||||||
10/14/2026