IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Snyder Bend WMA  Date: 1/5/2012  Project No.  
  Water Supply Channel Excavation  County:   WOODBURY  Time: 3:00 p.m.  12-01-97-01

 

 
1
2
3
Estimated Cost: $69,750.00
Contractor: 
Lieber Construction Inc.L A Carlson Contracting IncRichards Construction Co Inc
Funding Source: 90% Federal-FEMA 1, 10% Other, 2024 - 120th St
PO Box 217
20984 C-43
2721 Sierra Ave
Lawton IA  51030Merrill IA  51038Sac City IA  50583
Plan Sets Requested: 0
Quantities
712-944-5459712-239-3195712-662-4421
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,500.00$3,500.00 
2Channel Excavation19900C.Y.$1.23$24,477.00 $2.20$43,780.00 $2.40$47,760.00 
      $24,977.00  $45,430.00  $51,260.00 
 
 
4
5
6
Estimated Cost: $69,750.00
Contractor: 
Central Builders4 B ConstructionBuford Dozing & Excavating Inc
Funding Source: 90% Federal-FEMA 1, 10% Other, 1002 Lincolnway
PO Box 9
33501 Hickory
29623 - 260th St
Woodbine IA  51579Sioux City IA  51108Bonaparte IA  52620
Plan Sets Requested: 0
Quantities
712-647-2600712-251-0806319-470-1492
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,958.00$1,958.00 $1,000.00$1,000.00 $2,000.00$2,000.00 
2Channel Excavation19900C.Y.$3.14$62,486.00 $3.85$76,615.00 $3.84$76,416.00 
      $64,444.00  $77,615.00  $78,416.00 
 



 