IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Kellerton Wildlife Area  Date: 4/19/2012  Project No.  
  New headquarters (rebid)  County:   RINGGOLD  Time: 11:00 am  12-04-80-03

 

 
1
2
3
Estimated Cost: $500,000.00
Contractor: 
HANSON CONSTRUCTION LLCSeptagon Construction CoHooyer Construction Inc
Funding Source: 75% Federal-PR, 25% REAP Land Management, PO Box 614
2950 SE Gateway Drive
1109 Roosevelt Road
PO Box 687
Clear Lake IA  50614Grimes IA  50111Pella IA  50219
Plan Sets Requested: 0
Quantities
641-357-8171(515) 986-7313641-628-1578
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Earthwork & all utilities1L.S.$20,000.00$20,000.00 $22,000.00$22,000.00 $22,000.00$22,000.00 
26" Class "A" crushed stone paving1L.S.$25,000.00$25,000.00 $15,000.00$15,000.00 $18,000.00$18,000.00 
3Concrete sidewalk1L.S.$4,000.00$4,000.00 $3,500.00$3,500.00 $6,000.00$6,000.00 
450'-0" x 110'-0" SIPs building1L.S.$396,000.00$396,000.00 $492,500.00$492,500.00 $498,000.00$498,000.00 
5Furnace HVAC system1L.S.$45,000.00$45,000.00 $35,000.00$35,000.00 $30,000.00$30,000.00 
6Septic System1L.S.$15,000.00$15,000.00 $11,500.00$11,500.00 $12,000.00$12,000.00 
      $505,000.00  $579,500.00  $586,000.00 
 



 

10/14/2026