IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Pilot Knob State Park | Date: 8/15/2013 | Project No. |
| SHOWER BUILDING, HOST CAMP SITE, WATER TREATMENT BUILDING & DUMP STATION | County: | HANCOCK | Time: 11:00 a.m. | 13-02-41-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $485,000.00 | Contractor: | Dean Snyder Construction | Larson Contracting Central, LLC | Kingland Construction Services | |||||||||
| Funding Source: 100% Infrastructure 2012, | 913 N 14th St | 508 W Main St | 1105 East E St | ||||||||||
| Clear Lake IA 50428 | Lake Mills IA 50450 | Forest City IA 50436 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 641-357-2283 | 641-592-5800 | 641-585-0101 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $2,000.00 | $2,000.00 | $10,000.00 | $10,000.00 | $14,107.00 | $14,107.00 | ||||
| 2 | CLEARING AND GRUBBING | 1 | L.S. | $5,060.00 | $5,060.00 | $10,000.00 | $10,000.00 | $7,596.00 | $7,596.00 | ||||
| 3 | SITE WORK AND UTILITY CONNECTIONS | 1 | L.S. | $500.00 | $500.00 | $8,000.00 | $8,000.00 | $32,556.00 | $32,556.00 | ||||
| 4 | CHEYENNE PRECAST CONCRETE SHOWER BUILDING | 1 | Each | $221,500.00 | $221,500.00 | $197,885.00 | $197,885.00 | $266,121.00 | $266,121.00 | ||||
| 5 | CLASS "A" CRUSHED STONE | 477 | Tons | $22.00 | $10,494.00 | $30.00 | $14,310.00 | $20.62 | $9,835.74 | ||||
| 6 | SIDEWALK, PCC, 6" | 103 | S.Y. | $68.25 | $7,029.75 | $60.00 | $6,180.00 | $49.86 | $5,135.58 | ||||
| 7 | PARKING LOT, PCC, 6" | 61 | S.Y. | $51.00 | $3,111.00 | $60.00 | $3,660.00 | $63.40 | $3,867.40 | ||||
| 8 | SIGNING | 1 | Each | $3,175.00 | $3,175.00 | $500.00 | $500.00 | $332.00 | $332.00 | ||||
| 9 | DRAIN-DOWN PIT | 1 | L.S. | $4,000.00 | $4,000.00 | $4,218.00 | $4,218.00 | $6,511.00 | $6,511.00 | ||||
| 10 | PRECAST CONCRETE PARKING WHEEL STOPS | 1 | Each | $100.00 | $100.00 | $350.00 | $350.00 | $100.00 | $100.00 | ||||
| 11 | EARTHWORK, CLASS 10, EXCAVATION | 500 | C.Y. | $5.00 | $2,500.00 | $40.00 | $20,000.00 | $16.40 | $8,200.00 | ||||
| 12 | EARTHWORK, CLASS 10, BORROW | 460 | C.Y. | $5.00 | $2,300.00 | $25.00 | $11,500.00 | $16.27 | $7,484.20 | ||||
| 13 | ENGINEERING FABRIC | 139 | S.Y. | $8.00 | $1,112.00 | $5.50 | $764.50 | $6.51 | $904.89 | ||||
| 14 | MACADAM STONE | 31 | Tons | $34.00 | $1,054.00 | $50.00 | $1,550.00 | $27.36 | $848.16 | ||||
| 15 | 3/8" MINUS CRUSHED STONE | 14 | Tons | $33.00 | $462.00 | $50.00 | $700.00 | $21.64 | $302.96 | ||||
| 16 | PAINTED PAVEMENT MARK, WATERBORNE/SOLVENT | 2.7 | STA. | $200.00 | $540.00 | $300.00 | $810.00 | $128.38 | $346.626 | ||||
| 17 | BOLLARD | 3 | Each | $530.00 | $1,590.00 | $600.00 | $1,800.00 | $1,000.00 | $3,000.00 | ||||
| 18 | REMOVE EXISTING DUMP STATION | 1 | L.S. | $3,100.00 | $3,100.00 | $3,000.00 | $3,000.00 | $16,278.00 | $16,278.00 | ||||
| 19 | REMOVE EXISTING MANHOLES | 2 | Each | $1,500.00 | $3,000.00 | $750.00 | $1,500.00 | $813.50 | $1,627.00 | ||||
| 20 | REMOVE EXISTING SANITARY SEWER PIPE, 6" | 39.36 | L.F. | $10.00 | $393.60 | $30.00 | $1,180.80 | $19.52 | $768.307 | ||||
| 21 | ABANDON EXISTING SANITARY SEWER PIPE, 4" | 68.53 | L.F. | $12.04 | $825.101 | $12.00 | $822.36 | $16.55 | $1,134.172 | ||||
| 22 | MANHOLE, SW-301, 48" | 4 | Each | $2,500.00 | $10,000.00 | $4,290.00 | $17,160.00 | $4,340.75 | $17,363.00 | ||||
| 23 | SANITARY SEWER PIPE, 4" PVC | 497.03 | L.F. | $25.00 | $12,425.75 | $25.00 | $12,425.75 | $32.55 | $16,178.327 | ||||
| 24 | SANITARY SEWER PIPE, 6" PVC | 478.1 | L.F. | $27.00 | $12,908.70 | $40.00 | $19,124.00 | $35.82 | $17,125.542 | ||||
| 25 | WATER MAIN, 1" HDPE | 361 | L.F. | $25.00 | $9,025.00 | $3.58 | $1,292.38 | $3.00 | $1,083.00 | ||||
| 26 | WATER MAIN, 2" HDPE | 165 | L.F. | $27.00 | $4,455.00 | $7.77 | $1,282.05 | $7.00 | $1,155.00 | ||||
| 27 | SCHWEITZER UTILITY BUILDING, SMALL | 1 | Each | $35,000.00 | $35,000.00 | $28,000.00 | $28,000.00 | $29,439.00 | $29,439.00 | ||||
| 28 | WATER TREATMENT SYSTEM | 1 | L.S. | $17,151.00 | $17,151.00 | $27,643.00 | $27,643.00 | $24,689.00 | $24,689.00 | ||||
| 29 | ELECTRICAL SERVICE | 228 | L.F. | $31.15 | $7,102.20 | $34.25 | $7,809.00 | $15.44 | $3,520.32 | ||||
| 30 | ELECTRICAL CAMP PEDESTAL | 1 | Each | $620.00 | $620.00 | $1,650.00 | $1,650.00 | $1,627.00 | $1,627.00 | ||||
| 31 | RV TO SANITARY SEWER CONNECTION | 1 | Each | $1,700.00 | $1,700.00 | $300.00 | $300.00 | $542.00 | $542.00 | ||||
| 32 | YARD HYDRANT | 1 | Each | $2,200.00 | $2,200.00 | $1,000.00 | $1,000.00 | $1,627.00 | $1,627.00 | ||||
| 33 | INSTALL WIRE GATE AND POSTS | 2 | Each | $1,600.00 | $3,200.00 | $1,000.00 | $2,000.00 | $2,084.00 | $4,168.00 | ||||
| 34 | INSTALL METAL GATE | 1 | Each | $600.00 | $600.00 | $500.00 | $500.00 | $2,084.00 | $2,084.00 | ||||
| 35 | REMOVE GATE POSTS | 2 | Each | $25.00 | $50.00 | $250.00 | $500.00 | $250.00 | $500.00 | ||||
| 36 | CONCRETE PAVING, 6" C4 MIX | 458 | S.Y. | $55.17 | $25,267.86 | $65.00 | $29,770.00 | $48.00 | $21,984.00 | ||||
| 37 | DUMP STATION | 1 | L.S. | $5,950.00 | $5,950.00 | $4,000.00 | $4,000.00 | $3,798.00 | $3,798.00 | ||||
| 38 | CONCRETE ISLAND AT DUMP STATION | 30 | S.Y. | $130.00 | $3,900.00 | $80.00 | $2,400.00 | $82.00 | $2,460.00 | ||||
| 39 | EROSION CONTROL | 584 | L.F. | $3.50 | $2,044.00 | $5.50 | $3,212.00 | $4.00 | $2,336.00 | ||||
| 40 | CONSTRUCTION STAKING | 1 | L.S. | $3,500.00 | $3,500.00 | $4,000.00 | $4,000.00 | $4,064.00 | $4,064.00 | ||||
| 41 | MOBILIZATION | 1 | L.S. | $46,146.04 | $46,146.04 | $15,000.00 | $15,000.00 | $7,598.00 | $7,598.00 | ||||
| 42 | DROP INLET | 2 | Each | $3,000.00 | $6,000.00 | $5,000.00 | $10,000.00 | $542.50 | $1,085.00 | ||||
| 43 | SANITARY SEWER PIPE, 4" C900 | 40 | L.F. | $10.00 | $400.00 | $25.00 | $1,000.00 | $50.00 | $2,000.00 | ||||
| $483,492.001 | $488,798.84 | $553,482.223 | |||||||||||