IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Spirit Lake Hatchery  Date: 9/15/2011  Project No.  
  roof replacement, wall repair  County:   DICKINSON  Time: 11:00 a.m.  12-01-30-05

 

 
1
2
3
Estimated Cost: $275,000.00
Contractor: 
Modern Builders, Inc.Sande Construction And Supply Company Inc
Funding Source: 70% Federal-DJ, 30% REAP Land Management, 202 Main St
1111 16th Ave N
Box 368

Janesville IA  50674Humboldt IA  50548  
Plan Sets Requested: 5
Quantities
(319) 987-2911515-332-2021
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1NEW STANDING SEAM STEEL ROOF W/ STRUCTURE1L.S.$216,600.00$216,600.00 $287,680.00$287,680.00 $0.00 
2STEEL SIDING1L.S.$1,900.00$1,900.00 $2,000.00$2,000.00 $0.00 
3BRICK DEMOLITION1L.S.$38,400.00$38,400.00 $42,000.00$42,000.00 $0.00 
      $256,900.00  $331,680.00  $0.00 
 



 

10/13/2026