IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | D.U. Marsh | Date: 5/17/2012 | Project No. |
| repair water control structure | County: | CLAY | Time: 3:00 p.m. | 12-01-21-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $17,000.00 | Contractor: | Christian Brothers Excavating | Redings Gravel & Excavating | ||||||||||
| Funding Source: 100% F&W Trust - Other, | 2070 485th St | 2001 East Oak St PO Box 158 | |||||||||||
| Sioux Rapids IA 50585 | Algona IA 50511 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-390-4001 | 515-295-3661 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,300.00 | $1,300.00 | $2,920.00 | $2,920.00 | $0.00 | |||||
| 2 | 12" Dual Wall P.E. Tubing (non perf) | 180 | L.F. | $15.50 | $2,790.00 | $23.00 | $4,140.00 | $0.00 | |||||
| 3 | 15" CMP | 20 | L.F. | $23.00 | $460.00 | $28.00 | $560.00 | $0.00 | |||||
| 4 | Fieldstone Rip Rap (12" to 18") | 10 | Tons | $50.00 | $500.00 | $120.00 | $1,200.00 | $0.00 | |||||
| 5 | 64"x43" CMP Arch Pipe | 24 | L.F. | $340.00 | $8,160.00 | $810.00 | $19,440.00 | $0.00 | |||||
| 6 | Arch Pipe Concrete Collar | 1 | L.S. | $1,500.00 | $1,500.00 | $1,200.00 | $1,200.00 | $0.00 | |||||
| 7 | 12"x 12" Water Control Structure | 1 | L.S. | $2,100.00 | $2,100.00 | $2,370.00 | $2,370.00 | $0.00 | |||||
| 8 | 8" Sch 40 PVC | 19 | L.F. | $45.00 | $855.00 | $64.00 | $1,216.00 | $0.00 | |||||
| $17,665.00 | $33,046.00 | $0.00 | |||||||||||