IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Zimmerman Pool at lake Icaria | Date: 1/17/2013 | Project No. |
| Fix dam of wetland | County: | ADAMS | Time: 11:00 am | 12-04-02-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $341,050.00 | Contractor: | Murphy Heavy Contracting Corporation | Michael J. Lamb | Kevin Kent Construction | |||||||||
| Funding Source: 50% Lake Restoration, 50% Other, | 101 Roosevelt Dr | 2751 Marion Ave | 15157 US Hwy 34 | ||||||||||
| Anita IA 50020 | Greenfield IA 50849 | Lucas IA 50151 | |||||||||||
| Plan Sets Requested: 15 | Quantities | 712-762-3386 | 515-250-8440 | 641-766-6126 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $4,500.00 | $4,500.00 | $12,000.00 | $12,000.00 | ||||
| 2 | Earthfill | 411 | C.Y. | $7.00 | $2,877.00 | $3.50 | $1,438.50 | $6.00 | $2,466.00 | ||||
| 3 | Excavation | 411 | C.Y. | $7.00 | $2,877.00 | $3.50 | $1,438.50 | $8.00 | $3,288.00 | ||||
| 4 | Rip Rap, Grizzled Class E | 3441 | Tons | $45.00 | $154,845.00 | $47.50 | $163,447.50 | $48.50 | $166,888.50 | ||||
| 5 | Rip Rap Concrete Grout | 695 | C.Y. | $180.00 | $125,100.00 | $152.50 | $105,987.50 | $170.00 | $118,150.00 | ||||
| 6 | Geotextile Fabric | 3410 | S.Y. | $2.50 | $8,525.00 | $2.25 | $7,672.50 | $2.00 | $6,820.00 | ||||
| 7 | 42" Stoplog Riser | 1 | L.S. | $3,500.00 | $3,500.00 | $3,210.00 | $3,210.00 | $5,800.00 | $5,800.00 | ||||
| 8 | 30" Diameter CMP Pipe | 80 | L.F. | $65.00 | $5,200.00 | $46.99 | $3,759.20 | $48.00 | $3,840.00 | ||||
| 9 | Seeding | 1 | L.S. | $2,500.00 | $2,500.00 | $4,500.00 | $4,500.00 | $10,000.00 | $10,000.00 | ||||
| 10 | Site Dewatering | 1 | L.S. | $1,000.00 | $1,000.00 | $7,500.00 | $7,500.00 | $6,500.00 | $6,500.00 | ||||
| 11 | Rip Rap Removal | 1 | L.S. | $15,000.00 | $15,000.00 | $38,000.00 | $38,000.00 | $14,000.00 | $14,000.00 | ||||
| 12 | Regrade Rip Rap Base | 1 | L.S. | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | ||||
| $333,924.00 | $344,953.70 | $353,252.50 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $341,050.00 | Contractor: | Carley Construction, LLC | P & P Contractors | Nelson & Rock Contracting Inc. | |||||||||
| Funding Source: 50% Lake Restoration, 50% Other, | 216 Meadow Ln | 2687 Homestead Ave | 23565 Hwy K45 | ||||||||||
| Treynor IA 57575 | Winterset IA 50273 | Onawa IA 51040 | |||||||||||
| Plan Sets Requested: 15 | Quantities | 712-256-5818 | 515-975-9229 | 712-423-1065 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $15,000.00 | $15,000.00 | $10,000.00 | $10,000.00 | $20,000.00 | $20,000.00 | ||||
| 2 | Earthfill | 411 | C.Y. | $6.00 | $2,466.00 | $8.50 | $3,493.50 | $10.00 | $4,110.00 | ||||
| 3 | Excavation | 411 | C.Y. | $5.00 | $2,055.00 | $6.00 | $2,466.00 | $10.00 | $4,110.00 | ||||
| 4 | Rip Rap, Grizzled Class E | 3441 | Tons | $50.00 | $172,050.00 | $51.00 | $175,491.00 | $50.00 | $172,050.00 | ||||
| 5 | Rip Rap Concrete Grout | 695 | C.Y. | $195.00 | $135,525.00 | $236.50 | $164,367.50 | $230.00 | $159,850.00 | ||||
| 6 | Geotextile Fabric | 3410 | S.Y. | $4.10 | $13,981.00 | $8.00 | $27,280.00 | $3.00 | $10,230.00 | ||||
| 7 | 42" Stoplog Riser | 1 | L.S. | $3,100.00 | $3,100.00 | $9,500.00 | $9,500.00 | $6,000.00 | $6,000.00 | ||||
| 8 | 30" Diameter CMP Pipe | 80 | L.F. | $62.50 | $5,000.00 | $40.00 | $3,200.00 | $90.00 | $7,200.00 | ||||
| 9 | Seeding | 1 | L.S. | $4,500.00 | $4,500.00 | $16,500.00 | $16,500.00 | $5,000.00 | $5,000.00 | ||||
| 10 | Site Dewatering | 1 | L.S. | $4,500.00 | $4,500.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | ||||
| 11 | Rip Rap Removal | 1 | L.S. | $28,500.00 | $28,500.00 | $21,000.00 | $21,000.00 | $35,000.00 | $35,000.00 | ||||
| 12 | Regrade Rip Rap Base | 1 | L.S. | $8,000.00 | $8,000.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | ||||
| $394,677.00 | $443,298.00 | $443,550.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $341,050.00 | Contractor: | TEK Builders Inc. | K.M. King, Inc | ||||||||||
| Funding Source: 50% Lake Restoration, 50% Other, | 201 N Taylor St | 4765 Summer St | |||||||||||
| Mount Ayr IA 50854 | Burlington IA 52601 | ||||||||||||
| Plan Sets Requested: 15 | Quantities | 641-464-3972 | 319-753-0507 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $30,000.00 | $30,000.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
| 2 | Earthfill | 411 | C.Y. | $10.00 | $4,110.00 | $10.00 | $4,110.00 | $0.00 | |||||
| 3 | Excavation | 411 | C.Y. | $10.00 | $4,110.00 | $10.00 | $4,110.00 | $0.00 | |||||
| 4 | Rip Rap, Grizzled Class E | 3441 | Tons | $52.00 | $178,932.00 | $65.00 | $223,665.00 | $0.00 | |||||
| 5 | Rip Rap Concrete Grout | 695 | C.Y. | $210.00 | $145,950.00 | $143.00 | $99,385.00 | $0.00 | |||||
| 6 | Geotextile Fabric | 3410 | S.Y. | $2.00 | $6,820.00 | $4.00 | $13,640.00 | $0.00 | |||||
| 7 | 42" Stoplog Riser | 1 | L.S. | $2,600.00 | $2,600.00 | $10,000.00 | $10,000.00 | $0.00 | |||||
| 8 | 30" Diameter CMP Pipe | 80 | L.F. | $56.00 | $4,480.00 | $75.00 | $6,000.00 | $0.00 | |||||
| 9 | Seeding | 1 | L.S. | $8,000.00 | $8,000.00 | $3,000.00 | $3,000.00 | $0.00 | |||||
| 10 | Site Dewatering | 1 | L.S. | $8,000.00 | $8,000.00 | $50,000.00 | $50,000.00 | $0.00 | |||||
| 11 | Rip Rap Removal | 1 | L.S. | $56,380.00 | $56,380.00 | $140,000.00 | $140,000.00 | $0.00 | |||||
| 12 | Regrade Rip Rap Base | 1 | L.S. | $1,000.00 | $1,000.00 | $27,000.00 | $27,000.00 | $0.00 | |||||
| $450,382.00 | $595,910.00 | $0.00 | |||||||||||
10/14/2026