IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Hartwick riffle, Delhi lakebed | Date: 6/28/2012 | Project No. |
| Repair toe of riffle | County: | DELAWARE | Time: 11:00 a.m. | 12-03-28-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $35,000.00 | Contractor: | B & J Hauling & Excavation Inc. | Steger Construction Inc | Top Grade Excavating, Inc. | |||||||||
| Funding Source: 100% Marine Fuel Tax, | P.O. Box | 3297 Vine Rd | 971 9th Ave NW | ||||||||||
| Monticello IA 52310 | Dyersville IA 52040 | Farley IA 52046 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-480-1218 | 563-875-7876 | 563-744-3416 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $150.00 | $150.00 | $500.00 | $500.00 | $750.00 | $750.00 | ||||
| 2 | Revetment, Class 'E' Riprap | 640 | Tons | $17.35 | $11,104.00 | $20.60 | $13,184.00 | $21.60 | $13,824.00 | ||||
| $11,254.00 | $13,684.00 | $14,574.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $35,000.00 | Contractor: | Connolly Construction Inc | Lansing Brothers Construction Co. Inc. | McClain Excavating | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 18409 N Cascade Rd PO Box 68 | 101 E 1st St P.O. Box 36 | 660 Peosta Street PO Box 77 | ||||||||||
| Peosta IA 52068 | Luxemburg IA 52056 | Peosta IA 52068 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-876-3225 | 563-543-7360 | 563-556-2348 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,100.00 | $2,100.00 | $3,500.00 | $3,500.00 | $1,650.00 | $1,650.00 | ||||
| 2 | Revetment, Class 'E' Riprap | 640 | Tons | $19.55 | $12,512.00 | $22.00 | $14,080.00 | $30.00 | $19,200.00 | ||||
| $14,612.00 | $17,580.00 | $20,850.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $35,000.00 | Contractor: | CJ Moyna & Sons Inc | Taylor Construction Inc | Riehm Construction Company | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 24412 Hwy 13 | 7314 Columbus St PO Box 110 | 2340 - 9th St SW | ||||||||||
| Elkader IA 52043 | New Vienna IA 52065 | Waukon IA 52172 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-245-1442 | 563-921-2315 | 563-568-3314 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $1,000.00 | $1,000.00 | $26,300.00 | $26,300.00 | ||||
| 2 | Revetment, Class 'E' Riprap | 640 | Tons | $27.50 | $17,600.00 | $36.00 | $23,040.00 | $36.90 | $23,616.00 | ||||
| $21,100.00 | $24,040.00 | $49,916.00 | |||||||||||