 Bids For:  Location:   Clear Lake State Park  Date: 12/15/2011  Project No.  
  Campground Improvements & Sanitary Sewer Rehabilitation  County:   CERRO GORDO  Time: 3:00 p.m.  10-03-17-09

 

 
1
2
3
Estimated Cost:
Contractor: 
Dean Snyder Construction Co.GM Contracting INCMunicipal Pipe Tool Co
Funding Source: 100% Health and Safety Account, 913 N 14th St
19810 515 Ave
515 5th St
PO Box 398
Clearlake IA  50428Lake Crystal MN  56055Hudson IA  50643
Plan Sets Requested: 8
Quantities
641-357-2283507-726-6433(319) 988-4505
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$14,202.00$14,202.00 $11,250.00$11,250.00 $30,000.00$30,000.00 
2Remove Existing Dump Station1Each$1.05$1.05 $3,500.00$3,500.00 $2,122.00$2,122.00 
3Remove Existing Electric Posts5Each$11.00$55.00 $150.22$751.10 $278.00$1,390.00 
4Remove Existing Yard Hydrants1Each$1.00$1.00 $171.17$171.17 $267.00$267.00 
5Remove Tree1Each$368.00$368.00 $392.38$392.38 $1,162.00$1,162.00 
6Clear & Grub1L.S.$1,575.00$1,575.00 $750.00$750.00 $1,742.00$1,742.00 
7Sanitary Sewer Point Repairs2Each$1,050.00$2,100.00 $1,050.00$2,100.00 $655.20$1,310.40 
86" Sanitary Sewer Lining906L.F.$35.70$32,344.20 $46.00$41,676.00 $34.00$30,804.00 
9Seal Lined Pipe Ends6Each$525.00$3,150.00 $350.00$2,100.00 $500.00$3,000.00 
10Lined Service Lateral Reconnections1Each$158.00$158.00 $100.00$100.00 $150.00$150.00 
11Air Test Service Lateral Connection1Each$1,313.00$1,313.00 $300.00$300.00 $1,250.00$1,250.00 
12Chemical Grout Service Laterals1Each$53.00$53.00 $56.75$56.75 $50.00$50.00 
13Replace Manhole Cover & Frame1Each$1,575.00$1,575.00 $1,684.19$1,684.19 $1,106.00$1,106.00 
14Reconstruct Manhole Chimney3Each$1,575.00$4,725.00 $1,534.87$4,604.61 $929.00$2,787.00 
15Construct Sanitary Dump Station2Each$4,900.00$9,800.00 $23,250.00$46,500.00 $24,333.00$48,666.00 
16Sanitary Service Lines (4")230L.F.$21.00$4,830.00 $27.78$6,389.40 $71.00$16,330.00 
17RV Sanitary Sewer Connection8Each$525.00$4,200.00 $852.99$6,823.92 $1,786.00$14,288.00 
18Water Main (2")415L.F.$21.00$8,715.00 $26.71$11,084.65 $32.00$13,280.00 
19Water Service Connections11Each$262.50$2,887.50 $588.66$6,475.26 $919.00$10,109.00 
20Water Service Line125L.F.$19.00$2,375.00 $22.57$2,821.25 $42.00$5,250.00 
21Service Hydrants (Yard Hydrants)9Each$1,455.00$13,095.00 $2,091.81$18,826.29 $1,487.00$13,383.00 
22Campsite Electrical Modifications1L.S.$27,877.00$27,877.00 $27,369.63$27,369.63 $40,250.00$40,250.00 
23Granular Surfacing & Base72C.Y.$31.50$2,268.00 $28.75$2,070.00 $67.00$4,824.00 
24HMA Pavement165S.Y.$47.25$7,796.25 $49.33$8,139.45 $113.00$18,645.00 
25PCC Pavement52C.Y.$252.00$13,104.00 $395.00$20,540.00 $83.00$4,316.00 
26Site Restoration1L.S.$7,560.00$7,560.00 $12,502.00$12,502.00 $9,184.00$9,184.00 
      $166,128.00  $238,978.05  $275,665.40 
 



 