IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Zimmerman Pool at lake Icaria  Date: 1/17/2013  Project No.  
  Fix dam of wetland  County:   ADAMS  Time: 11:00 am  12-04-02-01

 

 
1
2
3
Estimated Cost: $341,050.00
Contractor: 
Murphy Heavy Contracting CorporationMichael J. LambKevin Kent Construction
Funding Source: 50% Lake Restoration, 50% Other, 101 Roosevelt Dr
2751 Marion Ave
15157 US Hwy 34
Anita IA  50020Greenfield IA  50849Lucas IA  50151
Plan Sets Requested: 15
Quantities
712-762-3386515-250-8440641-766-6126
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$10,000.00$10,000.00 $4,500.00$4,500.00 $12,000.00$12,000.00 
2Earthfill411C.Y.$7.00$2,877.00 $3.50$1,438.50 $6.00$2,466.00 
3Excavation411C.Y.$7.00$2,877.00 $3.50$1,438.50 $8.00$3,288.00 
4Rip Rap, Grizzled Class E3441Tons$45.00$154,845.00 $47.50$163,447.50 $48.50$166,888.50 
5Rip Rap Concrete Grout695C.Y.$180.00$125,100.00 $152.50$105,987.50 $170.00$118,150.00 
6Geotextile Fabric3410S.Y.$2.50$8,525.00 $2.25$7,672.50 $2.00$6,820.00 
742" Stoplog Riser1L.S.$3,500.00$3,500.00 $3,210.00$3,210.00 $5,800.00$5,800.00 
830" Diameter CMP Pipe80L.F.$65.00$5,200.00 $46.99$3,759.20 $48.00$3,840.00 
9Seeding1L.S.$2,500.00$2,500.00 $4,500.00$4,500.00 $10,000.00$10,000.00 
10Site Dewatering1L.S.$1,000.00$1,000.00 $7,500.00$7,500.00 $6,500.00$6,500.00 
11Rip Rap Removal1L.S.$15,000.00$15,000.00 $38,000.00$38,000.00 $14,000.00$14,000.00 
12Regrade Rip Rap Base1L.S.$2,500.00$2,500.00 $3,500.00$3,500.00 $3,500.00$3,500.00 
      $333,924.00  $344,953.70  $353,252.50 
 
 
4
5
6
Estimated Cost: $341,050.00
Contractor: 
Carley Construction, LLCP & P ContractorsNelson & Rock Contracting Inc.
Funding Source: 50% Lake Restoration, 50% Other, 216 Meadow Ln
2687 Homestead Ave
23565 Hwy K45
Treynor IA  57575Winterset IA  50273Onawa IA  51040
Plan Sets Requested: 15
Quantities
712-256-5818515-975-9229712-423-1065
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$15,000.00$15,000.00 $10,000.00$10,000.00 $20,000.00$20,000.00 
2Earthfill411C.Y.$6.00$2,466.00 $8.50$3,493.50 $10.00$4,110.00 
3Excavation411C.Y.$5.00$2,055.00 $6.00$2,466.00 $10.00$4,110.00 
4Rip Rap, Grizzled Class E3441Tons$50.00$172,050.00 $51.00$175,491.00 $50.00$172,050.00 
5Rip Rap Concrete Grout695C.Y.$195.00$135,525.00 $236.50$164,367.50 $230.00$159,850.00 
6Geotextile Fabric3410S.Y.$4.10$13,981.00 $8.00$27,280.00 $3.00$10,230.00 
742" Stoplog Riser1L.S.$3,100.00$3,100.00 $9,500.00$9,500.00 $6,000.00$6,000.00 
830" Diameter CMP Pipe80L.F.$62.50$5,000.00 $40.00$3,200.00 $90.00$7,200.00 
9Seeding1L.S.$4,500.00$4,500.00 $16,500.00$16,500.00 $5,000.00$5,000.00 
10Site Dewatering1L.S.$4,500.00$4,500.00 $5,000.00$5,000.00 $10,000.00$10,000.00 
11Rip Rap Removal1L.S.$28,500.00$28,500.00 $21,000.00$21,000.00 $35,000.00$35,000.00 
12Regrade Rip Rap Base1L.S.$8,000.00$8,000.00 $5,000.00$5,000.00 $10,000.00$10,000.00 
      $394,677.00  $443,298.00  $443,550.00 
 
7
8
9
Estimated Cost: $341,050.00
Contractor: 
TEK Builders Inc.K.M. King, Inc
Funding Source: 50% Lake Restoration, 50% Other, 201 N Taylor St
4765 Summer St

Mount Ayr IA  50854Burlington IA  52601  
Plan Sets Requested: 15
Quantities
641-464-3972319-753-0507
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$30,000.00$30,000.00 $15,000.00$15,000.00 $0.00 
2Earthfill411C.Y.$10.00$4,110.00 $10.00$4,110.00 $0.00 
3Excavation411C.Y.$10.00$4,110.00 $10.00$4,110.00 $0.00 
4Rip Rap, Grizzled Class E3441Tons$52.00$178,932.00 $65.00$223,665.00 $0.00 
5Rip Rap Concrete Grout695C.Y.$210.00$145,950.00 $143.00$99,385.00 $0.00 
6Geotextile Fabric3410S.Y.$2.00$6,820.00 $4.00$13,640.00 $0.00 
742" Stoplog Riser1L.S.$2,600.00$2,600.00 $10,000.00$10,000.00 $0.00 
830" Diameter CMP Pipe80L.F.$56.00$4,480.00 $75.00$6,000.00 $0.00 
9Seeding1L.S.$8,000.00$8,000.00 $3,000.00$3,000.00 $0.00 
10Site Dewatering1L.S.$8,000.00$8,000.00 $50,000.00$50,000.00 $0.00 
11Rip Rap Removal1L.S.$56,380.00$56,380.00 $140,000.00$140,000.00 $0.00 
12Regrade Rip Rap Base1L.S.$1,000.00$1,000.00 $27,000.00$27,000.00 $0.00 
      $450,382.00  $595,910.00  $0.00 
 



 

10/14/2026