IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lacey Keosauqua State Park | Date: 2/7/2013 | Project No. |
| Campground Water and Electrical Improvements | County: | VAN BUREN | Time: 3:00 p.m. | 13-06-89-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Cicco Construction, LLC | Joiner Construction | K.M. King, Inc | |||||||||
| Funding Source: 100% Other, | 1205 W Orchard | 11996 490th St | 4765 Summer St | ||||||||||
| Centerville IA 52544 | Plano IA 52581 | Burlington IA 52601 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-895-1980 | 641-649-2646 | 319-753-0507 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2” Dia. HDPE SDR 21 Pipe (Bored) | 691 | L.F. | $15.58 | $10,765.78 | $12.00 | $8,292.00 | $20.00 | $13,820.00 | ||||
| 2 | 1” Dia. PE Water Service Tubing (Bored) | 263 | L.F. | $9.46 | $2,487.98 | $10.00 | $2,630.00 | $15.00 | $3,945.00 | ||||
| 3 | Detectable Warning Tape, 3 “ Water | 954 | L.F. | $0.56 | $534.24 | $1.50 | $1,431.00 | $0.50 | $477.00 | ||||
| 4 | Curb Stop/Valve Box | 11 | Each | $193.51 | $2,128.61 | $850.00 | $9,350.00 | $400.00 | $4,400.00 | ||||
| 5 | Yard Hydrant | 10 | Each | $624.65 | $6,246.50 | $650.00 | $6,500.00 | $600.00 | $6,000.00 | ||||
| 6 | 2-1/2” Flushing Hydrant | 1 | Each | $2,404.15 | $2,404.15 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 | ||||
| 7 | System Disinfection | 1 | L.S. | $300.00 | $300.00 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | ||||
| 8 | Bore, Single Circuit Secondary | 740 | L.F. | $8.84 | $6,541.60 | $12.00 | $8,880.00 | $7.50 | $5,550.00 | ||||
| 9 | Detectable Warning Tape, 3” Electrical | 814 | L.F. | $0.00 | $0.00 | $0.25 | $203.50 | $0.05 | $40.70 | ||||
| 10 | Roadway Crossing Conduit – Schedule 80 PVC | 74 | L.F. | $0.00 | $0.00 | $3.00 | $222.00 | $2.45 | $181.30 | ||||
| 11 | Single Campsite Outlet Post (Metallic Power Center) 50 Amp | 10 | Each | $478.40 | $4,784.00 | $750.00 | $7,500.00 | $679.90 | $6,799.00 | ||||
| 12 | Campsite Outlet Post, One (Spare – Not Installed) | 1 | Each | $254.80 | $254.80 | $100.00 | $100.00 | $301.90 | $301.90 | ||||
| 13 | #8. AWG Grounding Conductor Cable, Type THW or USE | 394 | L.F. | $1.04 | $409.76 | $0.75 | $295.50 | $0.66 | $260.04 | ||||
| 14 | #2. AWG Grounding Conductor Cable, Type THW or USE | 566 | L.F. | $1.98 | $1,120.68 | $2.00 | $1,132.00 | $1.60 | $905.60 | ||||
| 15 | #1/0. AWG Single Conductor Cable, Type USE | 426 | L.F. | $3.54 | $1,508.04 | $3.00 | $1,278.00 | $2.61 | $1,111.86 | ||||
| 16 | #2/0. AWG Single Conductor Cable, Type USE | 756 | L.F. | $4.35 | $3,288.60 | $3.50 | $2,646.00 | $3.13 | $2,366.28 | ||||
| 17 | #4/0. AWG Single Conductor Cable, Type USE | 1145 | L.F. | $6.01 | $6,881.45 | $5.00 | $5,725.00 | $5.00 | $5,725.00 | ||||
| 18 | 250. AWG Single Conductor Cable, Type USE | 522 | L.F. | $6.30 | $3,288.60 | $5.50 | $2,871.00 | $5.77 | $3,011.94 | ||||
| 19 | Pad-Mounted 400 Amp Distribution Panel & Connections, Complete | 1 | Each | $3,588.00 | $3,588.00 | $2,500.00 | $2,500.00 | $8,239.00 | $8,239.00 | ||||
| 20 | Seeding, Fertilizing and Mulching | 1 | L.S. | $1,560.00 | $1,560.00 | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | ||||
| $58,092.79 | $66,056.00 | $67,134.62 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Snyder LLC | WAG Trenching and Construction | Smith Seeding Inc. | |||||||||
| Funding Source: 100% Other, | 18619 Teal Ave | 13935 Hwy 99 | 219 N First St | ||||||||||
| Bonaparte IA 52620 | Burlington IA 52601 | Eldridge IA 52748 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-796-4419 | 319-759-4037 | 563-210-1846 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2” Dia. HDPE SDR 21 Pipe (Bored) | 691 | L.F. | $13.00 | $8,983.00 | $14.92 | $10,309.72 | $12.00 | $8,292.00 | ||||
| 2 | 1” Dia. PE Water Service Tubing (Bored) | 263 | L.F. | $10.75 | $2,827.25 | $12.00 | $3,156.00 | $12.00 | $3,156.00 | ||||
| 3 | Detectable Warning Tape, 3 “ Water | 954 | L.F. | $0.09 | $85.86 | $1.00 | $954.00 | $1.00 | $954.00 | ||||
| 4 | Curb Stop/Valve Box | 11 | Each | $300.00 | $3,300.00 | $700.00 | $7,700.00 | $356.00 | $3,916.00 | ||||
| 5 | Yard Hydrant | 10 | Each | $750.00 | $7,500.00 | $750.00 | $7,500.00 | $475.00 | $4,750.00 | ||||
| 6 | 2-1/2” Flushing Hydrant | 1 | Each | $3,000.00 | $3,000.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | ||||
| 7 | System Disinfection | 1 | L.S. | $500.00 | $500.00 | $1,200.00 | $1,200.00 | $1,000.00 | $1,000.00 | ||||
| 8 | Bore, Single Circuit Secondary | 740 | L.F. | $12.00 | $8,880.00 | $16.00 | $11,840.00 | $12.00 | $8,880.00 | ||||
| 9 | Detectable Warning Tape, 3” Electrical | 814 | L.F. | $0.15 | $122.10 | $1.00 | $814.00 | $1.00 | $814.00 | ||||
| 10 | Roadway Crossing Conduit – Schedule 80 PVC | 74 | L.F. | $5.00 | $370.00 | $0.00 | $0.00 | $15.00 | $1,110.00 | ||||
| 11 | Single Campsite Outlet Post (Metallic Power Center) 50 Amp | 10 | Each | $600.00 | $6,000.00 | $300.00 | $3,000.00 | $526.31 | $5,263.10 | ||||
| 12 | Campsite Outlet Post, One (Spare – Not Installed) | 1 | Each | $280.00 | $280.00 | $300.00 | $300.00 | $263.81 | $263.81 | ||||
| 13 | #8. AWG Grounding Conductor Cable, Type THW or USE | 394 | L.F. | $0.80 | $315.20 | $0.80 | $315.20 | $0.86 | $338.84 | ||||
| 14 | #2. AWG Grounding Conductor Cable, Type THW or USE | 566 | L.F. | $2.75 | $1,556.50 | $2.25 | $1,273.50 | $2.87 | $1,624.42 | ||||
| 15 | #1/0. AWG Single Conductor Cable, Type USE | 426 | L.F. | $5.20 | $2,215.20 | $3.75 | $1,597.50 | $5.88 | $2,504.88 | ||||
| 16 | #2/0. AWG Single Conductor Cable, Type USE | 756 | L.F. | $6.50 | $4,914.00 | $3.30 | $2,494.80 | $6.66 | $5,034.96 | ||||
| 17 | #4/0. AWG Single Conductor Cable, Type USE | 1145 | L.F. | $9.20 | $10,534.00 | $4.90 | $5,610.50 | $6.28 | $7,190.60 | ||||
| 18 | 250. AWG Single Conductor Cable, Type USE | 522 | L.F. | $9.70 | $5,063.40 | $5.52 | $2,881.44 | $9.96 | $5,199.12 | ||||
| 19 | Pad-Mounted 400 Amp Distribution Panel & Connections, Complete | 1 | Each | $4,500.00 | $4,500.00 | $12,792.50 | $12,792.50 | $13,013.00 | $13,013.00 | ||||
| 20 | Seeding, Fertilizing and Mulching | 1 | L.S. | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $5,500.00 | $5,500.00 | ||||
| $72,446.51 | $77,239.16 | $79,804.73 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Schoon Construction Inc. | Hennigar Construction L.C. | Meyers Driveway | |||||||||
| Funding Source: 100% Other, | 1500 S 2nd St | 1853 303rd Ave | PO Box 488 | ||||||||||
| Cherokee IA 51012 | Fort Madison IA 52627 | Keokuk IA 52632 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 712-225-5736 | 319-372-1784 | 319-524-7329 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2” Dia. HDPE SDR 21 Pipe (Bored) | 691 | L.F. | $16.00 | $11,056.00 | $29.45 | $20,349.95 | $25.00 | $17,275.00 | ||||
| 2 | 1” Dia. PE Water Service Tubing (Bored) | 263 | L.F. | $16.00 | $4,208.00 | $21.60 | $5,680.80 | $25.00 | $6,575.00 | ||||
| 3 | Detectable Warning Tape, 3 “ Water | 954 | L.F. | $0.85 | $810.90 | $0.25 | $238.50 | $2.00 | $1,908.00 | ||||
| 4 | Curb Stop/Valve Box | 11 | Each | $650.00 | $7,150.00 | $639.00 | $7,029.00 | $1,150.00 | $12,650.00 | ||||
| 5 | Yard Hydrant | 10 | Each | $975.00 | $9,750.00 | $642.00 | $6,420.00 | $500.00 | $5,000.00 | ||||
| 6 | 2-1/2” Flushing Hydrant | 1 | Each | $1,500.00 | $1,500.00 | $2,304.00 | $2,304.00 | $2,500.00 | $2,500.00 | ||||
| 7 | System Disinfection | 1 | L.S. | $1,250.00 | $1,250.00 | $740.00 | $740.00 | $2,000.00 | $2,000.00 | ||||
| 8 | Bore, Single Circuit Secondary | 740 | L.F. | $12.00 | $8,880.00 | $25.15 | $18,611.00 | $25.00 | $18,500.00 | ||||
| 9 | Detectable Warning Tape, 3” Electrical | 814 | L.F. | $0.75 | $610.50 | $0.29 | $236.06 | $1.00 | $814.00 | ||||
| 10 | Roadway Crossing Conduit – Schedule 80 PVC | 74 | L.F. | $25.00 | $1,850.00 | $32.78 | $2,425.72 | $25.00 | $1,850.00 | ||||
| 11 | Single Campsite Outlet Post (Metallic Power Center) 50 Amp | 10 | Each | $600.00 | $6,000.00 | $361.00 | $3,610.00 | $700.00 | $7,000.00 | ||||
| 12 | Campsite Outlet Post, One (Spare – Not Installed) | 1 | Each | $400.00 | $400.00 | $361.00 | $361.00 | $350.00 | $350.00 | ||||
| 13 | #8. AWG Grounding Conductor Cable, Type THW or USE | 394 | L.F. | $1.25 | $492.50 | $0.53 | $208.82 | $2.20 | $866.80 | ||||
| 14 | #2. AWG Grounding Conductor Cable, Type THW or USE | 566 | L.F. | $3.00 | $1,698.00 | $1.98 | $1,120.68 | $3.50 | $1,981.00 | ||||
| 15 | #1/0. AWG Single Conductor Cable, Type USE | 426 | L.F. | $3.50 | $1,491.00 | $3.22 | $1,371.72 | $4.50 | $1,917.00 | ||||
| 16 | #2/0. AWG Single Conductor Cable, Type USE | 756 | L.F. | $4.00 | $3,024.00 | $3.89 | $2,940.84 | $6.00 | $4,536.00 | ||||
| 17 | #4/0. AWG Single Conductor Cable, Type USE | 1145 | L.F. | $6.50 | $7,442.50 | $6.26 | $7,167.70 | $7.00 | $8,015.00 | ||||
| 18 | 250. AWG Single Conductor Cable, Type USE | 522 | L.F. | $7.00 | $3,654.00 | $7.36 | $3,841.92 | $8.00 | $4,176.00 | ||||
| 19 | Pad-Mounted 400 Amp Distribution Panel & Connections, Complete | 1 | Each | $6,000.00 | $6,000.00 | $14,296.00 | $14,296.00 | $7,500.00 | $7,500.00 | ||||
| 20 | Seeding, Fertilizing and Mulching | 1 | L.S. | $5,500.00 | $5,500.00 | $2,000.00 | $2,000.00 | $7,500.00 | $7,500.00 | ||||
| $82,767.40 | $100,953.71 | $112,913.80 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | King Construction, LLC | |||||||||||
| Funding Source: 100% Other, | 104 Main St PO Box 369 | ||||||||||||
| Wall Lake IA 51466 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-664-2918 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2” Dia. HDPE SDR 21 Pipe (Bored) | 691 | L.F. | $51.15 | $35,344.65 | $0.00 | $0.00 | ||||||
| 2 | 1” Dia. PE Water Service Tubing (Bored) | 263 | L.F. | $45.75 | $12,032.25 | $0.00 | $0.00 | ||||||
| 3 | Detectable Warning Tape, 3 “ Water | 954 | L.F. | $2.40 | $2,289.60 | $0.00 | $0.00 | ||||||
| 4 | Curb Stop/Valve Box | 11 | Each | $500.00 | $5,500.00 | $0.00 | $0.00 | ||||||
| 5 | Yard Hydrant | 10 | Each | $935.00 | $9,350.00 | $0.00 | $0.00 | ||||||
| 6 | 2-1/2” Flushing Hydrant | 1 | Each | $2,400.00 | $2,400.00 | $0.00 | $0.00 | ||||||
| 7 | System Disinfection | 1 | L.S. | $600.00 | $600.00 | $0.00 | $0.00 | ||||||
| 8 | Bore, Single Circuit Secondary | 740 | L.F. | $40.75 | $30,155.00 | $0.00 | $0.00 | ||||||
| 9 | Detectable Warning Tape, 3” Electrical | 814 | L.F. | $1.00 | $814.00 | $0.00 | $0.00 | ||||||
| 10 | Roadway Crossing Conduit – Schedule 80 PVC | 74 | L.F. | $45.00 | $3,330.00 | $0.00 | $0.00 | ||||||
| 11 | Single Campsite Outlet Post (Metallic Power Center) 50 Amp | 10 | Each | $1,810.00 | $18,100.00 | $0.00 | $0.00 | ||||||
| 12 | Campsite Outlet Post, One (Spare – Not Installed) | 1 | Each | $220.00 | $220.00 | $0.00 | $0.00 | ||||||
| 13 | #8. AWG Grounding Conductor Cable, Type THW or USE | 394 | L.F. | $4.40 | $1,733.60 | $0.00 | $0.00 | ||||||
| 14 | #2. AWG Grounding Conductor Cable, Type THW or USE | 566 | L.F. | $5.75 | $3,254.50 | $0.00 | $0.00 | ||||||
| 15 | #1/0. AWG Single Conductor Cable, Type USE | 426 | L.F. | $7.35 | $3,131.10 | $0.00 | $0.00 | ||||||
| 16 | #2/0. AWG Single Conductor Cable, Type USE | 756 | L.F. | $7.95 | $6,010.20 | $0.00 | $0.00 | ||||||
| 17 | #4/0. AWG Single Conductor Cable, Type USE | 1145 | L.F. | $9.75 | $11,163.75 | $0.00 | $0.00 | ||||||
| 18 | 250. AWG Single Conductor Cable, Type USE | 522 | L.F. | $10.50 | $5,481.00 | $0.00 | $0.00 | ||||||
| 19 | Pad-Mounted 400 Amp Distribution Panel & Connections, Complete | 1 | Each | $4,400.00 | $4,400.00 | $0.00 | $0.00 | ||||||
| 20 | Seeding, Fertilizing and Mulching | 1 | L.S. | $2,100.00 | $2,100.00 | $0.00 | $0.00 | ||||||
| $157,409.65 | $0.00 | $0.00 | |||||||||||