| Bids For: | Location: | Big Creek State Park | Date: 11/15/2012 | Project No. |
| Replacement of Trails Building | County: | POLK | Time: 11:00 am | 13-02-77-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $500,000.00 | Contractor: | Larry Elwood Construction | R.H. Grabau Construction, Inc. | Hanson Construction, LLC | |||||||||
| Funding Source: 87% Executive Council, 13% Infrastructure 2013, | 2401 S Federal | 871 P Avenue | 614 | ||||||||||
| Mason City IA 50401 | Boone IA 50036 | Clear Lake IA 50428 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 641-423-3261 | 515-432-6935 | 641-357-8171 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | EXCAVATION CLASS 10 | 1 | L.S. | $1,545.00 | $1,545.00 | $8,000.00 | $8,000.00 | $2,000.00 | $2,000.00 | ||||
| 2 | MODIFIED BASE | 31.3 | Tons | $20.40 | $638.52 | $38.33 | $1,199.729 | $40.00 | $1,252.00 | ||||
| 3 | WATER SERVICE | 1 | Each | $2,575.00 | $2,575.00 | $0.00 | $0.00 | $5,000.00 | $5,000.00 | ||||
| 4 | 6" P.C.C. PAVEMENT | 149.3 | S.Y. | $61.28 | $9,149.104 | $133.96 | $20,000.228 | $75.00 | $11,197.50 | ||||
| 5 | 4" P.C.C. SIDEWALK | 31.1 | S.Y. | $42.06 | $1,308.066 | $19.30 | $600.23 | $70.06 | $2,178.866 | ||||
| 6 | DEMOLITION WORK (INCLUDES SITE RESTORATION) | 1 | L.S. | $4,635.00 | $4,635.00 | $2,000.00 | $2,000.00 | $8,000.00 | $8,000.00 | ||||
| 7 | BUILDING SYSTEM (SIPS) AND ALL ASSOCIATED EQUIPMENT & FINISHES (ARCH., ELECTRICAL, MECHANICAL, PLUMBING) | 1 | L.S. | $311,000.00 | $311,000.00 | $329,947.00 | $329,947.00 | $365,000.00 | $365,000.00 | ||||
| $330,850.69 | $361,747.187 | $394,628.366 | |||||||||||
| Alternate | |||||||||||||
| 8 | ALTERNATE #1: SUPPLEMENTAL BAY 108 AND ALL ASSOCIATED EQUIPMENT | 1 | L.S. | $75,325.00 | $75,325.00 | $83,400.00 | $83,400.00 | $62,000.00 | $62,000.00 | ||||
| $406,175.69 | $445,147.187 | $456,628.366 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $500,000.00 | Contractor: | Septagon Construction Co., Inc. | Lansink Construction, Inc. | Prostruct Construction, Inc. | |||||||||
| Funding Source: 87% Executive Council, 13% Infrastructure 2013, | 2950 SE Gateway Dr | 5967 Merle Hay Rd | 4920 Pleasant St, Ste #2 | ||||||||||
| Grimes IA 50111 | Johnston IA 50131 | West Des Moines IA 50266 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 515-986-7313 | 515-270-8506 | 515-267-0177 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | EXCAVATION CLASS 10 | 1 | L.S. | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 | $2,651.00 | $2,651.00 | ||||
| 2 | MODIFIED BASE | 31.3 | Tons | $25.80 | $807.54 | $30.00 | $939.00 | $42.00 | $1,314.60 | ||||
| 3 | WATER SERVICE | 1 | Each | $1,500.00 | $1,500.00 | $2,842.00 | $2,842.00 | $3,022.00 | $3,022.00 | ||||
| 4 | 6" P.C.C. PAVEMENT | 149.3 | S.Y. | $51.00 | $7,614.30 | $75.00 | $11,197.50 | $66.75 | $9,965.775 | ||||
| 5 | 4" P.C.C. SIDEWALK | 31.1 | S.Y. | $73.50 | $2,285.85 | $65.00 | $2,021.50 | $42.96 | $1,336.056 | ||||
| 6 | DEMOLITION WORK (INCLUDES SITE RESTORATION) | 1 | L.S. | $8,000.00 | $8,000.00 | $8,000.00 | $8,000.00 | $1,548.00 | $1,548.00 | ||||
| 7 | BUILDING SYSTEM (SIPS) AND ALL ASSOCIATED EQUIPMENT & FINISHES (ARCH., ELECTRICAL, MECHANICAL, PLUMBING) | 1 | L.S. | $365,692.31 | $365,692.31 | $365,000.00 | $365,000.00 | $383,114.00 | $383,114.00 | ||||
| Alternate | |||||||||||||
| 8 | ALTERNATE #1: SUPPLEMENTAL BAY 108 AND ALL ASSOCIATED EQUIPMENT | 1 | L.S. | $77,000.00 | $77,000.00 | $82,000.00 | $82,000.00 | $80,253.33 | $80,253.33 | ||||
| $466,900.00 | $477,000.00 | $483,204.761 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $500,000.00 | Contractor: | Lang Construction Group, Inc. | Blue Ribbon Builders | TK Concrete Inc. | |||||||||
| Funding Source: 87% Executive Council, 13% Infrastructure 2013, | 1601 West Lakes Pkwy #100 | 1840 137th Ln | 1608 Fifield Rd | ||||||||||
| West Des Moines IA 50266 | Earlham IA 50072 | Pella IA 50219 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 515-645-9680 | 515-371-0754 | 641-628-4590 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | EXCAVATION CLASS 10 | 1 | L.S. | $2,003.00 | $2,003.00 | $2,160.00 | $2,160.00 | $5,000.00 | $5,000.00 | ||||
| 2 | MODIFIED BASE | 31.3 | Tons | $26.68 | $835.084 | $21.09 | $660.117 | $30.00 | $939.00 | ||||
| 3 | WATER SERVICE | 1 | Each | $3,000.00 | $3,000.00 | $5,200.00 | $5,200.00 | $10,000.00 | $10,000.00 | ||||
| 4 | 6" P.C.C. PAVEMENT | 149.3 | S.Y. | $71.40 | $10,660.02 | $62.40 | $9,316.32 | $60.00 | $8,958.00 | ||||
| 5 | 4" P.C.C. SIDEWALK | 31.1 | S.Y. | $49.00 | $1,523.90 | $54.00 | $1,679.40 | $41.00 | $1,275.10 | ||||
| 6 | DEMOLITION WORK (INCLUDES SITE RESTORATION) | 1 | L.S. | $8,352.00 | $8,352.00 | $11,880.00 | $11,880.00 | $20,000.00 | $20,000.00 | ||||
| 7 | BUILDING SYSTEM (SIPS) AND ALL ASSOCIATED EQUIPMENT & FINISHES (ARCH., ELECTRICAL, MECHANICAL, PLUMBING) | 1 | L.S. | $398,526.00 | $398,526.00 | $392,600.00 | $392,600.00 | $425,250.00 | $425,250.00 | ||||
| Alternate | |||||||||||||
| 8 | ALTERNATE #1: SUPPLEMENTAL BAY 108 AND ALL ASSOCIATED EQUIPMENT | 1 | L.S. | $71,500.00 | $71,500.00 | $100,887.00 | $100,887.00 | $85,000.00 | $85,000.00 | ||||
| $496,400.004 | $524,382.837 | $556,422.10 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $500,000.00 | Contractor: | Jensen Builders, Ltd. | TBB, L.C. | ||||||||||
| Funding Source: 87% Executive Council, 13% Infrastructure 2013, | 1175 South 32nd St | 425 28th St | |||||||||||
| Fort Dodge IA 50501 | Des Moines IA 50312 | ||||||||||||
| Plan Sets Requested: 5 | Quantities | 515-573-3292 | 515-240-4504 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | EXCAVATION CLASS 10 | 1 | L.S. | $6,000.00 | $6,000.00 | $28,000.00 | $28,000.00 | $0.00 | |||||
| 2 | MODIFIED BASE | 31.3 | Tons | $41.60 | $1,302.08 | $40.00 | $1,252.00 | $0.00 | |||||
| 3 | WATER SERVICE | 1 | Each | $2,000.00 | $2,000.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| 4 | 6" P.C.C. PAVEMENT | 149.3 | S.Y. | $57.13 | $8,529.509 | $70.00 | $10,451.00 | $0.00 | |||||
| 5 | 4" P.C.C. SIDEWALK | 31.1 | S.Y. | $48.23 | $1,499.953 | $50.00 | $1,555.00 | $0.00 | |||||
| 6 | DEMOLITION WORK (INCLUDES SITE RESTORATION) | 1 | L.S. | $3,000.00 | $3,000.00 | $25,000.00 | $25,000.00 | $0.00 | |||||
| 7 | BUILDING SYSTEM (SIPS) AND ALL ASSOCIATED EQUIPMENT & FINISHES (ARCH., ELECTRICAL, MECHANICAL, PLUMBING) | 1 | L.S. | $475,668.46 | $475,668.46 | $436,000.00 | $436,000.00 | $0.00 | |||||
| Alternate | |||||||||||||
| 8 | ALTERNATE #1: SUPPLEMENTAL BAY 108 AND ALL ASSOCIATED EQUIPMENT | 1 | L.S. | $100,000.00 | $100,000.00 | $94,900.00 | $94,900.00 | $0.00 | |||||
| $598,000.002 | $599,658.00 | $0.00 | |||||||||||