IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pleasant Creek State Rec Area  Date: 10/18/2012  Project No.  
  campground and shelter electric  County:   LINN  Time: 11:00 a.m.  12-06-57-03

 

 
1
2
3
Estimated Cost: $235,000.00
Contractor: 
Connolly Construction IncEngineering Consultants Inc [ECINC]JB Holland Construction
Funding Source: 100% Health and Safety Account, 18409 N Cascade Rd
PO Box 68
1680 Davis Avenue Suite A
2092 HWY 9 West
Peosta IA  52068Nichols IA  52766Decorah IA  52101
Plan Sets Requested: 6
Quantities
563-876-3225319-723-4440563-382-2901
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Camp Pad Excavation, Class 10847C.Y.$13.80$11,688.60 $15.50$13,128.50 $25.26$21,395.22 
2Macadam Stone Base Material, 5"975Tons$18.05$17,598.75 $18.85$18,378.75 $18.00$17,550.00 
3Granular Surfacing, Crushed Limestone, 2" Depth400Tons$11.10$4,440.00 $24.38$9,752.00 $11.75$4,700.00 
4Engineering Fabric2770S.Y.$1.95$5,401.50 $2.10$5,817.00 $1.50$4,155.00 
54" Dia PVC SDR 35 Sewer Pipe, with Detectable Warning Tape203L.F.$27.65$5,612.95 $15.50$3,146.50 $21.00$4,263.00 
6RV to Sanitary Sewer Hook-up Assembly3Each$860.00$2,580.00 $1,050.85$3,152.55 $905.00$2,715.00 
78" x 8" x 4" Wye connections3Each$124.00$372.00 $334.92$1,004.76 $842.50$2,527.50 
81" HDPE Water Service Line, with Detectable Warning Tape500L.F.$17.20$8,600.00 $9.35$4,675.00 $10.75$5,375.00 
91" Curb Stop/Valve Box9Each$645.00$5,805.00 $437.20$3,934.80 $496.00$4,464.00 
10Yard Hydrants - New9Each$692.00$6,228.00 $3,025.38$27,228.42 $2,975.00$26,775.00 
11Shelter LED Lighting Fixtures, including Power Receptacles4Each$1,118.00$4,472.00 $1,190.75$4,763.00 $947.00$3,788.00 
12Conection to Transformers4Each$559.00$2,236.00 $250.00$1,000.00 $505.00$2,020.00 
13Pad Mounted 600 Amp Distribution Panel, Complete1Each$6,150.00$6,150.00 $6,628.00$6,628.00 $5,553.00$5,553.00 
14Pad Mounted 400 Amp Distribution Panel, Complete 1Each$4,471.00$4,471.00 $5,128.00$5,128.00 $4,039.00$4,039.00 
15Pad Mounted 100 Amp Distribution Panel, Complete 2Each$2,235.00$4,470.00 $2,946.50$5,893.00 $2,020.00$4,040.00 
16Campsite Outlet Post (Metallic Power Center), 50 Amp, Installed30Each$335.00$10,050.00 $345.00$10,350.00 $303.00$9,090.00 
17Campsite Outlet Post (Metallic Power Center), 50 Amp, Spare 1Each$335.00$335.00 $194.00$194.00 $303.00$303.00 
18Trench, Single Circuit Secondary3943L.F.$2.25$8,871.75 $2.24$8,832.32 $2.00$7,886.00 
19Trench, Double Circuit Secondary 22L.F.$2.25$49.50 $10.00$220.00 $2.00$44.00 
20Detectable Warning Tape, 3" Electrical3987L.F.$0.25$996.75 $0.05$199.35 $0.20$797.40 
21roadway Crossing Conduit, Schedule80 PVC111L.F.$13.40$1,487.40 $27.95$3,102.45 $12.00$1,332.00 
22No. 6 AWG Grounding Conductor, Type THW or USE 360L.F.$0.90$324.00 $0.70$252.00 $0.80$288.00 
23No. 2 AWG Grounding Conductor, Type THW or USE 2804L.F.$2.10$5,888.40 $1.35$3,785.40 $1.87$5,243.48 
24No. 4 AWG Single Conductor Cable, Type USE 210L.F.$1.35$283.50 $1.20$252.00 $1.21$254.10 
25No. 1 AWG Single Conductor Cable, Type USE 3582L.F.$2.70$9,671.40 $1.70$6,089.40 $2.44$8,740.08 
26No. 3/0 AWG Single Conductor Cable, Type USE 1812L.F.$5.25$9,513.00 $2.45$4,439.40 $4.73$8,570.76 
27No. 4/0 AWG Single Conductor Cable, Type USE 2376L.F.$6.35$15,087.60 $3.40$8,078.40 $5.73$13,614.48 
28250 AWG Single Conductor Cable, Type USE 1488L.F.$7.35$10,936.80 $4.20$6,249.60 $6.63$9,865.44 
29300 AWG Single Conductor Cable, Type USE 2736L.F.$9.20$25,171.20 $5.00$13,680.00 $8.30$22,708.80 
30Drinking FountainRepalcement/Repair2Each$3,890.00$7,780.00 $6,980.00$13,960.00 $4,750.00$9,500.00 
31Remove and Dispose Existing Fire Rings42Each$28.25$1,186.50 $35.00$1,470.00 $150.00$6,300.00 
32Remove and Dispose Existing Yard Hydrants2Each$336.00$672.00 $100.00$200.00 $150.00$300.00 
33Remove and Dispose Existing Drinking Fountains2Each$336.00$672.00 $100.00$200.00 $250.00$500.00 
34Remove and Dispose Existing Electric Campsite Pedestals16Each$35.55$568.80 $200.00$3,200.00 $50.50$808.00 
35Surface Restoration- Seeding, Fertilizing, & Mulching1L.S.$3,915.00$3,915.00 $5,500.00$5,500.00 $4,050.00$4,050.00 
36Storom Water Pollution Prevention Plan (SWPPP)1L.S.$2,815.00$2,815.00 $1,200.00$1,200.00 $3,000.00$3,000.00 
37Mobilization1L.S.$8,970.00$8,970.00 $19,109.00$19,109.00 $7,500.00$7,500.00 
      $215,371.40  $224,193.60  $234,055.26 
 



 

10/14/2026