| Bids For: | Location: | George Wyth | Date: 3/15/2012 | Project No. |
| Wyth boat ramp lift station | County: | BLACK HAWK | Time: 3:00 p.m. | 12-03-07-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Matt Construction Inc | |||||||||||
| Funding Source: 100% Health and Safety Account, | 203 Y Ave | ||||||||||||
| Sumner IA 50674 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-578-8418 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 2 | Remove Existing Lift Station Pump & Disconnect From Control Panel | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
| 3 | Remove & Dispose Existing Steel Lift Station Basin | 1 | L.S. | $1,300.00 | $1,300.00 | $0.00 | $0.00 | ||||||
| 4 | Acquire & Install New Fiberglass Lift Station Basin | 1 | L.S. | $8,800.00 | $8,800.00 | $0.00 | $0.00 | ||||||
| 5 | Install Existing Lift Station Pump, Reconnect To Force Main & Electric Control Panel | 1 | L.S. | $4,000.00 | $4,000.00 | $0.00 | $0.00 | ||||||
| $19,100.00 | $0.00 | $0.00 | |||||||||||