IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Backbone State Park | Date: 6/21/2012 | Project No. |
| CCC Cabin Renovation | County: | DELAWARE | Time: 11:00 AM | 12-03-28-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $1,000,000.00 | Contractor: | Jonas Raber Construction LLC | Matt Construction Inc | Tricon Construction | |||||||||
| Funding Source: 100% REAP Land Management, | 1296 - 145th St | 203 Y Ave | 2245 Kerper Blvd Ste #2 | ||||||||||
| Fairbank IA 50629 | Sumner IA 50674 | Dubuque IA 52001 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 319-850-8676 | 563-578-8418 | 563-588-9516 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clear & Grub | 79 | Units | $30.38 | $2,399.996 | $23.00 | $1,817.00 | $100.00 | $7,900.00 | ||||
| 2 | Excavation, Class 10, Roadway and Borrow | 790 | C.Y. | $19.873 | $15,699.986 | $10.00 | $7,900.00 | $8.00 | $6,320.00 | ||||
| 3 | Rock Excavation | 100 | C.Y. | $40.00 | $4,000.00 | $50.00 | $5,000.00 | $50.00 | $5,000.00 | ||||
| 4 | Topsoil, Strip, Salvage & Spread | 677 | C.Y. | $4.874 | $3,299.969 | $10.00 | $6,770.00 | $4.00 | $2,708.00 | ||||
| 5 | Mulch, Bonded Fiber Matrix | 0.8 | Acres | $4,375.00 | $3,500.00 | $5,000.00 | $4,000.00 | $2,750.00 | $2,200.00 | ||||
| 6 | Seed and Fertilize (rural) | 0.8 | Acres | $2,906.25 | $2,325.00 | $3,000.00 | $2,400.00 | $5,500.00 | $4,400.00 | ||||
| 7 | Silt Fence | 1512 | L.F. | $0.694 | $1,049.933 | $3.00 | $4,536.00 | $3.50 | $5,292.00 | ||||
| 8 | Granular Subbase Material | 290 | Tons | $24.966 | $7,239.995 | $18.00 | $5,220.00 | $17.00 | $4,930.00 | ||||
| 9 | Sidewalk, PCC, 5" | 599 | S.Y. | $12.609 | $7,552.971 | $40.00 | $23,960.00 | $36.00 | $21,564.00 | ||||
| 10 | Portland Cement Concrete Pavement, 6" | 452 | S.Y. | $15.535 | $7,022.001 | $45.00 | $20,340.00 | $45.00 | $20,340.00 | ||||
| 11 | Sawcut Existing Asphalt Pavement Edge | 187 | L.F. | $11.497 | $2,149.995 | $5.00 | $935.00 | $10.00 | $1,870.00 | ||||
| 12 | Removal of Sidewalk | 456 | S.Y. | $25.00 | $11,400.00 | $9.00 | $4,104.00 | $9.00 | $4,104.00 | ||||
| 13 | Remove Underground Concrete Support Piers | 96 | Each | $89.583 | $8,599.997 | $20.00 | $1,920.00 | $75.00 | $7,200.00 | ||||
| 14 | Water Service Line, 1" PVC | 346 | L.F. | $7.185 | $2,486.01 | $20.00 | $6,920.00 | $20.00 | $6,920.00 | ||||
| 15 | Curb Stop and Valve Box | 8 | Each | $345.00 | $2,760.00 | $180.00 | $1,440.00 | $400.00 | $3,200.00 | ||||
| 16 | PVC Sanitary Sewer Lateral Pipe, 4" | 439 | L.F. | $7.973 | $3,500.015 | $22.00 | $9,658.00 | $25.00 | $10,975.00 | ||||
| 17 | Sanitary Sewer Cleanout | 7 | Each | $267.857 | $1,875.00 | $115.00 | $805.00 | $200.00 | $1,400.00 | ||||
| 18 | Mobilization | 1 | L.S. | $1,250.00 | $1,250.00 | $15,000.00 | $15,000.00 | $25,000.00 | $25,000.00 | ||||
| 19 | Painted Pavement Mark, Waterbourne / Solvent | 1 | L.S. | $1,800.00 | $1,800.00 | $1,000.00 | $1,000.00 | $350.00 | $350.00 | ||||
| 20 | ADA Parking Sign | 2 | Each | $850.00 | $1,700.00 | $100.00 | $200.00 | $200.00 | $400.00 | ||||
| 21 | Tire Stop | 12 | Each | $220.833 | $2,650.00 | $100.00 | $1,200.00 | $75.00 | $900.00 | ||||
| 22 | Removal / Selective Demolition of Eight (8) Cabins | 1 | L.S. | $217,430.00 | $217,430.00 | $50,000.00 | $50,000.00 | $52,900.00 | $52,900.00 | ||||
| 23 | Complete Renovation of Eight (8) Cabins | 1 | L.S. | $472,200.00 | $472,200.00 | $640,000.00 | $640,000.00 | $952,127.00 | $952,127.00 | ||||
| $783,890.867 | $815,125.00 | $1,148,000.00 | |||||||||||
10/14/2026