 Bids For:  Location:   White Fox Creek Oxbow  Date: 12/1/2011  Project No.  
  Oxbow restoration  County:   HAMILTON  Time: 3:00 p.m.  12-02-40-02

 

 
1
2
3
Estimated Cost: $15,000.00
Contractor: 
J N Peterson & Sons Inc dba/Peterson ConstructionStony Creek Landscapes
Funding Source: 50% F&W Trust-Fish Habitat Stamp, 50% Other, 1929 W 2nd St
404 E Second St

Webster City IA  50595 Webster City IA  50595  
Plan Sets Requested: 0
Quantities
515-832-1216515-832-1281
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Oxbow Restoration Complete1L.S.$19,300.00$19,300.00 $28,550.00$28,550.00 $0.00 
      $19,300.00  $28,550.00  $0.00 
 



 