IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Spirit Lake Hatchery | Date: 9/15/2011 | Project No. |
| roof replacement, wall repair | County: | DICKINSON | Time: 11:00 a.m. | 12-01-30-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $275,000.00 | Contractor: | Modern Builders, Inc. | Sande Construction And Supply Company Inc | ||||||||||
| Funding Source: 70% Federal-DJ, 30% REAP Land Management, | 202 Main St | 1111 16th Ave N Box 368 | |||||||||||
| Janesville IA 50674 | Humboldt IA 50548 | ||||||||||||
| Plan Sets Requested: 5 | Quantities | (319) 987-2911 | 515-332-2021 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | NEW STANDING SEAM STEEL ROOF W/ STRUCTURE | 1 | L.S. | $216,600.00 | $216,600.00 | $287,680.00 | $287,680.00 | $0.00 | |||||
| 2 | STEEL SIDING | 1 | L.S. | $1,900.00 | $1,900.00 | $2,000.00 | $2,000.00 | $0.00 | |||||
| 3 | BRICK DEMOLITION | 1 | L.S. | $38,400.00 | $38,400.00 | $42,000.00 | $42,000.00 | $0.00 | |||||
| $256,900.00 | $331,680.00 | $0.00 | |||||||||||
10/13/2026