| Bids For: | Location: | Lake Keomah State Park | Date: 1/5/2012 | Project No. |
| Sewer Rehab | County: | MAHASKA | Time: 3:00 p.m. | 10-05-62-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: | Contractor: | WRH INC | SYNERGY CONTRACTING LLC | Hagerty Earthworks LLC | |||||||||
| Funding Source: 100% I-JOBS, | PO BOX 256 | 1120 2nd St NE PO BOX 388 | 1002 Robin Rd | ||||||||||
| AMANA IA 52203 | Bondurant IA 50035 | Muscatine IA 52761 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-622-3816 | 515-957-4907 | 563-260-3877 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | CIPP Line Sewer Pipe, 6" Dia. | 1925 | L.F. | $33.60 | $64,680.00 | $40.00 | $77,000.00 | $42.00 | $80,850.00 | ||||
| 2 | CIPP Line Sewer Pipe, 8" Dia. | 330 | L.F. | $35.70 | $11,781.00 | $35.00 | $11,550.00 | $44.00 | $14,520.00 | ||||
| 3 | Chemical Grout Sewer, VCP Pipe Joints, 8" Dia. | 1200 | L.F. | $11.00 | $13,200.00 | $10.00 | $12,000.00 | $20.50 | $24,600.00 | ||||
| 4 | Post-Improvement Televising | 3455 | L.F. | $1.32 | $4,560.60 | $1.00 | $3,455.00 | $1.50 | $5,182.50 | ||||
| 5 | Interior Manhole Chimney Seals | 1 | Each | $350.00 | $350.00 | $415.00 | $415.00 | $800.00 | $800.00 | ||||
| 6 | Manhole CCCM Interior Lining with Epoxy Seal | 73 | L.F. | $181.00 | $13,213.00 | $240.00 | $17,520.00 | $222.00 | $16,206.00 | ||||
| 7 | New Casting for CCCM Lined Manholes | 12 | Each | $600.00 | $7,200.00 | $1,000.00 | $12,000.00 | $2,200.00 | $26,400.00 | ||||
| 8 | Manhole Grout/Repair of Inlet/Outlet Piping | 4 | Each | $875.00 | $3,500.00 | $450.00 | $1,800.00 | $835.00 | $3,340.00 | ||||
| 9 | New Precast 4' Dia. Manhole | 1 | Each | $6,200.00 | $6,200.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | ||||
| 10 | New Lift Station Rehabilitation - South System | 1 | L.S. | $24,600.00 | $24,600.00 | $55,000.00 | $55,000.00 | $55,500.00 | $55,500.00 | ||||
| 11 | New Packaged Lift Station - North System | 1 | L.S. | $57,600.00 | $57,600.00 | $90,000.00 | $90,000.00 | $57,500.00 | $57,500.00 | ||||
| 12 | Reconnect Existing Sewer/Abandon Existing Manhole | 1 | L.S. | $5,000.00 | $5,000.00 | $8,500.00 | $8,500.00 | $500.00 | $500.00 | ||||
| 13 | 2" HDPE Force Main | 820 | L.F. | $13.00 | $10,660.00 | $21.00 | $17,220.00 | $100.00 | $82,000.00 | ||||
| $222,544.60 | $312,960.00 | $373,898.50 | |||||||||||