IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lost Island Lake | Date: 8/15/2013 | Project No. |
| Lost Island Lake Electric Fish Barrier | County: | PALO ALTO | Time: 11:00 a.m. | 12-01-74-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $209,215.00 | Contractor: | Midstates Builders Inc | Christensen Construction & Design Company | ||||||||||
| Funding Source: 75% Lake Restoration, 25% Other, | 520 S Grand PO Box 5027 | 821 S 28th St | |||||||||||
| Spencer IA 51301 | Estherville IA 51334 | ||||||||||||
| Plan Sets Requested: 2 | Quantities | (712) 262-2227 | 712-362-7755 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $66,950.00 | $66,950.00 | $0.00 | |||||
| 2 | Demobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $13.00 | $13.00 | $0.00 | |||||
| 3 | Dewatering | 1 | L.S. | $1,200.00 | $1,200.00 | $1,430.00 | $1,430.00 | $0.00 | |||||
| 4 | Reinforced 6" PCC Building Slab | 3.4 | C.Y. | $700.00 | $2,380.00 | $688.23 | $2,339.982 | $0.00 | |||||
| 5 | Anchor Bolts, 5/8" dia x 8" long | 25 | Each | $15.00 | $375.00 | $6.50 | $162.50 | $0.00 | |||||
| 6 | Steel Plate, Strctural, for electrodes, 3/4" thick, shop fabricated include fastners | 15 | S.F. | $80.00 | $1,200.00 | $533.00 | $7,995.00 | $0.00 | |||||
| 7 | 1/2" Steel Wire Rope, IPS, IWRC | 130 | L.F. | $5.70 | $741.00 | $25.00 | $3,250.00 | $0.00 | |||||
| 8 | Schedule 40 Conduit to Barrier | 125 | L.F. | $6.00 | $750.00 | $32.50 | $4,062.50 | $0.00 | |||||
| 9 | Fiberglass castings, square tube, 3" x 3" x 1/4" thick | 24 | L.F. | $56.36 | $1,352.64 | $183.08 | $4,393.92 | $0.00 | |||||
| 10 | Steel Sign Posts, 4lb Galvanized U-post, 10' long | 6 | Each | $180.00 | $1,080.00 | $115.92 | $695.52 | $0.00 | |||||
| 11 | #8 AWG 2000 Volt Locomotive Cable | 780 | L.F. | $1.75 | $1,365.00 | $4.23 | $3,299.40 | $0.00 | |||||
| 12 | Power/Communication Wiring | 125 | L.F. | $15.10 | $1,887.50 | $15.60 | $1,950.00 | $0.00 | |||||
| 13 | #8 AWG Ground Wire, copper wire, bare stranded | 230 | L.F. | $0.93 | $213.90 | $12.16 | $2,796.80 | $0.00 | |||||
| 14 | Tree Removal, Clear and Grub Site | 1 | L.S. | $2,000.00 | $2,000.00 | $650.00 | $650.00 | $0.00 | |||||
| 15 | Excavating, chain trencher, utility trench, 8" wide, 24" deep, backfill by hand, includes compaction | 416 | L.F. | $7.00 | $2,912.00 | $1.41 | $586.56 | $0.00 | |||||
| 16 | Fill, gravel fill, Compacted for Building Pad | 42 | Tons | $48.00 | $2,016.00 | $21.67 | $910.14 | $0.00 | |||||
| 17 | Synthetic Erosion Control, silt fence, 3' high | 250 | L.F. | $8.00 | $2,000.00 | $3.90 | $975.00 | $0.00 | |||||
| 18 | Fence, Chain Link Industrial, double swing gates, 8' high, 12' opening, includes excavation, posts in concrete, & hardware | 1 | Each | $2,000.00 | $2,000.00 | $2,080.00 | $2,080.00 | $0.00 | |||||
| 19 | Steel Fence Posts, 4" OD Galvanized for steel cable assembly, 10'-0" long set in concrete | 10 | Each | $100.00 | $1,000.00 | $221.00 | $2,210.00 | $0.00 | |||||
| 20 | Fence, Chain Link Industrial, galvanized steel, 6 ga wire, 2-1/2" posts @ 10' OC, 8' high, includes excavation, posts in concete | 93 | L.F. | $54.00 | $5,022.00 | $52.35 | $4,868.55 | $0.00 | |||||
| 21 | Fence, Chain Link Industrial, galvanized steel gate, 8' high, 3' opening, includes excavation, posts in concrete, & hardware | 1 | Each | $1,103.00 | $1,103.00 | $721.50 | $721.50 | $0.00 | |||||
| 22 | Supply and install control building including all fixtures | 1 | L.S. | $48,042.00 | $48,042.00 | $34,515.00 | $34,515.00 | $0.00 | |||||
| 23 | Manufacture, Supply and deliver SRI fish barrier equipment, includes installation if not listed as a seperate bid item | 1 | L.S. | $130,772.00 | $130,772.00 | $75,011.00 | $75,011.00 | $0.00 | |||||
| 24 | Schedule 80 Conduit for power and communication wiring | 190 | L.F. | $12.00 | $2,280.00 | $41.60 | $7,904.00 | $0.00 | |||||
| 25 | Kohler 8.5RES Generator | 1 | L.S. | $7,233.00 | $7,233.00 | $16,120.00 | $16,120.00 | $0.00 | |||||
| 26 | 500 gal Propane Tank | 1 | L.S. | $2,500.00 | $2,500.00 | $3,250.00 | $3,250.00 | $0.00 | |||||
| 27 | 3'x5' Informational Kiosk | 1 | L.S. | $350.00 | $350.00 | $1,300.00 | $1,300.00 | $0.00 | |||||
| $228,775.04 | $250,440.372 | $0.00 | |||||||||||
12/17/2025