 Bids For:  Location:   Rice Lake State Park  Date: 6/21/2012  Project No.  
  CCC Shelter Renovation  County:   WINNEBAGO  Time: 11:00 am  12-02-95-02

 

 
1
2
3
Estimated Cost: $70,000.00
Contractor: 
Larson Contracting Central LLCMD Johnson Consulting Inc.Holland Contracting Corp
Funding Source: 100% I-JOBS 2, 508 W Main St
1102 Terrasol Lane
1400 S 4th St
Lake Mills IA  50450Kasota MN  56050Forest City IA  50436
Plan Sets Requested: 1
Quantities
641-592-5800507-469-0474641-585-2231
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Restoration of CCC Shelter1L.S.$49,660.00$49,660.00 $44,421.00$44,421.00 $90,000.00$90,000.00 
2Selective Demolition and removal of existing CCC structure1L.S.$6,817.00$6,817.00 $9,749.00$9,749.00 $8,200.00$8,200.00 
3CXT Cascadian Pit-vault and all related items1L.S.$22,875.00$22,875.00 $25,300.00$25,300.00 $26,000.00$26,000.00 
4CRUSHED ROCK FOR PATHING13Tons$23.00$299.00 $27.308$355.00 $76.923$1,000.00 
      $79,651.00  $79,825.00  $125,200.00 
 



 