IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Mines of Spain | Date: 4/19/2012 | Project No. |
| trail repair/riprap | County: | DUBUQUE | Time: 11:00 a.m. | 12-03-31-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $150,000.00 | Contractor: | M-Z Construction Inc. | Connolly Construction Inc | Top Grade Excavating | |||||||||
| Funding Source: 75% Federal-FEMA 1, 12% Executive Council, 13% Park & Institutional Road Fund, | 1770 County Road J | 18409 N Cascade Rd | 971 9th Avenue NW | ||||||||||
| Linden WI 53553 | Peosta IA 52068 | Farley IA 52046 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 608-623-23578 | 563-876-3225 | 563-744-3416 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $9,600.00 | $9,600.00 | $2,500.00 | $2,500.00 | $4,000.00 | $4,000.00 | ||||
| 2 | Furnish & Install Fill (Trail) | 7021 | C.Y. | $5.71 | $40,089.91 | $8.25 | $57,923.25 | $6.80 | $47,742.80 | ||||
| 3 | Furnish & Install Fill (Bridge) | 93 | C.Y. | $5.71 | $531.03 | $10.50 | $976.50 | $6.80 | $632.40 | ||||
| 4 | Engineering Fabric (Trail) | 1164 | S.Y. | $1.55 | $1,804.20 | $2.45 | $2,851.80 | $2.00 | $2,328.00 | ||||
| 5 | Engineering Fabric (Bridge) | 249 | S.Y. | $1.55 | $385.95 | $2.45 | $610.05 | $2.00 | $498.00 | ||||
| 6 | Revetment, Class "D" Riprap (Trail) | 1187 | Tons | $14.29 | $16,962.23 | $17.00 | $20,179.00 | $25.00 | $29,675.00 | ||||
| 7 | Revetment, Class "D" Rirpap (Bridge) | 716 | Tons | $14.29 | $10,231.64 | $19.10 | $13,675.60 | $25.00 | $17,900.00 | ||||
| 8 | Surfacing, Class "A" Cr. Stone | 275 | Tons | $16.27 | $4,474.25 | $16.35 | $4,496.25 | $16.00 | $4,400.00 | ||||
| $84,079.21 | $103,212.45 | $107,176.20 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $150,000.00 | Contractor: | Lansing Brothers Construction Co. Inc. | McClain Excavating | Tschigffrie Excavating Co | |||||||||
| Funding Source: 75% Federal-FEMA 1, 12% Executive Council, 13% Park & Institutional Road Fund, | 101 E 1st Street | 660 Peosta Street PO Box 77 | 425 Julian Dubuque Dr PO Box 3280 | ||||||||||
| Luxemburg IA 52056 | Peosta IA 52068 | Dubuque IA 52003 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-543-7360 | 563-556-2348 | 563-557-7450 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $6,500.00 | $6,500.00 | $2,740.00 | $2,740.00 | $1,500.00 | $1,500.00 | ||||
| 2 | Furnish & Install Fill (Trail) | 7021 | C.Y. | $7.00 | $49,147.00 | $9.50 | $66,699.50 | $9.30 | $65,295.30 | ||||
| 3 | Furnish & Install Fill (Bridge) | 93 | C.Y. | $10.00 | $930.00 | $9.50 | $883.50 | $9.30 | $864.90 | ||||
| 4 | Engineering Fabric (Trail) | 1164 | S.Y. | $2.00 | $2,328.00 | $1.10 | $1,280.40 | $3.10 | $3,608.40 | ||||
| 5 | Engineering Fabric (Bridge) | 249 | S.Y. | $2.00 | $498.00 | $1.10 | $273.90 | $3.10 | $771.90 | ||||
| 6 | Revetment, Class "D" Riprap (Trail) | 1187 | Tons | $22.00 | $26,114.00 | $17.00 | $20,179.00 | $17.50 | $20,772.50 | ||||
| 7 | Revetment, Class "D" Rirpap (Bridge) | 716 | Tons | $25.00 | $17,900.00 | $17.00 | $12,172.00 | $17.50 | $12,530.00 | ||||
| 8 | Surfacing, Class "A" Cr. Stone | 275 | Tons | $14.00 | $3,850.00 | $16.30 | $4,482.50 | $16.40 | $4,510.00 | ||||
| $107,267.00 | $108,710.80 | $109,853.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $150,000.00 | Contractor: | Mainline Excavating Co. Inc. | Arensdorf Excavating & Trucking Inc. | ||||||||||
| Funding Source: 75% Federal-FEMA 1, 12% Executive Council, 13% Park & Institutional Road Fund, | 8180 Seippel Court | 9802 County Road X-40 | |||||||||||
| Dubuque IA 52002 | Anamosa IA 52205 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-583-1888 | 319-462-2385 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,666.00 | $3,666.00 | $2,991.50 | $2,991.50 | $0.00 | |||||
| 2 | Furnish & Install Fill (Trail) | 7021 | C.Y. | $9.66 | $67,822.86 | $16.50 | $115,846.50 | $0.00 | |||||
| 3 | Furnish & Install Fill (Bridge) | 93 | C.Y. | $9.66 | $898.38 | $16.50 | $1,534.50 | $0.00 | |||||
| 4 | Engineering Fabric (Trail) | 1164 | S.Y. | $2.75 | $3,201.00 | $4.50 | $5,238.00 | $0.00 | |||||
| 5 | Engineering Fabric (Bridge) | 249 | S.Y. | $2.75 | $684.75 | $4.50 | $1,120.50 | $0.00 | |||||
| 6 | Revetment, Class "D" Riprap (Trail) | 1187 | Tons | $28.65 | $34,007.55 | $17.50 | $20,772.50 | $0.00 | |||||
| 7 | Revetment, Class "D" Rirpap (Bridge) | 716 | Tons | $29.00 | $20,764.00 | $17.50 | $12,530.00 | $0.00 | |||||
| 8 | Surfacing, Class "A" Cr. Stone | 275 | Tons | $14.00 | $3,850.00 | $15.50 | $4,262.50 | $0.00 | |||||
| $134,894.54 | $164,296.00 | $0.00 | |||||||||||
10/14/2026