 Bids For:  Location:   Lake Wapello State Park  Date: 6/21/2012  Project No.  
  restore CCC entrance portal  County:   DAVIS  Time: 11:00 AM  12-05-26-02

 

 
1
2
3
Estimated Cost: $40,000.00
Contractor: 
HANSON CONSTRUCTION LLC
Funding Source: 100% Health and Safety Account, PO Box 614


Clear Lake IA  50428    
Plan Sets Requested: 2
Quantities
641-357-8171
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1DEMOLITION AND REMOVAL OF EXISTING ENTRY PORTAL1L.S.$3,500.00$3,500.00 $0.00 $0.00 
2RECONSTRUCTION OF NEW ENTRY PORTAL1L.S.$45,000.00$45,000.00 $0.00 $0.00 
3GRADING AND EARTHWORK AROUND NEW PORTAL1L.S.$3,500.00$3,500.00 $0.00 $0.00 
      $52,000.00  $0.00  $0.00 
 



 