 Bids For:  Location:   Lake Manawa State Park  Date: 4/5/2012  Project No.  
  Shoreline rip rap  County:   POTTAWATTAMIE  Time: 3:00 p.m.  12-04-78-12

 

 
1
2
3
Estimated Cost: $19,000.00
Contractor: 
Carley Construction LLCTEK Builders, Inc.K & L Landscape & Construction Inc
Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), 216 MEADOW DR
201 N Taylor
PO Box 632
501 S Ridge Rd
Box 1040
TREYNOR IA  51575Mount Ayr IA  50854Sergeant Bluff IA  51054
Plan Sets Requested: 0
Quantities
712-487-3599641-464-3972712-943-2939
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Class "E" Riprap500Tons$42.30$21,150.00 $45.45$22,725.00 $95.00$47,500.00 
      $21,150.00  $22,725.00  $47,500.00 
 



 