IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pleasant Creek State Rec Area  Date: 7/19/2012  Project No.  
  FEMA 2008 Trail Repair  County:   LINN  Time: 3:00 p.m.  12-06-57-04

 

 
1
2
3
Estimated Cost: $26,000.00
Contractor: 
Stop Leak Able Building MaintenanceGodby Land Improvements, LLCMiene Septic Service
Funding Source: 90% Federal-FEMA 1, 10% REAP Land Management, 3176 63rd St Dr
2569 560th Ave
3306 N Center Point Rd
Shellsburg IA  52332Albia IA  52531Marion IA  52302
Plan Sets Requested: 0
Quantities
319-241-3396319-393-4142
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,200.00$2,200.00 $1,000.00$1,000.00 $2,500.00$2,500.00 
2Embankment In Place540C.Y.$27.22$14,698.80 $30.00$16,200.00 $25.11$13,559.40 
33/4" Roadstone100Tons$13.85$1,385.00 $63.00$6,300.00 $88.02$8,802.00 
      $18,283.80  $23,500.00  $24,861.40 
 



 

10/14/2026